Pradnyaraj Buds
RG-MH-15842 · RERA P52100024131 · Last updated on MahaRERA portal: 15 Apr 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 26 months past the filed date
- Completion date moved by 8 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Pradnyaraj Buds is a Residential / Group Housing project by Pradnyaraj Properties in Munurwar Housing Society, 411014, registered with MahaRERA as P52100024131 on 21 Jan 2020. Possession was promised by 12 Aug 2024 and is now 26 months past that date. The completion date has moved by 8 months from the original filing. 17 of the 24 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NamePradnyaraj Buds
- TypeResidential / Group Housing
- Location
- Munurwar Housing Society road
- Munurwar Housing Society
- 411014
- Pincode411014
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100024131
- ReraGenie IDRG-MH-15842
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on21 Jan 2020
- Promised completion12 Aug 2024
- Revised completionRevised to 12 Aug 2024 (originally 30 Dec 2023)
- Buildings1 building record
- Documents filed68 files
Current status
Figures as on 15 Apr 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Pradnyaraj Buds | NA | 5 | 0 | 24 | 0 | 24 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 15 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.
Pradnyaraj Buds: 68% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Progress on shared amenities15
As on 15 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 50% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Pradnyaraj Buds | NA | Rs 3.07 cr | Rs 2.38 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ankur Associates |
| Engineer | Mr. Sagar Jadhav Jadhav |
| Chartered Accountant | Khandekar & Associates |
| Chartered Accountant | Vyankatesh V Joshi & Co. |
| Partner | Role in project |
|---|---|
| Pradnyaraj Properties | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Project is in the final stages and not complete yet due to some unenforceable delays, and we cannot get the OC issued before the due date of validity. Hence, we need more time to complete the Project. Rest assured, we are nearing the completion of the Project, and need some more time to complete the Project work. Therefore, we hereby apply for extension of Project Registration validity till 30/06/2024. Hence, we kindly request you to grant us the extension so that we can complete the project.
Reason as filed by the promoterIt got delayed in completing process and procuring the OC by couple of months. Hence, we seeked backdated extension till the date of OC (Occupancy Certificate) and accordingly have sent mail to MahaRERA helpdesk. After brief discussion with them they forwarded the mail to Hon’ble Secretary and he freezed the date. We hereby applying for the Extension till OC date i.e. 12-08-2024 u/s. 7(3) and request to grant us the extension till said date. No option to choose Sec. 7(3) as the extension is Post-facto extension and the field to choose 7 (3) id freezed. Hence, We hereby again state and declare
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 13 Jan 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 May 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 May 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 May 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 29 Oct 2024
Documents filed68
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Declaration in FORM BFile: Form B - Affidavit cum Declaration 12_8_24 (1).pdf | 15 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Booked inventory.pdf | 15 Apr 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: Final Form 4 Pradnyaraj Buds.pdf | 29 Oct 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Pradnyaraj Buds Final Completion Certificate B wing.pdf | 29 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - Quality Assessment (P Buds) Apr 21-Mar 22.pdf | 22 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - Annual Report by CA (P Buds) Apr 21-Mar 22 (1).pdf | 22 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 20 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Certificate of Project Engineer.pdf | 20 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf | 20 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Certificate of CA.pdf | 20 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Q1 23-24.pdf | 13 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Q1 23-24.pdf | 13 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold _ Booked Inventory.pdf | 13 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 C A Q1 23-24.pdf | 13 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (Architect).pdf | 25 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (Architect) (2).pdf | 25 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (Architect).pdf | 25 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 (Engineer) (2).pdf | 25 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 (Engineer).pdf | 25 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 (Engineer).pdf | 25 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 A (Engineer)2022-23.pdf | 25 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Flats (Sept 2022).pdf | 25 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Flats (March23).pdf | 25 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (CA) (Q2).pdf | 25 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (CA) (Q3).pdf | 25 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (CA) (Q4).pdf | 25 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 (CA) 2022-23.pdf | 25 Jul 2023 |
