Home / Browse projects / Riverdale Residences-I

Completed No litigation declared Residential / Group Housing project

Riverdale Residences-I

By Duville Estates Private Limited

RG-MH-12093 · RERA P52100004692 · Last updated on MahaRERA portal: 16 Jul 2025

Source: official MahaRERA filing

Red flags

  • 30 complaints at MahaRERA
  • Completion date moved by 16 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Feb 2024Possession promisedregistration recorded completed
24 of 33Construction stages doneacross 3 buildings; furthest along: Basement (if any), 0%
30Complaints at MahaRERAon this registration
Jump to the 143 documents Report an error

Riverdale Residences-I is a Residential / Group Housing project by Duville Estates Private Limited in KHARADI, 411014, registered with MahaRERA as P52100004692 on 9 Aug 2017. The registration is recorded completed; possession was promised by 26 Feb 2024. The completion date has moved by 16 months from the original filing. 30 complaints are on record with the regulator.

At a glance

Project

  • NameRiverdale Residences-I
  • TypeResidential / Group Housing
  • Location
    • SHIVANE ROAD
    • KHARADI
    • 411014
  • Pincode411014
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100004692
  • ReraGenie IDRG-MH-12093

Builder

  • NameDuville Estates Private Limited
  • Entity typeCompany
  • GSTIN27AACCC8436BIZW
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • DirectorTushad Behram Dubash
  • Other registrations7 more →
  • Completed4 of 8
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2017First promiseOct 2022Revised toFeb 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on9 Aug 2017
  • Promised completion26 Feb 2024
  • Revised completionRevised to 26 Feb 2024 (originally 30 Oct 2022)
  • Buildings3 building records
  • Documents filed143 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
E1NA280000
E2NA280000
E3NA280000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 16 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Basement (if any), at 0%.

E173%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
E273%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
E373%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 16 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed582

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots582
Closed/Covered552
Open Space30
BuildingClosed/CoveredOpen SpaceTotal
E118410194
E218410194
E318410194

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,451 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI45563.07
Proposed, not sanctioned25,668 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchManeckji Wadia Building, Ground Floor , Nanik Motwani Marg, Fort, Mumbai - 400023 Maharashtra

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPinnac AECL Consultancy Pvt Ltd
EngineerJW Consultants LLP
PartnerRole in project
Duville Estates Private Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100012837Oct 2022 → Oct 2023

Reason as filed by the promoterDue to Covid-19 Pandemic, project work got hampered due to inadequate manpower and difficulty in re-mobilisation of resources. As a result there is a delay in completion of project within stipulated timelines. We humbly request you to grant an extension for a period of 1 year.

EXT52100024988Oct 2022 → Feb 2024

Reason as filed by the promoterDue to Covid-19 pandemic the work in the said Project has got delayed due to inadequate manpower and difficulty in re-mobilisation of resources. We had applied for extension of project registration under Section 6 of the Real Estates Regulation Act, 2016 (the ‘Act’) and the validity of the said Project had been extended by MahaRERA till 30th October, 2023. We have completed the construction of the said Project and possession of flats has already been delivered to the flat owners. Since the final Occupancy Certificate of date 7th February, 2024 has been received after expiry of validity of the

Litigation declared4

CaseCourtStatus
1774/2015Court of Civil Judge Senior Division PuneDismissed by Honble District and Sessions Court Pune
226/2015Court of Civil Judge Senior Division PunePending
597/2015Court of Civil Judge Senior Division PunePending
221/2014Sub Divisional Officer PuneDISMISSED

