Completed No litigation declared Commercial project

Prozone Trade Centre

By Empire Mall Private Limited

RG-MH-01216 · RERA P51500003693 · Last updated on MahaRERA portal: 4 Apr 2023

Source: official MahaRERA filing

Red flags

  • 5 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Jun 2019Possession promisedregistration recorded completed
6 of 11Construction stages donefurthest along: Excavation, 0%
5Complaints at MahaRERAon this registration
Jump to the 21 documents Report an error

Prozone Trade Centre is a Commercial project by Empire Mall Private Limited in Aurangabad, Maharashtra, registered with MahaRERA as P51500003693 on 6 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2019. The completion date has moved by 12 months from the original filing. 5 complaints are on record with the regulator.

At a glance

Project

  • NameProzone Trade Centre
  • TypeCommercial
  • Location
    • Aurangabad
    • 431003
  • Pincode431003
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500003693
  • ReraGenie IDRG-MH-01216

Builder

  • NameEmpire Mall Private Limited
  • Entity typeCompany

Key dates

this monthRegisteredAug 2017First promiseJun 2018Revised toJun 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on6 Aug 2017
  • Promised completion30 Jun 2019
  • Revised completionRevised to 30 Jun 2019 (originally 30 Jun 2018)
  • Buildings1 building record
  • Documents filed21 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Prozone Trade CentreNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

Prozone Trade Centre: 55% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 4 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes96%
Storm Water DrainsYes96%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes96%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes96%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes96%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,245 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI16365.2
Proposed, not sanctioned15,536 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSwami Samarth Nagar, Lokhandwala Complex, Andheri West, Mumbai - 400053

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectManoj Kapurchand Kalal
EngineerCandG Building Consultancy pvt ltd
PartnerRole in project
Empire Mall Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51500000534Jun 2018 → Jun 2019

Reason as filed by the promoterRespected Sir/Madam, With reference to our project Prozone Trade Centre, registered with MAHARERA under registration number P51500003693, the project construction is complete and we are in the process of obtaining OC/ BCC. With reference to the same request you to extend the project validity by one year. Yours Faithfully, For Empire Mall Private Limited Lt Col Sudhanshu Chaturvedi (Retd.) Authorised Signatory

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC003000000000019Mahendra ShindeEmpire Mall Private Limited27/06/2018
CC003000000000020Amit ShahEmpire Mall Pvt. Ltd27/06/2018
CC003000000000038NANDLAL PANNALAL AGRAWALEmpire Mall Pvt.Ltd01/09/2018
CC003000000000039Girish Leeladhar MeisheriEmpire Mall Pvt.Ltd01/09/2018
CC12501669Ms A G Construction Through its Authorised Signatory Mohd Aslam Khan Mohd Arif KhanEmpire Mall Private Limited23/05/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Sep 2019

Documents filed21

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 PTC (new format).pdf4 Apr 2023
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 (new format) 310819.pdf28 May 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PTC OC 210918.pdf7 Sep 2019
Certificates of CA (Form 5)File: PTC Form 5 Mar18.pdf1 Oct 2018
OtherFile: PTC PART OC 210918.pdf1 Oct 2018
OtherFile: EMPL Declaration.pdf1 Oct 2018
Proforma of Allotment letterFile: 4 Proforma Agreement.pdf31 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: 9 PTC Commencement cert and Build approval.pdf11 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: 9 PTC Commencement cert and Build approval.pdf5 Apr 2018
Layout approvalFile: PTC Approved Layout.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: PTC Approved Layout.pdf29 Jul 2017
Declaration in FORM BFile: 5 Form B Affidavit.pdf29 Jul 2017
Building plan approvalFile: 9 PTC Commencement cert (Build approval) 2011.pdf28 Jul 2017
PAN CardFile: 1 PAN - Empire Mall.pdf28 Jul 2017
Copy of the legal title reportFile: 2 Title Search Report.pdf28 Jul 2017
Details of encumbrancesFile: 3 Land Encumbrance Certificate.pdf28 Jul 2017
Building Plan Approval (IOD)File: 9 PTC Commencement cert (Build approval) 2011.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 6 Form 1 Arch cert.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 8 PTC Form 2 Engineer Cert.pdf28 Jul 2017
Certificates of CA (Form 3)File: 7 PTC CA Certificate.pdf28 Jul 2017
Proforma of Allotment letterFile: 4 Proforma LOA and Agreement.pdf28 Jul 2017

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one moved by 12 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is completed

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep Prozone Trade Centre on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Aurangabad1,400+ in Aurangabad

Builder: Empire Mall Private Limited

Empire Mall Private Limited has 1 registration on MahaRERA, including Prozone Trade Centre. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if Prozone Trade Centre is delayed beyond 30 Jun 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Prozone Trade Centre?

The registered promoter entity is Empire Mall Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Prozone Trade Centre?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Prozone Trade Centre?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Prozone Trade Centre?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Prozone Trade Centre?

The professionals named in the filing: Architect: Manoj Kapurchand Kalal; Engineer: CandG Building Consultancy pvt ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Prozone Trade Centre?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Prozone Trade Centre. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Prozone Trade Centre to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.