| Layout approvalFile: Layout HPSC1868 2.pdf | 27 May 2022 |
| Building plan approvalFile: Sanctioned Plan 1:2 HPSC1870 2.pdf | 27 May 2022 |
| Building plan approvalFile: Sanctioned Plan 2:2 HPSC1869 2.pdf | 27 May 2022 |
| Copy of Layout Approval (in case of layout)File: Layout HPSC1868 2.pdf | 27 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Sanctioned Plan 1:2 HPSC1870 2.pdf | 27 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Sanctioned Plan 2:2 HPSC1869 2.pdf | 27 May 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencment Certificate | 2.pdf | 27 May 2022 |
| CERSAI detailsFile: CERSAI Details Pradnyaraj Buds 2.pdf | 24 May 2022 |
| CERSAI detailsFile: CERSAI Details Pradnyaraj Buds 3.pdf | 24 May 2022 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate | Format - D.pdf | 18 May 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect 2.pdf | 18 May 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate 2.pdf | 18 May 2022 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold : Booked Inventory.pdf | 18 May 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Buds Form 3 (CA) 2.pdf | 18 May 2022 |
| Declaration about Commencement CertificateFile: Declaration of Commencement Certificate.pdf | 20 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A - Quality Assessment (P Buds) Jan-Mar 20.pdf | 20 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - Quality Assessment (P Buds) Apr-Jun 20.pdf | 20 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - Quality Assessment (P Buds) Jul-Sept 20.pdf | 20 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - Quality Assessment (P Buds) Oct-Dec 20.pdf | 20 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - Quality Assessment (P Buds) Jan-Mar 21.pdf | 20 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - Quality Assessment (P Buds) Jan-Mar 21.pdf | 20 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - Quality Assessment (P Buds) Jan-Mar 21.pdf | 20 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure Of Sold _ Booked Inventory.pdf | 20 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - Annual Report by CA (P Buds) 19-20.pdf | 20 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - Annual Report by CA (P Buds) 20-21.pdf | 20 Aug 2021 |
| Proforma of Allotment letterFile: Buds Flat Allotment Letter_20200116190139 (1).pdf | 16 Jan 2020 |
| Copy of the legal title reportFile: Final Search and Tital Report Bande (compressed further).pdf | 13 Jan 2020 |
| Proforma of Allotment letterFile: Final Agreement For Sale Demo Draft.pdf | 13 Jan 2020 |
| Layout approvalFile: Blue Print.pdf | 11 Jan 2020 |
| Building plan approvalFile: N A Order.pdf | 11 Jan 2020 |
| PAN CardFile: Pan Card.pdf | 11 Jan 2020 |
| Details of encumbrancesFile: Declaration Encumbrances.pdf | 11 Jan 2020 |
| Copy of Layout Approval (in case of layout)File: Blue Print.pdf | 11 Jan 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: N A Order.pdf | 11 Jan 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencment Letter.pdf | 11 Jan 2020 |
| Declaration in FORM BFile: Form B- Declaration.pdf | 11 Jan 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Arcitect Certificate.pdf | 11 Jan 2020 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineers Certificate.pdf | 11 Jan 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3 Project Report.pdf | 11 Jan 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: ITR AY 2018 - 2019.pdf | 11 Jan 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: ITR AY 2019 - 2020.pdf | 11 Jan 2020 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Nirmitee Enclave | Plot no 39 Dighi Pune 411019 | 8 | Completed | Jun 2015 | Jun 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 68 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Pradnyaraj Buds on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Munurwar Housing Society
Filed coordinates, straight-line distance. 109 registered projects within 2 km.
VJ IndiLife Kharadi
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
VJ Central Avenue
Vilas Javdekar Eco Homes
VJ IndiWorks Kharadi Central
Vilas Javdekar Eco Homes
RIVERDALE GRAND
DUVILLE ESTATES PRIVATE LIMITED
Yashwin Orizzonte Phase II
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
ZEN ESTATE
DESTINATION KHARADI DEVELOPERS LLP
Builder: Pradnyaraj Properties
Pradnyaraj Properties has 3 registrations on MahaRERA, including Pradnyaraj Lotus and Pradnyaraj Buds. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record.
Frequently asked questions
What does it mean that Pradnyaraj Buds shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Pradnyaraj Buds is delayed beyond 12 Aug 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Pradnyaraj Buds?
The registered promoter entity is Pradnyaraj Properties, a partnership as per the filing. Its GSTIN 27AAOFP3441N1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Pradnyaraj Buds?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Pradnyaraj Buds?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Pradnyaraj Buds?
The professionals named in the filing: Architect: Ankur Associates; Engineer: Mr. Sagar Jadhav Jadhav; Chartered Accountant: Khandekar & Associates; Chartered Accountant: Vyankatesh V Joshi & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Pradnyaraj Buds?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback