Home / Browse projects / Pune, Maharashtra / RAJGRUHI RESIDENCY TOWER D
RAJGRUHI RESIDENCY TOWER D
RG-MH-27478 · RERA P52100034436 · Last updated on MahaRERA portal: 3 Jun 2026
Source: official MahaRERA filing
Red flags
- Litigation declared, 5 cases
- 5 complaints at MahaRERA
Clear
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
RAJGRUHI RESIDENCY TOWER D is a Residential / Group Housing project by Atria Constructions in Pune, Maharashtra, registered with MahaRERA as P52100034436 on 5 Apr 2022. The registration is recorded completed; possession was promised by 31 Dec 2024. 5 complaints are on record with the regulator.
At a glance
Project
- NameRAJGRUHI RESIDENCY TOWER D
- TypeResidential / Group Housing
- Location
- S. NO. 63
- HISSA NO. 1/1
- 1/ 2 and 2
- KONDHWA BUDRUK
- SHATRUNJAY MADIR ROAD
- KONDHWA BUDRUK
- SHATRUNJAY MADIR ROAD
- Pune (M Corp.)
- Pune City
- Pune
- 411048
- Pincode411048
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100034436
- ReraGenie IDRG-MH-27478
Builder
- NameAtria Constructions
- Entity typePartnership
- GSTIN27AASFA5976B1Z5
- PartnersSambhaji Raghunath Tupe, Anil Ramalinga Reddy, Manjusha Dhananjay Thite, Dhananjay Nivrutti Thite, Vaishali Sanjayrao Holkar, Jitendra Dilip Shinde
- Other registrations5 more →
- Completed5 of 6
- No longer live1 lapsed, de-registered or revoked
- Declared earlier projects4 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on5 Apr 2022
- Promised completion31 Dec 2024
- Revised completionNone
- Buildings1 building record
- Documents filed94 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| RAJGRUHI RESIDENCY TOWER D | NA | 31 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 3 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 0%.
RAJGRUHI RESIDENCY TOWER D: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 3 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| WELLBUILD MERCHANTS PRIVATE LIMITED | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Partner | Role in project |
|---|---|
| Atria Constructions | - |
Litigation declared5
| Case | Court | Status |
|---|---|---|
| 582/2024 | DISTRICT COURT PUNE | Ongoing |
| 544/2024 | DISTRICT COURT PUNE | Ongoing |
| 582/2024 | DISTRICT COURT | Ongoing |
| 13292/2024 | HON'BLE SHRI JUSTICE B.P. COLABAWALLA HON'BLE SHRI JUSTICE FIRDOSH PHIROZE POONIWALLA | Ongoing |
| 13293/2024 | HON'BLE SHRI JUSTICE B.P. COLABAWALLA HON'BLE SHRI JUSTICE FIRDOSH PHIROZE POONIWALLA | Ongoing |
Complaints filed with MahaRERA5
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12400824 | Dhaval Pradeep Badani | Atria Constructions | 20/11/2024 |
| CC12501986 | Akshay Sanjay Doshi | Atria Constructions | 18/06/2025 |
| CC12501987 | Vipul Vasant Jain | Atria Constructions | 18/06/2025 |
| CC12501988 | Sourabh Jagdishchand Chhajer | Atria Constructions | 18/06/2025 |
| CC12501994 | Shreyash Deepak Shah | Atria Constructions | 18/06/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 15 Feb 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Mar 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Mar 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed94
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: OCCUPANCY CERTIFICATE.pdf | 3 Jun 2026 |
| Occupational CertificateFile: COVER LETTER.pdf | 3 Jun 2026 |
| Occupational CertificateFile: Final High Court Order 1022 of 2025.pdf | 3 Jun 2026 |
| Occupational CertificateFile: Final High Court Order 1309 of 2025.pdf | 3 Jun 2026 |
| Occupational CertificateFile: SUPREME COURT ORDER.pdf | 3 Jun 2026 |
| Occupational CertificateFile: FORM 4.pdf | 3 Jun 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 19 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 19 Jul 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2.pdf | 19 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD.pdf | 19 Jul 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM-2A.pdf | 19 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 D.pdf | 18 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 D.pdf | 18 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 D.pdf | 18 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD D.pdf | 18 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A D.pdf | 18 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 D.pdf | 13 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Singed Form 3 Tower D_compressed.pdf | 13 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 D.pdf | 13 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD TOWER D.pdf | 13 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A D.pdf | 13 Jan 2025 |
| Declaration in FORM BFile: FORM B TOWER D_compressed.pdf | 15 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 TOWER D.pdf | 19 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 TOWER D_compressed.pdf | 19 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 TOWER D.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD TOWER D_compressed.pdf | 19 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A TOWER D.pdf | 19 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5-SIGNED D.pdf | 19 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5-TOWER D.pdf | 16 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 16 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 16 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf | 16 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf | 16 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed (5).pdf | 16 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: BOOK INVENTORY-D-PROJECT-Q-4-FY-23-24.pdf | 17 Apr 2024 |
| Details of encumbrancesFile: ENCUMBRANCE CERTIFICATE D PROJECT.pdf | 16 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 16 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 16 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf | 16 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD.pdf | 16 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf | 16 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 18 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 16 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf | 16 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVETORY.pdf | 16 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 16 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 RAJGRUHI D.pdf | 18 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Tower D.pdf | 18 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Tower D.pdf | 18 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE RAJGRUHI D.pdf | 18 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Rera Form 3 Q2 Tower D.pdf | 18 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Signed Form3 Rajgruhi Resdency Tower D_compressed.pdf | 2 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Rera Tower D.pdf | 18 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 18 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf | 18 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Tower D_MRL-3-5.pdf | 18 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Tower D_MRL-3-5.pdf | 18 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Rera Form 3_Tower D_Atria_compressed.pdf | 18 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect cert D wing.pdf | 13 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg certificate Tower D Rajgruhi .pdf | 13 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality assurance Tower D Rajgruhi .pdf | 13 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: D Signed Form 3_compressed.pdf | 13 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2-TOWER-D.pdf | 10 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM-2A-TOWER-D.pdf | 10 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Tower D.pdf | 10 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 - TOWER-D.pdf | 10 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 11 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A.pdf | 11 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 11 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 23 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 23 Jul 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A.pdf | 23 Jul 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 23 Jul 2022 |
| Layout approvalFile: HPSC3448.pdf | 31 Mar 2022 |
| Building plan approvalFile: HPSC3471.pdf | 31 Mar 2022 |
| Building plan approvalFile: HPSC3476.pdf | 31 Mar 2022 |
| Copy of Layout Approval (in case of layout)File: HPSC3448.pdf | 31 Mar 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: HPSC3471.pdf | 31 Mar 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: HPSC3476.pdf | 31 Mar 2022 |
| Declaration in FORM BFile: 2 Declaration in FORM B.pdf | 31 Mar 2022 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| ATRIA GRANDE PROJECT B | S NO 2 Autade Handewadi Katraj Mantarwadi Road Pune 411028 | 258 | Completed | Dec 2021 | Aug 2019 |
| ATRIA GRANDE PROJECT A | S No 2 Autade Handewadi Katraj Mantarwdi Road Pune 411028 | 258 | Completed | Dec 2019 | Dec 2018 |
| Dhanashree Aashiyana | S. no. 7 Autade Handewadi Nyati Estate Road Pune 411028 | 179 | Completed | Oct 2016 | Oct 2016 |
| Dhanashree Aangan | S. No. 2 Autade Handewadi Nyati Estate Road Pune 411028 | 153 | Completed | Mar 2015 | Late, Mar 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 5 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 94 filed documents as one ZIP, foldered, with a manifest
Keep RAJGRUHI RESIDENCY TOWER D on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KONDHWA BUDRUK, SHATRUNJAY MADIR ROAD13,700+ in Pune
Filed coordinates, straight-line distance. 177 registered projects within 2 km.
Dwarikadham
Yashodhan Affordable Landmark LLP
UNITAS FASHION CENTER
UNITATIS DEVELOPMENTS PVT. LTD
Millennium Park
Xrbia Epoch Creations LLP
BABAR CLASSIC VISTA WING E, F, G
Classic Properties
JITO NAGAR
JAIN ASHAPURI DEVELOPER UNIT II
Wellwisher West Views
Bhansali Infrastructure LLP
Builder: Atria Constructions
Atria Constructions has 6 registrations on MahaRERA, including ATRIA GRANDE PROJECT A and ATRIA GRANDE PROJECT B. Its filings disclose 4 earlier MahaRERA projects: declares 3 of 4 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if RAJGRUHI RESIDENCY TOWER D is delayed beyond 31 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of RAJGRUHI RESIDENCY TOWER D?
The registered promoter entity is Atria Constructions, a partnership as per the filing. Its GSTIN 27AASFA5976B1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in RAJGRUHI RESIDENCY TOWER D?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against RAJGRUHI RESIDENCY TOWER D?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for RAJGRUHI RESIDENCY TOWER D?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
What should I check before booking in RAJGRUHI RESIDENCY TOWER D?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback