ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Purva Aspire

Registered No litigation declared Others project

Purva Aspire

By Puravankara Limited

RG-MH-49153 · RERA P52100017650 · Last updated on MahaRERA portal: 29 Sep 2026

Source: official MahaRERA filing

Red flags

  • 18 complaints at MahaRERA
  • Completion date moved by 49 months
  • 4 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jan 2027Possession promisedmoved 49 months from the original
8 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 96%
98 of 236Units unsoldnot recorded sold or booked
18Complaints at MahaRERAon this registration
Jump to the 126 documents Report an error

Purva Aspire is a Others project by Puravankara Limited in Pune, Maharashtra, registered with MahaRERA as P52100017650 on 4 Sep 2018. Possession is promised by 30 Jan 2027. The completion date has moved by 49 months from the original filing. 138 of the 236 units on this registration are recorded sold or booked, and 8 of 33 construction stages are filed complete. 18 complaints are on record with the regulator.

At a glance

Project

  • NamePurva Aspire
  • TypeOthers
  • Location
    • Bavdhan
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411021
  • Pincode411021
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100017650
  • ReraGenie IDRG-MH-49153

Builder

  • NamePuravankara Limited
  • Entity typeCompany
  • Managing DirectorNani R Choksey
  • Other registrations6 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredSep 2018First promiseDec 2022Revised toJan 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Sep 2018
  • Promised completion30 Jan 2027
  • Revised completionRevised to 30 Jan 2027 (originally 31 Dec 2022)
  • Buildings3 building records
  • Documents filed126 files

Current status

58%138 of 236 units booked
66.0%Work done, per cost certificate

Figures as on 29 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ENA20201180118
FNA20201180118
GNA00000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 29 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 96%.

E76%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises86%
Sanitary Fittings within the flats / premises46%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks69%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.74%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%
F76%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure96%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises77%
Sanitary Fittings within the flats / premises44%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.69%
G0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes75%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes70%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes25%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed200

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots200
Closed/Covered200
BuildingClosed/CoveredTotal
E100100
F100100

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,687 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
SIddharth PropertiesPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPMC
Permissible FSI25421.0
Proposed, not sanctioned25,421 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShivajinagar Branch
Estimated costRs 199.87 cr
Cost incurredRs 132.02 cr
Work done66.05%
BuildingWingEstimatedIncurred
ENARs 75.53 crRs 52.24 cr
FNARs 75.53 crRs 52.24 cr
-NARs 48.82 crRs 27.54 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVilas Yele
ArchitectAdvantage Architects
EngineerJW Consultants
EngineerSynte Great PMC
Chartered AccountantV D S R & CO LLP
Chartered AccountantMs Bhuvana Bhat and Associates
PartnerRole in project
Puravankara Limited-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P52100017650/WarDec 2022 → Jan 2027

Reason as filed by the promoterNA

EXT52100002378Dec 2022 → Sep 2023

Reason as filed by the promoterUntil project was transferred to Puravankara Ltd in April 2019 no work was undertaken at site. It is necessary to extend the date of completion by 9 months to allow for the procedural delays. No money has been collected from persons or units allotted till date.

EXT52100019631Dec 2022 → Sep 2025

Reason as filed by the promoterRe: Extension for project registration validity under section 7 of the Real Estate (Regulation and Development) Act, 2016 Compliance Report [[ Respected Sir, I, the undersigned, authorised signatory of the Promoter M/S Puravankara Ltd, (Purva Aspire) hereby state that we have registered the project “Purva Aspire” (hereinafter referred to as the said project) situated at survey no 37/1B at Pune (M Corp.), Pune City, Pune, 411021; with MahaRERA vide registration number P52100017650(Purva Aspire). We state that the registration validity of the said project has expired on September 30, 2024, and p

EA16072502087Dec 2022 → Sep 2026

Reason as filed by the promoterThe delay to achieve completion of the project is neither wilful or deliberate but due to various factors such as fallout of Covid Pandemic, labour exodus, issues with project execution contractors and certain mitigation circumstances

Complaints filed with MahaRERA18

Case no.ComplainantRespondentFiled
CC12502569Arbazali Nazir KhanPuravankara Limited26/07/2025
CC12502724NITIN TULARAM MAHAJANPuravankara Limited04/08/2025
CC12602445JITENDRA PANDURANG BARATEPuravankara Limited26/04/2026
CC12600623Amit Govindrao KagwadePuravankara Limited03/02/2026
CC12602529Najmul HussainPuravankara Limited30/04/2026
CC12601210Manoj SharmaPuravankara Limited06/03/2026
CC12601508Tejas Arun SathePuravankara Limited18/03/2026
CC12602357Bhavesh GujarathiPuravankara Limited21/04/2026
CC12602394Nachiket Satish KshirePuravankara Limited23/04/2026
CC12602416Suryad Hemant PaiPuravankara Limited25/04/2026
CC12602406Vikrant HasePuravankara Limited24/04/2026
CC12602434KISHOR DEVIDAS PAKHMODEPuravankara Limited26/04/2026
CC12602719Trupti Madhukar RotwadkarPuravankara limited10/05/2026
CC12602552Kanchan ChoudharyPuravankara Limited01/05/2026
CC12602993ANJALI NITIN LATKARPuravankara Limited20/05/2026
CC12603239Minal Tejas ThoratPuravankara Limited29/05/2026
CC12605652Najmul HussainPuravankara Limited01/09/2026
CC12605291YOGESH SADASHIV KATHANEPuravankara Limited19/08/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Aug 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Oct 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Oct 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Dec 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jan 2027

Documents filed126

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 126 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: 0733_001.pdf29 Sep 2026
Form 5 (FY 2025-2026)File: FORM 5-Aspire FY 2025-26.pdf29 Sep 2026
Withdrawal Update Form 1File: Form 1 SIgned.pdf1 Aug 2026
Withdrawal Update Form 2File: Form 2 Signed.pdf1 Aug 2026
Withdrawal Update Form 3File: Form 3.pdf1 Aug 2026
Withdrawal Update Form 1File: Architect Form 1 Q4.pdf22 May 2026
Withdrawal Update Form 2File: Form 2.pdf22 May 2026
Withdrawal Update Form 3File: CA Form 3 Q4_compressed.pdf22 May 2026
Withdrawal Update Form 1File: Form 1 Q3.pdf16 May 2026
Withdrawal Update Form 2File: Form 2.pdf16 May 2026
Withdrawal Update Form 3File: Form 3 Q3_compressed.pdf16 May 2026
Withdrawal Update Form 1File: Form 1.pdf30 Mar 2026
Withdrawal Update Form 2File: Form 2.pdf30 Mar 2026
Withdrawal Update Form 3File: Purva Aspire RERA Sep 25_compressed.pdf30 Mar 2026
Commencement certificateFile: mohan_BP_CC.pdf4 Dec 2025
Commencement certificateFile: mohan_DP_CC.pdf4 Dec 2025
Withdrawal Update Form 1File: Form 1.pdf4 Dec 2025
Withdrawal Update Form 2File: Form 2.pdf4 Dec 2025
Withdrawal Update Form 3File: Purva Aspire RERA Sep 25_compressed.pdf4 Dec 2025
Withdrawal Update Form 1File: adc3fcba-5d13-4c2d-8400-44ef7426027c.pdf6 Sep 2025
Withdrawal Update Form 2File: 4e9f475a-e205-4bed-8101-a825f782d658.pdf6 Sep 2025
Withdrawal Update Form 3File: Form 3 Aspire Q1.pdf6 Sep 2025
Withdrawal Update Form 1File: RERA Progress certificate Aspire -Q3 2023.pdf23 Aug 2025
Withdrawal Update Form 1File: adc3fcba-5d13-4c2d-8400-44ef7426027c.pdf23 Aug 2025
Withdrawal Update Form 2File: FORM-2, EC_PURVA ASPIRE_Q4_FY23-24.pdf23 Aug 2025
Withdrawal Update Form 2File: 4e9f475a-e205-4bed-8101-a825f782d658.pdf23 Aug 2025
Withdrawal Update Form 3File: Form 3 Latest Signed_compressed.pdf23 Aug 2025
Withdrawal Update Form 3File: Form 3 Latest Signed_compressed.pdf23 Aug 2025
Form 1File: Form 1 M 25.pdf12 Aug 2025
Form 2File: Form 2 M 25.pdf12 Aug 2025
Form 3File: Form 3 M 25.pdf12 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold M 25.pdf12 Aug 2025
Certificates of CA (Form 3)File: 0129_001_compressed.pdf29 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 0128_001.pdf29 May 2025
Disclosure of sold/ booked inventoryFile: Q4 Aspire_compressed.pdf26 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q3 Aspire.pdf23 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4 Aspire.pdf23 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Aspire.pdf23 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q4 Aspire.pdf23 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FOrm 2A.pdf23 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Aspire Form 7 2023-24.pdf22 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aspire Architect Certificate Mar-25_compressed.pdf9 May 2025
Certificates of CA (Form 3)File: Purva Aspire RERA FORM 3 Mar-25.pdf9 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aspire Engineer Certificate Q4 Mar25.pdf9 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aspire Architect Certificate-30 Jun24.pdf7 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aspire Architect Certificate Sep-24.pdf7 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aspire Architect Dec 24.pdf7 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aspire Architect Certificate Mar-25_compressed.pdf7 May 2025
Certificates of CA (Form 3)File: Aspire form-3 June 24.pdf7 May 2025
Certificates of CA (Form 3)File: Aspire form-3 Mr24.pdf7 May 2025
Certificates of CA (Form 3)File: Aspire form-3 Sep 24.pdf7 May 2025
Certificates of CA (Form 3)File: Purva Aspire RERA Dec-24.pdf7 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aspire Eng certificate Q1 Jun24.pdf7 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aspire Engineer Certificate Q2 Sep24.pdf7 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aspire Engineer Certificate Q3 Dec24.pdf7 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aspire Engineer Certificate Q4 Mar25.pdf7 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Progress certificate Aspire -Q3 2023.pdf4 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-6, EC_PURVA ASPIRE_Q2_FY23-24.pdf4 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2, EC_PURVA ASPIRE_Q3_FY23-24.pdf4 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2, EC_PURVA ASPIRE_Q4_FY23-24.pdf4 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf23 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf23 Apr 2024
Disclosure of sold/ booked inventoryFile: SOld Detail Aspire.pdf23 Apr 2024
Certificates of CA (Form 3)File: Form 3 Latest Signed_compressed.pdf23 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21.pdf23 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 19-20.pdf23 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf23 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Aspire - Form 2A - Quality Assurance Certificate Mar-22.pdf18 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Aspire - Form 2A - Quality Assurance Certificate Mar-23.PDF18 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Progress certificate Aspire -Q3 2023.pdf27 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-6, EC_PURVA ASPIRE_Q2_FY23-24.pdf27 Mar 2024
Certificates of CA (Form 3)File: Aspire Form 3 Dec 23.pdf27 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect progress certificate Aspire Q2 2023.pdf22 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Progress certificate Aspire -Q3 2023.pdf22 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5- Aspire FY 2022-23.pdf22 Feb 2024
Certificates of CA (Form 3)File: Purva Aspire_Form-3_Jun-23_sd.pdf25 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect RERA Progress certificate Aspire Q1.pdf10 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ASPIRE - RERA CERTIFICATES.pdf29 May 2023
Certificates of CA (Form 3)File: Form-3_Purva Aspire Q_4 Mar23.pdf29 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Purva Aspire Form -5 2018-19 sd.pdf20 Apr 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Purva Clermont Wing AP51800028571Ghatkopar Taluk, Deonar Village, Mumbai Suburban52Mar 2021OngoingJun 2027Not due yet

How this compares with Pune

58%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 49 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Purva Aspire on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bavdhan13,700+ in Pune

2 kmPurva AspireCompleted 74Lapsed / revoked 46Other 61Dot size: filed unitsN

Filed coordinates, straight-line distance. 181 registered projects within 2 km.

Builder: Puravankara Limited

Puravankara Limited has 7 registrations on MahaRERA, including Purva Aspire and Purva Clermont Wing A. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Purva Aspire is delayed beyond 30 Jan 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Purva Aspire?

The registered promoter entity is Puravankara Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Purva Aspire?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Purva Aspire?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Purva Aspire?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Purva Aspire?

The professionals named in the filing: Architect: Vilas Yele; Architect: Advantage Architects; Engineer: JW Consultants; Engineer: Synte Great PMC; Chartered Accountant: V D S R & CO LLP; Chartered Accountant: Ms Bhuvana Bhat and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Purva Aspire?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Purva Aspire. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Purva Aspire to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.