Complaints filed with MahaRERA30

Case no.ComplainantRespondentFiled
CC005000000085486Duville estates through Tushad Behram DubhashSeema Mohammad Bilal Hasan27/04/2021
CC005000000085632Duville estates through authorised signatory Shrinivas KulkarniMrs Manisha Nikhil Nikam06/07/2021
CC005000000177815Lokesh DeshmukhTushad Behram Dubash02/04/2023
CC005000000157315Nandansing Jagatsing PatilTushar Dubhash04/07/2022
CC005000000177794Parth Ashok AroraTushad Behram Dubash13/11/2022
CC005000000177790Atul AgarwalDuville Estate11/11/2022
CC005000000177795Sandeep Prakash PatilDuville Estate Pvt Ltd, Mr.Srinivas Kulkarni,Mrs. Priyanka Nandurkar13/11/2022
CC005000000177827Abhishek ChaudhariDuvIlle Riverdale Residences I Management20/11/2022
CC005000000177917Nitin KaleTushad Dubash25/02/2023
CC005000000208237Abhinav GuptaDuville Estates Private Ltd05/02/2023
CC005000000208239Mithun Satish VakilDUVILLE ESTATES PRIVATE LIMITED14/02/2023
CC005000000208240SAMIR KIRANRAO DHOKDuville Estates Private Limited21/02/2023
CC005000000208259Kaminee BalkawadeDuville Estates Private Limited10/02/2023
CC005000000228340Prashant AgarwalDuville Estates Pvt. Ltd.21/02/2023
CC005000000238558Akshay MehtaRiverdale Residencies - 126/03/2023
CC005000000228348Vicky Gobindram BachaniDUVILLE ESTATES PRIVATE LIMITED24/02/2023
CC005000000228394Sukhpreet Singh Jagtar Singh GuraiDuville Estate Pvt Ltd25/02/2023
CC005000000228396Upasana GuptaDuville Estate Pvt Ltd26/02/2023
CC005000000228444Charu ChotraniDUVILLE ESTATES PVT LTD.05/03/2023
CC005000000228445Mayur AgrawalDuville Estates11/03/2023
CC005000000228462KAVITA GOBIND AIDASANIDUVILLE ESTATES PVT LTD06/03/2023
CC005000000228467Vivek Dinkar SagaleDuville Estates PVT LTD07/03/2023
CC005000000238550Rajesh ShahDuville Estates Pvt Ltd25/03/2023
CC005000000238567Poornima IyengarDuville Estates Pvt Ltd27/03/2023
CC005000000238555Sachin Gangadhar ZambreTushad Behram Dubash26/03/2023
CC005000000238554Shradha SelarkaDuville26/03/2023
CC005000000238557Hitu Kajal KajalDuville Estates Pvt Ltd.26/03/2023
CC005000000238630Manasi Suraj GhemadDuville Estates Pvt Ltd02/04/2023
CC005000000238631MIHIR DAVDADuville Estates Private Limited03/04/2023
CC12602744Duville Estates Private LimitedRASHMI TIWARI11/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Apr 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Apr 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 30 Apr 2024

Documents filed143

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 143 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: Form-3 - RRI - Dec2024.pdf16 Jul 2025
Declaration in FORM BFile: rri form B.pdf8 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1 Form 2A - RR-I - Jun 2022 - Signed.pdf2 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2 Form 2A - RR-I - Sep 2022 - Signed.pdf2 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 3 Form 2A - RR-I - Dec 2022 - Signed.pdf2 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 4 Form 2A - RR-I - Mar 2023 - Counter Signed.pdf2 Apr 2025
Certificates of CA (Form 3)File: RRI Form 3 Dec24.pdf21 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 RRI.pdf21 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A RRI.pdf21 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RRI June 2024.pdf18 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RRI Sept 2024.pdf18 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RRI June 2024.pdf18 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RRI Sept 2024.pdf18 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A)File: 10 Form 2A - RR-1 - Sep 2024.pdf14 Nov 2024
Certificates of CA (Form 3)File: Form-3 - RRI- Jun 2024.pdf12 Nov 2024
Disclosure of sold/ booked inventoryFile: RRI.pdf12 Nov 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 - Riverdale Residences-I - P52100004692.pdf6 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - RRI - FY 2023-24.pdf10 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- RR.pdf7 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RR Form 2.pdf7 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A)File: RR Form 2A.pdf7 Aug 2024
Disclosure of sold/ booked inventoryFile: RRI Inv.pdf7 Aug 2024
Certificates of CA (Form 3)File: Form 3 RRI.pdf29 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RRI Form 1.pdf9 May 2024
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A RRI.pdf9 May 2024
Disclosure of sold/ booked inventoryFile: Residences I inv.pdf2 May 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC 0748 01 11 2021.pdf30 Apr 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC 0365 15 07 2022.pdf30 Apr 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC 1173 26 02 2024.pdf30 Apr 2024
Disclosure of sold/ booked inventoryFile: RR1 Dec-2023 Inventory.pdf4 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - RR-I - Dec 2023.pdf1 Mar 2024
Certificates of CA (Form 3)File: Form-3 - RRI - Dec 2023.pdf1 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Plot E - Form 1 - 31 Dec 2023.pdf12 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 6 Form 2 - RR-I - Sep 2023.pdf16 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A)File: 6 Form 2A - RR-1 - Sep 2023.pdf16 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - RR-I - Sep 2023.pdf2 Nov 2023
Disclosure of sold/ booked inventoryFile: 7 Inventory Data - RR-I - Sep 2023.pdf2 Nov 2023
Certificates of CA (Form 3)File: Form-3 - RRI- Sep 2023.pdf31 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - RRI - FY 2022-23.pdf30 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - RR-1 - Jun 2023.pdf8 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A)File: 5 Form 2A - RR-1 - Jun 2023.pdf8 Aug 2023
Disclosure of sold/ booked inventoryFile: 6 Inventory Details - June 2023 - Optimized.pdf27 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 5 Form 2- RR-I - Jun 2023.pdf21 Jul 2023
Certificates of CA (Form 3)File: Form 3 - RRI - June 2023.pdf21 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - RR-I - Mar 2023 - Counter Signed.pdf21 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4 Form 2 - RR-I - Mar 2023 - Counter Signed.pdf21 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A)File: 4 Form 2A - RR-I - Mar 2023 - Counter Signed.pdf21 Apr 2023
Disclosure of sold/ booked inventoryFile: 5 Inventory Details - 31032023.pdf21 Apr 2023
Certificates of CA (Form 3)File: Form 3 - RRI - Mar 2023.pdf21 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - RR-I - Dec 2022.pdf18 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - RR-I - Dec 2022 - signed.pdf18 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A - RR-I - Dec 2022 - Signed.pdf18 Jan 2023
Certificates of CA (Form 3)File: Form 3 - RR - Dec 2022.pdf13 Jan 2023
Disclosure of sold/ booked inventoryFile: Inventory Details - RR I - 31122022.pdf12 Jan 2023
Certificates of CA (Form 3)File: Form 3 - RR - Sep 2022.pdf16 Nov 2022
Certificates of CA (Form 3)File: Form 3 - RR - Jun 2022.pdf16 Nov 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - RR - 30062022 - Signed.pdf9 Nov 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - RR - 30092022 - Signed.pdf9 Nov 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - RR-I - 30062022 - Signed.pdf9 Nov 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - RR-I - 30092022 - Signed.pdf9 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A - RR-I - 30602022 - Signed.pdf9 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A - RR-I - 30092022 - Signed.pdf9 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - RR-I - 30062022.pdf9 Nov 2022
Disclosure of sold/ booked inventoryFile: Inventory Details - 30062022.pdf6 Nov 2022
Disclosure of sold/ booked inventoryFile: Inventory Details - 30092022.pdf6 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Plot E - RRI.pdf30 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - RR - 31032022 - Optimsed.pdf16 Jun 2022
Certificates of CA (Form 3)File: Form 3 - Riverdale Residences I - Optimized.pdf16 Jun 2022
Disclosure of sold/ booked inventoryFile: Inventory Details - 31032022-compressed.pdf8 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Riverdale - Residences.pdf29 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Riverdale - Residences.pdf29 Dec 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: RR.pdf22 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Plot E.pdf10 Oct 2021
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory E1 2 3.pdf9 Oct 2021
Declaration about Commencement CertificateFile: Declaration About Commencement Certificate Plot E.pdf5 Oct 2021
OtherFile: Legal.pdf26 Feb 2021
Engineers Certificate on Quality Assurance (Form 2A)File: Plot - E From-2A.PDF29 Oct 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Riverdale-Residences.pdf13 Oct 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - RR1.pdf13 Oct 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Duville Plot -E_compressed.pdf13 Nov 2019

Keep Riverdale Residences-I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KHARADI

2 kmRiverdale Residences-ICompleted 53Lapsed / revoked 30Other 40Dot size: filed unitsN

Filed coordinates, straight-line distance. 123 registered projects within 2 km.

Builder: Duville Estates Private Limited

Duville Estates Private Limited has 8 registrations on MahaRERA, including Riverdale Heights and Riverdale Residences-I. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Litigation is declared on 4 of its registrations. Read the full track record.

Frequently asked questions

What are my rights if Riverdale Residences-I is delayed beyond 26 Feb 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Riverdale Residences-I?

The registered promoter entity is Duville Estates Private Limited, a company as per the filing. Its GSTIN 27AACCC8436BIZW can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Riverdale Residences-I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Riverdale Residences-I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Riverdale Residences-I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Riverdale Residences-I?

The professionals named in the filing: Architect: Pinnac AECL Consultancy Pvt Ltd; Engineer: JW Consultants LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Riverdale Residences-I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Riverdale Residences-I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Riverdale Residences-I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.