Home / Browse projects / Mumbai Suburban, Maharashtra / RGS ANANTYA
RGS ANANTYA
RG-MH-88842 · RERA P51800032255 · Last updated on MahaRERA portal: 24 May 2023
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
RGS ANANTYA is a Residential / Group Housing project by SINGH HOLDING PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800032255 on 17 Dec 2021. The registration is recorded completed; possession was promised by 30 Jun 2023.
At a glance
Project
- NameRGS ANANTYA
- TypeResidential / Group Housing
- Location
- SION TROMBAY ROAD
- CHEMBUR
- Kurla
- Mumbai Suburban
- 400071
- Pincode400071
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800032255
- ReraGenie IDRG-MH-88842
Builder
- NameSINGH HOLDING PVT LTD
- Entity typeCompany
- Managing DirectorRAJIV BHOLANATH GUPTA
- DirectorsATUL BHOLANATH GUPTA, VINEET BHOLANATH GUPTA
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on17 Dec 2021
- Promised completion30 Jun 2023
- Revised completionNone
- Buildings1 building record
- Documents filed47 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| RGS ANANTYA | NA | 11 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 24 May 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
RGS ANANTYA: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 24 May 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed21
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RASIK P HINGOO ASSOCIATES |
| Engineer | ADVANCE CREATIVE DESIGN CONSULTANCY |
| Chartered Accountant | VINOD PAWAR |
| Chartered Accountant | RAKSHIT GOWDA & ASSOCIATES |
| Partner | Role in project |
|---|---|
| SINGH HOLDING PVT LTD | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Dec 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Nov 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 15 Mar 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 15 Mar 2023
Documents filed47
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Details of encumbrancesFile: SBI AC Closuer NOC.pdf | 24 May 2023 |
| Architect’s Certificate on Completion of Project (Form 4)File: SHPL Form 4.pdf | 30 Mar 2023 |
| Building plan approvalFile: OC Drawing.pdf | 15 Mar 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: OC Drawing.pdf | 15 Mar 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation cum Building Completion Cert.pdf | 15 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Engineers Cert Quality Assurance.pdf | 24 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect.pdf | 21 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engg Cert.pdf | 21 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engg.pdf | 21 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 Engg.pdf | 21 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA.pdf | 21 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf | 21 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert Form 1.pdf | 14 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Form - 2.pdf | 14 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf | 14 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Cert - Form 3.pdf | 14 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate June.pdf | 13 Jun 2022 |
| Disclosure of sold/ booked inventoryFile: Sold_Unsold_Flats_June.pdf | 13 Jun 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form_3_June.pdf | 13 Jun 2022 |
| Details of encumbrancesFile: Encumbrance Cert.pdf | 8 Apr 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4th Slab Certificate.pdf | 8 Apr 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Cert.pdf | 8 Apr 2022 |
| Building plan approvalFile: Drawing final.pdf | 9 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Drawing final.pdf | 9 Feb 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Full CC.pdf | 9 Feb 2022 |
| Declaration about Commencement CertificateFile: Declaration to CC.pdf | 9 Feb 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Plinth Cert.pdf | 9 Feb 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Cert.pdf | 9 Feb 2022 |
| Copy of the legal title reportFile: Format A Flow of Land.pdf | 3 Dec 2021 |
| Layout approvalFile: Concession upto 9th.pdf | 30 Nov 2021 |
| Building plan approvalFile: SHPL IOD received.pdf | 30 Nov 2021 |
| Building plan approvalFile: Aproved Plan 2nd floor.pdf | 30 Nov 2021 |
| Copy of Layout Approval (in case of layout)File: Concession upto 9th.pdf | 30 Nov 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: SHPL IOD received.pdf | 30 Nov 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Aproved Plan 2nd floor.pdf | 30 Nov 2021 |
| Declaration about Commencement CertificateFile: Declaration about CC.pdf | 30 Nov 2021 |
| Details of encumbrancesFile: Encumbrance Declration.pdf | 26 Nov 2021 |
| Declaration in FORM BFile: Form B-compressed.pdf | 26 Nov 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certficate.pdf | 26 Nov 2021 |
| CERSAI detailsFile: CERSAIREP.pdf | 26 Nov 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate.pdf | 26 Nov 2021 |
| Proforma of Allotment letterFile: Final_RERA_Agreement__1_-converted.pdf | 26 Nov 2021 |
| Proforma of Allotment letterFile: Allotment_Letter-Anantya (2)-converted.pdf | 26 Nov 2021 |
| Status of ConveyanceFile: Deed_of_Conveyance_11zon (1).pdf | 26 Nov 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: SHPL CC upto pinth.pdf | 9 Nov 2021 |
| PAN CardFile: singh holdings pancard.PDF | 22 Oct 2021 |
| Copy of the legal title reportFile: Format A Title Report.pdf | 22 Oct 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 47 filed documents as one ZIP, foldered, with a manifest
Keep RGS ANANTYA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near CHEMBUR6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 315 registered projects within 2 km.
Hiranandani Maitri Park Phase 1
SHODEN DEVELOPERS PRIVATE LIMITED
Premiere by Panache
Panache Developers Pvt Ltd.
Sai Shrushti
Shree Sai Realtors
MASS METROPOLIS
GRACE URBAN DEVELOPMENT CORPORATION
ELEVIA
VIDA INFRAHUB LLP
PODDAR HARMONY
PODDAR CREATORS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: SINGH HOLDING PVT LTD
SINGH HOLDING PVT LTD has 1 registration on MahaRERA, including RGS ANANTYA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if RGS ANANTYA is delayed beyond 30 Jun 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of RGS ANANTYA?
The registered promoter entity is SINGH HOLDING PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in RGS ANANTYA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for RGS ANANTYA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at RGS ANANTYA?
The professionals named in the filing: Architect: RASIK P HINGOO ASSOCIATES; Engineer: ADVANCE CREATIVE DESIGN CONSULTANCY; Chartered Accountant: VINOD PAWAR; Chartered Accountant: RAKSHIT GOWDA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in RGS ANANTYA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback