ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / Ramashray

Completed No litigation declared Residential / Group Housing project

Ramashray

By Pariksheet Ramkrishna Dandekar

RG-MH-28549 · RERA P99000026369 · Last updated on MahaRERA portal: 9 May 2023

Source: official MahaRERA filing

Red flags

  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 2 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Jun 2022Possession promisedregistration recorded completed
8 of 11Construction stages donefurthest along: Basement (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 47 documents Report an error

Ramashray is a Residential / Group Housing project by Pariksheet Ramkrishna Dandekar in Palghar, Maharashtra, registered with MahaRERA as P99000026369 on 11 Sep 2020. The registration is recorded completed; possession was promised by 30 Jun 2022.

At a glance

Project

  • NameRamashray
  • TypeResidential / Group Housing
  • Location
    • Bhausaheb Dandekar Marg
    • Near ICICI Bank
    • Palghar
    • 401404
  • Pincode401404
  • RERA no.P99000026369
  • ReraGenie IDRG-MH-28549

Builder

  • NamePariksheet Ramkrishna Dandekar
  • Entity typeIndividual
  • Named personPariksheet Dandekar
  • Declared earlier projects2 →

Key dates

this monthRegisteredSep 2020PromisedJun 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on11 Sep 2020
  • Promised completion30 Jun 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed47 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RAMASHRAYNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 May 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

RAMASHRAY: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 9 May 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,160 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Ramkrishna Govind DandekarPalghar Palghar

Approvals and building plan

Permissible FSI4323.95
Proposed, not sanctioned4,324 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRaghunandan CHS Mahim Raod Palghar west 401404

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMahendra Kale
EngineerN M Rege
Chartered AccountantCA Sunil Vaidya
PartnerRole in project
Pariksheet Ramkrishna Dandekar-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000015419Jun 2022 → May 2023

Reason as filed by the promoterThe construction work of the building named Ramashray was complete and application for the occupation certificate/ work completion certificate was duly done the concerned government authority, that is, Palghar municipal council. The process of granting the occupation certificate/ work completion certificate was delayed from the side of Palghar municipal council. Hence the extension was not taken.

EXT99000011964Jun 2022 → Jan 2023

Reason as filed by the promoterDue to the covid pandemic and subsequent intermittent waves leading to lock downs resulted in the delay of the construction work. At the same time, the cyclone situation too resulted in halt of work. hence we will like to extend the completion date of the project to 31/01/2023

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Sep 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Sep 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Sep 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Sep 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 10 Apr 2023

Documents filed47

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf9 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A March 2023.pdf26 Apr 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold inventory.pdf26 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31 March 23.pdf26 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate.pdf10 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer certificate Form 2A July 2022.pdf2 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer certificate Form 2A October 2022.pdf2 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer certificate Form 2A January 2023.pdf2 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021 2022.pdf2 Feb 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Arcitect Complition1.pdf2 Feb 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Certificate .pdf2 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf24 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf24 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf24 Jan 2023
Declaration about Commencement CertificateFile: Format D.pdf8 Jun 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Table A and B.pdf8 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Sep 2020.pdf8 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A April 2021.pdf8 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Jan 2021.pdf8 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A July2021.pdf8 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Oct 2021.pdf8 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Jan 2022.pdf8 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A April 2022.pdf8 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Sep 2020.pdf8 Jun 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf8 Jun 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold details.pdf27 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 March .pdf27 Oct 2021
Copy of the legal title reportFile: Title Investigation Report 1.pdf8 Sep 2020
Copy of the legal title reportFile: Title Investigation Report 2.pdf8 Sep 2020
Layout approvalFile: Approve Plan 1.pdf7 Sep 2020
Building plan approvalFile: Approve Plan 1.pdf7 Sep 2020
Building plan approvalFile: Approve Plan 2.pdf7 Sep 2020
Copy of Layout Approval (in case of layout)File: Approve Plan 1.pdf7 Sep 2020
Building Plan Approval / NA Order for plotted developmentFile: Approve Plan 1.pdf7 Sep 2020
Building Plan Approval / NA Order for plotted developmentFile: Approve Plan 2.pdf7 Sep 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf5 Sep 2020
PAN CardFile: PRD Pan Card.pdf4 Sep 2020
Details of encumbrancesFile: Encumbrance.pdf4 Sep 2020
Commencement Certificates / NA Order for plotted developmentFile: CC Page 1.pdf4 Sep 2020
Commencement Certificates / NA Order for plotted developmentFile: CC Page 2.pdf4 Sep 2020
Commencement Certificates / NA Order for plotted developmentFile: CC Page 3.pdf4 Sep 2020
Commencement Certificates / NA Order for plotted developmentFile: CC Page 4.pdf4 Sep 2020
Declaration in FORM BFile: Affidavit RERA_compressed.pdf4 Sep 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate.pdf4 Sep 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf4 Sep 2020
Proforma of Allotment letterFile: Allotment Letter.pdf4 Sep 2020
Proforma of Allotment letterFile: Aggrement for Sale.pdf4 Sep 2020

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Bafna Meadows Phase 2Whagulsar Mahim Palghar108CompletedDec 2021Dec 2021
Bafna mEadows Phase 1Whagulsar Mahim159CompletedDec 2018Oct 2018

How this compares with Palghar

31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Ramashray on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near ICICI Bank3,200+ in Palghar

Builder: Pariksheet Ramkrishna Dandekar

Pariksheet Ramkrishna Dandekar has 1 registration on MahaRERA, including Ramashray. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if Ramashray is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Ramashray?

The registered promoter entity is Pariksheet Ramkrishna Dandekar, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Ramashray?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Ramashray?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Ramashray?

The professionals named in the filing: Architect: Mahendra Kale; Engineer: N M Rege; Chartered Accountant: CA Sunil Vaidya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ramashray?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ramashray. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ramashray to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.