Riverdale Residences-I
By Duville Estates Private Limited
RG-MH-12093 · RERA P52100004692 · Last updated on MahaRERA portal: 16 Jul 2025
Source: official MahaRERA filing
Red flags
- 30 complaints at MahaRERA
- Completion date moved by 16 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Riverdale Residences-I is a Residential / Group Housing project by Duville Estates Private Limited in KHARADI, 411014, registered with MahaRERA as P52100004692 on 9 Aug 2017. The registration is recorded completed; possession was promised by 26 Feb 2024. The completion date has moved by 16 months from the original filing. 30 complaints are on record with the regulator.
At a glance
Project
- NameRiverdale Residences-I
- TypeResidential / Group Housing
- Location
- SHIVANE ROAD
- KHARADI
- 411014
- Pincode411014
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100004692
- ReraGenie IDRG-MH-12093
Builder
- NameDuville Estates Private Limited
- Entity typeCompany
- GSTIN27AACCC8436BIZW
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- DirectorTushad Behram Dubash
- Other registrations7 more →
- Completed4 of 8
- No longer live3 lapsed, de-registered or revoked
- Declared earlier projects2 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on9 Aug 2017
- Promised completion26 Feb 2024
- Revised completionRevised to 26 Feb 2024 (originally 30 Oct 2022)
- Buildings3 building records
- Documents filed143 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| E1 | NA | 28 | 0 | 0 | 0 | 0 |
| E2 | NA | 28 | 0 | 0 | 0 | 0 |
| E3 | NA | 28 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 16 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
24 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Basement (if any), at 0%.
E173%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
E273%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
E373%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 16 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed582
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| E1 | 184 | 10 | 194 |
| E2 | 184 | 10 | 194 |
| E3 | 184 | 10 | 194 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Pinnac AECL Consultancy Pvt Ltd |
| Engineer | JW Consultants LLP |
| Partner | Role in project |
|---|---|
| Duville Estates Private Limited | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to Covid-19 Pandemic, project work got hampered due to inadequate manpower and difficulty in re-mobilisation of resources. As a result there is a delay in completion of project within stipulated timelines. We humbly request you to grant an extension for a period of 1 year.
Reason as filed by the promoterDue to Covid-19 pandemic the work in the said Project has got delayed due to inadequate manpower and difficulty in re-mobilisation of resources. We had applied for extension of project registration under Section 6 of the Real Estates Regulation Act, 2016 (the ‘Act’) and the validity of the said Project had been extended by MahaRERA till 30th October, 2023. We have completed the construction of the said Project and possession of flats has already been delivered to the flat owners. Since the final Occupancy Certificate of date 7th February, 2024 has been received after expiry of validity of the
Litigation declared4
| Case | Court | Status |
|---|---|---|
| 1774/2015 | Court of Civil Judge Senior Division Pune | Dismissed by Honble District and Sessions Court Pune |
| 226/2015 | Court of Civil Judge Senior Division Pune | Pending |
| 597/2015 | Court of Civil Judge Senior Division Pune | Pending |
| 221/2014 | Sub Divisional Officer Pune | DISMISSED |
Complaints filed with MahaRERA30
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000085486 | Duville estates through Tushad Behram Dubhash | Seema Mohammad Bilal Hasan | 27/04/2021 |
| CC005000000085632 | Duville estates through authorised signatory Shrinivas Kulkarni | Mrs Manisha Nikhil Nikam | 06/07/2021 |
| CC005000000177815 | Lokesh Deshmukh | Tushad Behram Dubash | 02/04/2023 |
| CC005000000157315 | Nandansing Jagatsing Patil | Tushar Dubhash | 04/07/2022 |
| CC005000000177794 | Parth Ashok Arora | Tushad Behram Dubash | 13/11/2022 |
| CC005000000177790 | Atul Agarwal | Duville Estate | 11/11/2022 |
| CC005000000177795 | Sandeep Prakash Patil | Duville Estate Pvt Ltd, Mr.Srinivas Kulkarni,Mrs. Priyanka Nandurkar | 13/11/2022 |
| CC005000000177827 | Abhishek Chaudhari | DuvIlle Riverdale Residences I Management | 20/11/2022 |
| CC005000000177917 | Nitin Kale | Tushad Dubash | 25/02/2023 |
| CC005000000208237 | Abhinav Gupta | Duville Estates Private Ltd | 05/02/2023 |
| CC005000000208239 | Mithun Satish Vakil | DUVILLE ESTATES PRIVATE LIMITED | 14/02/2023 |
| CC005000000208240 | SAMIR KIRANRAO DHOK | Duville Estates Private Limited | 21/02/2023 |
| CC005000000208259 | Kaminee Balkawade | Duville Estates Private Limited | 10/02/2023 |
| CC005000000228340 | Prashant Agarwal | Duville Estates Pvt. Ltd. | 21/02/2023 |
| CC005000000238558 | Akshay Mehta | Riverdale Residencies - 1 | 26/03/2023 |
| CC005000000228348 | Vicky Gobindram Bachani | DUVILLE ESTATES PRIVATE LIMITED | 24/02/2023 |
| CC005000000228394 | Sukhpreet Singh Jagtar Singh Gurai | Duville Estate Pvt Ltd | 25/02/2023 |
| CC005000000228396 | Upasana Gupta | Duville Estate Pvt Ltd | 26/02/2023 |
| CC005000000228444 | Charu Chotrani | DUVILLE ESTATES PVT LTD. | 05/03/2023 |
| CC005000000228445 | Mayur Agrawal | Duville Estates | 11/03/2023 |
| CC005000000228462 | KAVITA GOBIND AIDASANI | DUVILLE ESTATES PVT LTD | 06/03/2023 |
| CC005000000228467 | Vivek Dinkar Sagale | Duville Estates PVT LTD | 07/03/2023 |
| CC005000000238550 | Rajesh Shah | Duville Estates Pvt Ltd | 25/03/2023 |
| CC005000000238567 | Poornima Iyengar | Duville Estates Pvt Ltd | 27/03/2023 |
| CC005000000238555 | Sachin Gangadhar Zambre | Tushad Behram Dubash | 26/03/2023 |
| CC005000000238554 | Shradha Selarka | Duville | 26/03/2023 |
| CC005000000238557 | Hitu Kajal Kajal | Duville Estates Pvt Ltd. | 26/03/2023 |
| CC005000000238630 | Manasi Suraj Ghemad | Duville Estates Pvt Ltd | 02/04/2023 |
| CC005000000238631 | MIHIR DAVDA | Duville Estates Private Limited | 03/04/2023 |
| CC12602744 | Duville Estates Private Limited | RASHMI TIWARI | 11/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Apr 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Apr 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 30 Apr 2024
Documents filed143
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 143 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: Form-3 - RRI - Dec2024.pdf | 16 Jul 2025 |
| Declaration in FORM BFile: rri form B.pdf | 8 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1 Form 2A - RR-I - Jun 2022 - Signed.pdf | 2 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2 Form 2A - RR-I - Sep 2022 - Signed.pdf | 2 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 3 Form 2A - RR-I - Dec 2022 - Signed.pdf | 2 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 4 Form 2A - RR-I - Mar 2023 - Counter Signed.pdf | 2 Apr 2025 |
| Certificates of CA (Form 3)File: RRI Form 3 Dec24.pdf | 21 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 RRI.pdf | 21 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A RRI.pdf | 21 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RRI June 2024.pdf | 18 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RRI Sept 2024.pdf | 18 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RRI June 2024.pdf | 18 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RRI Sept 2024.pdf | 18 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A)File: 10 Form 2A - RR-1 - Sep 2024.pdf | 14 Nov 2024 |
| Certificates of CA (Form 3)File: Form-3 - RRI- Jun 2024.pdf | 12 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: RRI.pdf | 12 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 - Riverdale Residences-I - P52100004692.pdf | 6 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - RRI - FY 2023-24.pdf | 10 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- RR.pdf | 7 Aug 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RR Form 2.pdf | 7 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A)File: RR Form 2A.pdf | 7 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: RRI Inv.pdf | 7 Aug 2024 |
| Certificates of CA (Form 3)File: Form 3 RRI.pdf | 29 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RRI Form 1.pdf | 9 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A RRI.pdf | 9 May 2024 |
| Disclosure of sold/ booked inventoryFile: Residences I inv.pdf | 2 May 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC 0748 01 11 2021.pdf | 30 Apr 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC 0365 15 07 2022.pdf | 30 Apr 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC 1173 26 02 2024.pdf | 30 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: RR1 Dec-2023 Inventory.pdf | 4 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - RR-I - Dec 2023.pdf | 1 Mar 2024 |
| Certificates of CA (Form 3)File: Form-3 - RRI - Dec 2023.pdf | 1 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Plot E - Form 1 - 31 Dec 2023.pdf | 12 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 6 Form 2 - RR-I - Sep 2023.pdf | 16 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A)File: 6 Form 2A - RR-1 - Sep 2023.pdf | 16 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - RR-I - Sep 2023.pdf | 2 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: 7 Inventory Data - RR-I - Sep 2023.pdf | 2 Nov 2023 |
| Certificates of CA (Form 3)File: Form-3 - RRI- Sep 2023.pdf | 31 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - RRI - FY 2022-23.pdf | 30 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - RR-1 - Jun 2023.pdf | 8 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A)File: 5 Form 2A - RR-1 - Jun 2023.pdf | 8 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: 6 Inventory Details - June 2023 - Optimized.pdf | 27 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 5 Form 2- RR-I - Jun 2023.pdf | 21 Jul 2023 |
| Certificates of CA (Form 3)File: Form 3 - RRI - June 2023.pdf | 21 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - RR-I - Mar 2023 - Counter Signed.pdf | 21 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4 Form 2 - RR-I - Mar 2023 - Counter Signed.pdf | 21 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A)File: 4 Form 2A - RR-I - Mar 2023 - Counter Signed.pdf | 21 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: 5 Inventory Details - 31032023.pdf | 21 Apr 2023 |
| Certificates of CA (Form 3)File: Form 3 - RRI - Mar 2023.pdf | 21 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - RR-I - Dec 2022.pdf | 18 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - RR-I - Dec 2022 - signed.pdf | 18 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A - RR-I - Dec 2022 - Signed.pdf | 18 Jan 2023 |
| Certificates of CA (Form 3)File: Form 3 - RR - Dec 2022.pdf | 13 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Inventory Details - RR I - 31122022.pdf | 12 Jan 2023 |
| Certificates of CA (Form 3)File: Form 3 - RR - Sep 2022.pdf | 16 Nov 2022 |
| Certificates of CA (Form 3)File: Form 3 - RR - Jun 2022.pdf | 16 Nov 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - RR - 30062022 - Signed.pdf | 9 Nov 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - RR - 30092022 - Signed.pdf | 9 Nov 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - RR-I - 30062022 - Signed.pdf | 9 Nov 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - RR-I - 30092022 - Signed.pdf | 9 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A - RR-I - 30602022 - Signed.pdf | 9 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A - RR-I - 30092022 - Signed.pdf | 9 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - RR-I - 30062022.pdf | 9 Nov 2022 |
| Disclosure of sold/ booked inventoryFile: Inventory Details - 30062022.pdf | 6 Nov 2022 |
| Disclosure of sold/ booked inventoryFile: Inventory Details - 30092022.pdf | 6 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Plot E - RRI.pdf | 30 Sep 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - RR - 31032022 - Optimsed.pdf | 16 Jun 2022 |
| Certificates of CA (Form 3)File: Form 3 - Riverdale Residences I - Optimized.pdf | 16 Jun 2022 |
| Disclosure of sold/ booked inventoryFile: Inventory Details - 31032022-compressed.pdf | 8 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Riverdale - Residences.pdf | 29 Dec 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Riverdale - Residences.pdf | 29 Dec 2021 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: RR.pdf | 22 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Plot E.pdf | 10 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory E1 2 3.pdf | 9 Oct 2021 |
| Declaration about Commencement CertificateFile: Declaration About Commencement Certificate Plot E.pdf | 5 Oct 2021 |
| OtherFile: Legal.pdf | 26 Feb 2021 |
| Engineers Certificate on Quality Assurance (Form 2A)File: Plot - E From-2A.PDF | 29 Oct 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Riverdale-Residences.pdf | 13 Oct 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - RR1.pdf | 13 Oct 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Duville Plot -E_compressed.pdf | 13 Nov 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 7 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 143 filed documents as one ZIP, foldered, with a manifest
Keep Riverdale Residences-I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KHARADI
Filed coordinates, straight-line distance. 123 registered projects within 2 km.
VJ IndiLife Kharadi
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
VJ Central Avenue
Vilas Javdekar Eco Homes
VJ IndiWorks Kharadi Central
Vilas Javdekar Eco Homes
RIVERDALE GRAND
DUVILLE ESTATES PRIVATE LIMITED
Yashwin Orizzonte Phase II
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
ZEN ESTATE
DESTINATION KHARADI DEVELOPERS LLP
Builder: Duville Estates Private Limited
Duville Estates Private Limited has 8 registrations on MahaRERA, including Riverdale Heights and Riverdale Residences-I. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Litigation is declared on 4 of its registrations. Read the full track record.
Frequently asked questions
What are my rights if Riverdale Residences-I is delayed beyond 26 Feb 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Riverdale Residences-I?
The registered promoter entity is Duville Estates Private Limited, a company as per the filing. Its GSTIN 27AACCC8436BIZW can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Riverdale Residences-I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Riverdale Residences-I?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Riverdale Residences-I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Riverdale Residences-I?
The professionals named in the filing: Architect: Pinnac AECL Consultancy Pvt Ltd; Engineer: JW Consultants LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Riverdale Residences-I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback