Home / Browse projects / Palghar, Maharashtra / RG-A,B,E,F
RG-A,B,E,F
RG-MH-10392 · RERA P99000003885 · Last updated on MahaRERA portal: 1 Dec 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 5 complaints at MahaRERA
- Completion date moved by 72 months
- 2 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
RG-A,B,E,F is a Others project by RELIABLE REALTOUCH in Palghar, Maharashtra, registered with MahaRERA as P99000003885 on 6 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 72 months from the original filing. 264 of the 286 units on this registration are recorded sold or booked, and 28 of 44 construction stages are filed complete. 5 complaints are on record with the regulator.
At a glance
Project
- NameRG-A,B,E,F
- TypeOthers
- Location
- sATIVALI
- vASAI eAST
- Vasai-Virar City (M Corp)
- Vasai
- Palghar
- 401208
- Pincode401208
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000003885
- ReraGenie IDRG-MH-10392
Builder
- NameRELIABLE REALTOUCH
- Entity typePartnership
- GSTIN27AAPFR2090E2Z1
- PartnerMOHAMMED ALI UZAIR ZAINUL ABEDIN MUKADAM
- Other registrations1 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on6 Aug 2017
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 25 Dec 2019)
- Buildings4 building records
- Documents filed59 files
Current status
Figures as on 1 Dec 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A WING | NA | 12 | 12 | 72 | 14 | 86 |
| B WING | NA | 12 | 12 | 72 | 12 | 84 |
| E WING | NA | 11 | 11 | 54 | 8 | 62 |
| F WING | NA | 11 | 11 | 54 | 0 | 54 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 1 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
28 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 90%.
A WING85%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 60% |
B WING85%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 60% |
E WING85%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 60% |
F WING85%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 60% |
Progress on shared amenities15
As on 1 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 80% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 50% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed71
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A WING | 1 | 10 | 11 |
| B WING | 1 | 25 | 26 |
| E WING | 1 | 5 | 6 |
| F WING | 1 | 27 | 28 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VIJAY GURAV AND ASSOCIATES |
| Engineer | SHILPLEKHA CONSULTANT CHANDRESH CHHEDA Chandresh Chheda |
| Chartered Accountant | SANJAY B SHARMA AND CO |
| Chartered Accountant | satish omprakash soni |
| Chartered Accountant | S.LAKDAWALA & ASSOCIATES |
| Partner | Role in project |
|---|---|
| RELIABLE REALTOUCH | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDelay in permission from Development authority
Reason as filed by the promoterDue to covid, the project has been delayed and delay in Commencement certificate ,which is now received in full dated 07.07.2021
Complaints filed with MahaRERA5
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000195532 | Suyash Gopiram Modi | M/s. Reliable Realtouch | 05/01/2021 |
| CC006000000195534 | Sunita Gopiram Modi | M/s. Reliable Realtouch | 05/01/2021 |
| CC006000000192715 | Sameer Khan | Salim Mehmood Khan | 14/07/2024 |
| CC12500997 | MUBARAKUN NISA KHAN | RELIABLE REALTOUCH | 22/03/2025 |
| CC12500998 | MUBARAKUN NISA KHAN | RELIABLE REALTOUCH | 22/03/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Aug 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Aug 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed59
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2024-2025)File: form 5 Abe&f 2025.pdf | 1 Dec 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: S 1.pdf | 15 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: S 2.pdf | 15 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: S 3.pdf | 15 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: S 4.pdf | 15 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: S 5.pdf | 15 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: S 6.pdf | 15 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: S 7.pdf | 15 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: S 8.pdf | 15 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: S 9.pdf | 15 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: S 10.pdf | 15 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: S 11.pdf | 15 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form no 5 21 to 22.pdf | 15 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form no 5 23 to 24 .pdf | 15 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A to F April to Jun 22.pdf | 13 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A to F April To Jun 23.pdf | 13 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A To F Jan To Mach 24.pdf | 13 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A to F Jan To March 22.pdf | 13 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A to F Jan To March 23.pdf | 13 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A to F July To Sep 21.pdf | 13 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A to F July To sep 22.pdf | 13 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A to F July To Sep 23.pdf | 13 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A to F Oct to Dec 21.pdf | 13 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A to F Oct To Dec 22.pdf | 13 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A to F Oct To Dec 23.pdf | 13 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory Dt 23-11-23.pdf | 15 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form -5 Ca Certificate.pdf | 15 Dec 2023 |
| PAN CardFile: Reliable Realtouch.pdf | 9 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form -1.pdf | 8 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2.pdf | 8 Dec 2023 |
| Layout approvalFile: LAYOUT FINAL_compressed.pdf | 26 Aug 2021 |
| Building plan approvalFile: BLUE PRINT-FINAL_compressed.pdf | 26 Aug 2021 |
| Copy of Layout Approval (in case of layout)File: LAYOUT FINAL_compressed.pdf | 26 Aug 2021 |
| Building Plan Approval (IOD)File: BLUE PRINT-FINAL_compressed.pdf | 26 Aug 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: CC dated 7-7-2021_compressed.pdf | 26 Aug 2021 |
| Declaration about Commencement CertificateFile: CC-declaration.pdf | 26 Aug 2021 |
| Declaration in FORM BFile: FORM B- AMENDED_compressed.pdf | 26 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 Dated 10-08 2021_compressed.pdf | 26 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM -2A- MARCH 2020_compressed.pdf | 26 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A-MARCH 21.pdf | 26 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM -2A JUNE 2021_compressed.pdf | 26 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Inventory Details_Sold_Unslod.pdf | 26 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM-5-FY 19-20.pdf | 26 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM-5-FY 20-21.pdf | 26 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: RGABEF RERA 17-18.pdf | 7 Dec 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: RGABEF RERA 18-19.pdf | 7 Dec 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: REALTOUCH CC-ilovepdf-compressed(1).pdf | 12 Oct 2018 |
| Building plan approvalFile: Approved Plan Realtouch.pdf | 30 Jul 2017 |
| Layout approvalFile: REALTOUCH LAYOUT PLAN.pdf | 30 Jul 2017 |
| Copy of the legal title reportFile: realtouch search.pdf | 30 Jul 2017 |
| Details of encumbrancesFile: Reliable Realtouch A,B,E,F ENCRUM.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: REALTOUCH LAYOUT PLAN.pdf | 30 Jul 2017 |
| Building Plan Approval (IOD)File: Approved Plan Realtouch.pdf | 30 Jul 2017 |
| Declaration in FORM BFile: FORM 'B' REALTOUCH-ilovepdf-compressed-1.pdf | 30 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA-FORM1-B1W ABEF-ilovepdf-compressed.pdf | 30 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: REALTOUCH ABEF.pdf | 30 Jul 2017 |
| Certificates of CA (Form 3)File: FORM 3 ABEF REALTOUCH-ilovepdf-compressed.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: RELIABLE REALTOUCH SALE AGREEEMENT.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: Allotment Letter Draft.pdf | 30 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 59 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep RG-A,B,E,F on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near vASAI eAST3,200+ in Palghar
Filed coordinates, straight-line distance. 62 registered projects within 2 km.
Suraksha Smart City - Phase I
Conceptual Advisory Services LLP
The Great Western Mumbai
HOABL Impactum Land Private Limited
Suraksha Smart City - Phase II
Conceptual Advisory Services LLP
Suraksha Smart City - Phase III
Conceptual Advisory Services LLP
Rashmi Star City Phase 2
Rashmi Realty Builders Pvt Ltd
Agarwal Sky Heights
Shreenath Realtors
See every Palghar project, with the district possession charts
Builder: RELIABLE REALTOUCH
RELIABLE REALTOUCH has 2 registrations on MahaRERA, including RG-A,B,E,F and RG-C,D. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What does it mean that RG-A,B,E,F shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if RG-A,B,E,F is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of RG-A,B,E,F?
The registered promoter entity is RELIABLE REALTOUCH, a partnership as per the filing. Its GSTIN 27AAPFR2090E2Z1 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in RG-A,B,E,F?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against RG-A,B,E,F?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for RG-A,B,E,F?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at RG-A,B,E,F?
The professionals named in the filing: Architect: VIJAY GURAV AND ASSOCIATES; Engineer: SHILPLEKHA CONSULTANT CHANDRESH CHHEDA Chandresh Chheda; Chartered Accountant: SANJAY B SHARMA AND CO; Chartered Accountant: satish omprakash soni; Chartered Accountant: S.LAKDAWALA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in RG-A,B,E,F?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback