Atria Constructions: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

Atria Constructions has 6 registrations in this build, including ATRIA GRANDE PROJECT A and ATRIA GRANDE PROJECT B. Its filings disclose 4 earlier MahaRERA projects: 3 of 4 past projects completed on time. Litigation is declared on 2 of its registrations.

6Registrations in this build
4Past projects disclosed
on timeMedian delivery slip
2Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
ATRIA GRANDE PROJECT APune, Maharashtra--Completed
ATRIA GRANDE PROJECT BPune, Maharashtra--Completed
DHANASHREE AANAND 1Pune, Maharashtra--Completed
DHANASHREE AANAND 2Pune, Maharashtra--Completed
RAJGRUHI RESIDENCY TOWER C1Pune, Maharashtra703%Registration lapsed
RAJGRUHI RESIDENCY TOWER DPune, Maharashtra--Completed

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Dhanashree Aangan
1 Mar 201531 Mar 2015+1 months
Dhanashree Aashiyana
31 Oct 201618 Oct 2016On time
ATRIA GRANDE PROJECT A
31 Dec 201922 Dec 2018On time
ATRIA GRANDE PROJECT B
31 Dec 202119 Aug 2019On time

Frequently asked questions

How do I verify Atria Constructions as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Atria Constructions?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make Atria Constructions unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.