Registration lapsed No litigation declared Residential / Group Housing project

Rite Skyluxe

By Rite Developers Pvt. Ltd.

RG-MH-25413 · RERA P51800006893 · Last updated on MahaRERA portal: 23 Aug 2021

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 58 months past the filed date
  • 11 complaints at MahaRERA
  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2021Possession promised58 months past this date
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 94%
11Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

Rite Skyluxe is a Residential / Group Housing project by Rite Developers Pvt. Ltd. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800006893 on 16 Aug 2017. Possession was promised by 30 Dec 2021 and is now 58 months past that date. The completion date has moved by 36 months from the original filing. 11 complaints are on record with the regulator.

At a glance

Project

  • NameRite Skyluxe
  • TypeResidential / Group Housing
  • Location
    • Subhash Nagar
    • Chembur
    • Kurla
    • Mumbai Suburban
    • 400071
  • Pincode400071
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800006893
  • ReraGenie IDRG-MH-25413

Builder

  • NameRite Developers Pvt. Ltd.
  • Entity typeCompany
  • Other registrations9 more →
  • Completed4 of 10
  • No longer live6 lapsed, de-registered or revoked
  • Declared earlier projects6 →

Key dates

58 months past promisethis monthRegisteredAug 2017First promiseDec 2018Revised toDec 2021

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on16 Aug 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed56 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Rite SkyluxeNA180000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Aug 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 94%.

Rite Skyluxe: 88% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure94%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises94%
Sanitary Fittings within the flats / premises94%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks94%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.94%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.94%

Progress on shared amenities16

As on 23 Aug 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes75%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes94%
Electrical meter room, sub-station, receiving stationYes94%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
OthersYes0%

Parking filed77

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots77
Closed/Covered77

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,447 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI8530.18
Proposed, not sanctioned6,831 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCTS No 1023, PN 9, Esperanca Poly CHS, Holy Cross Road, I C Colony, Borivali West, Mumbai, Maharasht

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMR AMEET PAWAR
EngineerRajesh Tailor
Chartered AccountantJigar Zaveri & Associates
Chartered AccountantC S Mehta & Co
PartnerRole in project
Rite Developers Pvt. Ltd.-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800005423Dec 2018 → Dec 2020

Reason as filed by the promoterThe current status of the project i.e. internal and external development work in respect of project is 85% competed as per approved plans further due to change in goverment policy, change in approving authority i.e. from MCGM to MHADA due to which got delayed in completion of project within time line. We also obtain consent from the Allottees for extension of the date mentioned in RERA, and Allottees have no objection in extension of possession date in RERA i.e. date of Completion of project be extended from 31st December, 2019 to 31st December, 2020.

EXT51800001110Dec 2018 → Dec 2020

Reason as filed by the promoter(1) Due to change in Government policies initially there were difference of opinion occurred between two government authorities (i.e. MHADA and MCGM) due to which process to give sanctions were kept on hold by both the authorities; (2) further on 16th June, 2017 we got full concessions approved for “B” wing with condition that Subhash Nagar layout to be approved from Municipal commissioner for full FSI and Subhash Nagar Layout got approved by MHADA on 1st February, 2018. (3) Vide notification issued by Urban Department, Department of Govt. of Maharashtra, wherein MHADA has been appointed as Sp

Litigation declared1

CaseCourtStatus
CC/13/232/2013Consumer Disputes Redressal of Mumbai SuburbanRespondent Oral submission

Complaints filed with MahaRERA11

Case no.ComplainantRespondentFiled
CC006000000192449Hamendra Kasturlal DoshiRITE DEVELOPERS PVT. LTD.05/02/2020
CC006000000057602Parikshit Joshi & Pradip JoshiRite Developers Pvt Ltd10/01/2019
CC006000000089745Mr. Divyesh Mahendrapratap SatiM/s. Rites Developers Pvt. Ltd.16/06/2019
CC006000000079478Supriya inamdarRite Developers pvt ltd27/05/2019
CC006000000100223MR ABHY ABHAY KADAKIA & MRS CHANDRIKA BABUBHAI KADAKIAM/S RITE DEVELOPERS PVT LTD20/07/2019
CC006000000100298MRS ARPITA DATTA IYER AND MR SHIVRAM IYER THROUGH POWER OF ATTORNEY HOLDER MR. RAKESH JAYRAM JADHAVM/S RITE DEVELOPERS PVT LTD25/07/2019
CC006000000171500Manoj ThanekarRite Developers pvt.ltd.21/01/2020
CC006000000196506Mr. Binoy MathewRite Developers Pvt ltd26/03/2021
CC006000000209900Venkatesh IyerRite Developers Pvt. Ltd.07/02/2022
CC006000000209949CHIMANLAL SHANTILAL MEHTARITE DEVELOPERS PRIVATE LIMITED08/02/2022
CC006000000292254Anita Eldred MenezesRite Developers Private Limited07/08/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 May 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Aug 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 23 Aug 2019

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Skyluxe 18-19.pdf23 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: sky luxe 19-20.pdf23 Aug 2021
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory Rite Skyluxe (1).pdf14 Aug 2021
Declaration about Commencement CertificateFile: Format D Declation CC Rite Skyluxe.pdf13 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form -2A QAC FY 2019-20 Rite Skyluxe.pdf11 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A QAC Rite Skyluxe 2020-2021.pdf11 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Rite Skyluxe.pdf10 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Rite Skyluxe.pdf10 Aug 2021
Certificates of CA (Form 3)File: Form 3 Rite Skyluxe.pdf10 Aug 2021
Disclosure of sold/ booked inventoryFile: Rite Skyluxe.pdf9 Jun 2021
Details of encumbrancesFile: No encumberance Certificate Kalabharti-12122020.pdf15 Dec 2020
Details of encumbrancesFile: No Dues - Rite.PDF15 Dec 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC plan.pdf23 Aug 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Plan2.pdf23 Aug 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Plan 3.pdf23 Aug 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate (1).pdf22 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 RITE SKYLUXE.pdf17 Nov 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 RITE SKYLUXE.pdf17 Nov 2018
Certificates of CA (Form 3)File: FORM 3 RITE SKYLUXE.pdf17 Nov 2018
Certificates of CA (Form 5)File: FROM 5 RITE SKYLUXE.pdf15 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: Full CC for B wing 090818.PDF13 Aug 2018
Building plan approvalFile: Building Plan Approval Amended1.pdf10 May 2018
Building plan approvalFile: Building Plan Approval Amended2.pdf10 May 2018
Building plan approvalFile: Building Plan Appoval Amended3.pdf10 May 2018
Building plan approvalFile: Building Plan Approval Amended4.pdf10 May 2018
Building plan approvalFile: Building Plan Approval Amended5.pdf10 May 2018
Building plan approvalFile: Building Plan Approval Amended6.pdf10 May 2018
Building plan approvalFile: Building Plan Approval Amended7.pdf10 May 2018
Building plan approvalFile: Building Plan Approval letter.pdf10 May 2018
Building Plan Approval (IOD)File: Building Plan Approval Amended1.pdf10 May 2018
Building Plan Approval (IOD)File: Building Plan Approval Amended2.pdf10 May 2018
Building Plan Approval (IOD)File: Building Plan Appoval Amended3.pdf10 May 2018
Building Plan Approval (IOD)File: Building Plan Approval Amended4.pdf10 May 2018
Building Plan Approval (IOD)File: Building Plan Approval Amended5.pdf10 May 2018
Building Plan Approval (IOD)File: Building Plan Approval Amended6.pdf10 May 2018
Building Plan Approval (IOD)File: Building Plan Approval Amended7.pdf10 May 2018
Building Plan Approval (IOD)File: Building Plan Approval letter.pdf10 May 2018
Details of encumbrancesFile: No Encumbrance Certificate_ updated.pdf17 Nov 2017
Layout approvalFile: Skyluxe_2_Last_Amended_Plan.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Skyluxe_2_Last_Amended_Plan.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1-Architect Certificate-Kalabharti-Final Signed.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - Engnineer Certificate-Kalabharti-Final.pdf29 Jul 2017
Certificates of CA (Form 3)File: FORM 3 - CA Certificate.pdf29 Jul 2017
OtherFile: GIS MAP Survey Certificate.pdf29 Jul 2017
Building plan approvalFile: Amended IOD.pdf28 Jul 2017
Building plan approvalFile: IOD.pdf28 Jul 2017
PAN CardFile: Pan Card.pdf28 Jul 2017
Copy of the legal title reportFile: Title Certificate.pdf28 Jul 2017
Details of encumbrancesFile: No Encumbrance Certificate.pdf28 Jul 2017
Building Plan Approval (IOD)File: IOD.pdf28 Jul 2017
Building Plan Approval (IOD)File: Amended IOD.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf28 Jul 2017
Declaration in FORM BFile: FORM B.pdf28 Jul 2017
Proforma of Allotment letterFile: Agreement For Sale.pdf28 Jul 2017
Proforma of Allotment letterFile: Agreement For Sale.pdf28 Jul 2017
OtherFile: Resolution.pdf28 Jul 2017

Promoter's earlier projects6

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

6 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Rite PrimeAndheri West9CompletedMay 2016Late, Mar 2018
Rite CelestaKandivali West24CompletedJun 2015Late, Sep 2017
Rite OpusKandivali West16CompletedMar 2015Late, Mar 2016
Rite SplendorBorivali East31CompletedDec 2014Late, Apr 2015
Rite SenorMulund East43CompletedMar 2014Late, May 2015
Rite FortuneKandivali West51CompletedApr 2013Late, Mar 2016

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 36 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Rite Skyluxe on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chembur6,700+ in Mumbai Suburban

2 kmRite SkyluxeCompleted 155Lapsed / revoked 119Other 139Dot size: filed unitsN

Filed coordinates, straight-line distance. 413 registered projects within 2 km.

Builder: Rite Developers Pvt. Ltd.

Rite Developers Pvt. Ltd. has 10 registrations on MahaRERA, including Rite Bliss and Rite Aspire. Its filings disclose 6 earlier MahaRERA projects: declares 0 of 6 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Rite Skyluxe shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Rite Skyluxe is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Rite Skyluxe?

The registered promoter entity is Rite Developers Pvt. Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Rite Skyluxe?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Rite Skyluxe?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Rite Skyluxe?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Rite Skyluxe?

The professionals named in the filing: Architect: MR AMEET PAWAR; Engineer: Rajesh Tailor; Chartered Accountant: Jigar Zaveri & Associates; Chartered Accountant: C S Mehta & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Rite Skyluxe?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Rite Skyluxe. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Rite Skyluxe to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.