Home / Browse projects / Thane, Maharashtra / PODDAR WONDERCITY PHASE - II
PODDAR WONDERCITY PHASE - II
By Poddar Housing and Development Limited
RG-MH-02816 · RERA P51700020028 · Last updated on MahaRERA portal: 28 Apr 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 28 months past the filed date
- 23 complaints at MahaRERA
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PODDAR WONDERCITY PHASE - II is a Residential / Group Housing project by Poddar Housing and Development Limited in Thane, Maharashtra, registered with MahaRERA as P51700020028 on 19 Mar 2019. Possession was promised by 30 Jun 2024 and is now 28 months past that date. The completion date has moved by 24 months from the original filing. 23 complaints are on record with the regulator.
At a glance
Project
- NamePODDAR WONDERCITY PHASE - II
- TypeResidential / Group Housing
- Location
- -
- JOVELI VILLAGE
- Badlapur (M Cl)
- Ambarnath
- Thane
- 421503
- Pincode421503
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700020028
- ReraGenie IDRG-MH-02816
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on19 Mar 2019
- Promised completion30 Jun 2024
- Revised completionRevised to 30 Jun 2024 (originally 30 Jun 2022)
- Buildings3 building records
- Documents filed88 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| B4 | NA | 25 | 0 | 0 | 0 | 0 |
| B5 | NA | 25 | 0 | 0 | 0 | 0 |
| B6 | NA | 25 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 28 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
12 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 50%.
B441%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 43% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 3% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B541%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 50% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 5% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B641%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 44% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 10% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities24
As on 28 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
| Organic farm Patch / Horticulture, Petting Zoo, Barbeque Area, Skating Rink, Café | Yes | 0% |
| Senior Citizens Corner, Dominos Tables, Dart Board, Yoga Corner/Room/Aerobic Room/Meditation Area | Yes | 0% |
| Open Air Gymnasium, Jogging/Walking Track, Picnic Area/Event Space & Arena/Activity Deck/Park | Yes | 0% |
| Neighbourhood Retail, Giant Jenga Play Area, Giant Chess Play Area, Outdoor games tables with boards | Yes | 0% |
| Mini Football Ground, Cricket Pitches, Tennis, Volleyball and Basketball Court / Multi Purpose Court | Yes | 0% |
| Kids Play Area | Yes | 0% |
| Club House Indoor Games - Table Tennis, Chess & Carom Room, Pool, Cards, Health Club | Yes | 0% |
| Club House - Mini Cinema Theater, Library, Banquet / Multipurpose Town Hall, Gymnasium | Yes | 0% |
| Swimming Pool Adult and Kids | Yes | 0% |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ARCHITECT HAFEEZ CONTRACTOR |
| Architect | ubarchitects |
| Engineer | Chetan Kubal |
| Chartered Accountant | Bansal Bansal & Company |
| Chartered Accountant | M. S. Bajaj & Co. |
| Chartered Accountant | V A SHIMPI & ASSOCIATES |
| Partner | Role in project |
|---|---|
| Poddar Housing and Development Limited | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDear Sir With reference to our ongoing real estate project Poddar Wondercity Phase II situated at Village Joveli, Taluka Ambarnath, District Thane in respect of for building no 2 (Wing B4, B5 & B6) which is registered under MahaRERA under registration number P51700020028 & the said registration is valid till 30-Jun-22 Please Note till date construction of the Project reached Wing/Building B4, B6 upto 2nd slab & B5 upto 3rd slab & we have 69 registered allottees in the Project. Enclosed a list of all registered 69 allottees We propose Layout revisions of Project by making changes sanctioned pla
Complaints filed with MahaRERA23
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000408530 | SWAPNALI AJAY BETKAR | PODDAR WONDERCITY | 09/01/2024 |
| CC12400790 | Pramod Suhas Dhende | Poddar Housing and Development Limited | 15/11/2024 |
| CC12401007 | RAMESH SAHADEV JADHAV | Poddar Housing and Development Limited | 04/12/2024 |
| CC12401008 | Amol Ravaso Vichare | Poddar Housing and Development Limited | 04/12/2024 |
| CC12401009 | Adesh Shankar Ghatage | Poddar Housing and Development Limited | 04/12/2024 |
| CC12504407 | Swapnil Pandurang Adsul | Swapnil Adsul | 11/12/2025 |
| CC12401199 | Pinkukumar Shivkumar Jaiswal | Poddar Housing and Development Limited | 21/12/2024 |
| CC12401272 | Sunil Laxminarayan Pandey | Poddar Housing and Development Limited | 29/12/2024 |
| CC12500513 | BANDU DAGDU PANDIT | Poddar Housing and Development Limited | 14/02/2025 |
| CC12500493 | Nityanand Nawale | Poddar Housing and Development Limited | 14/02/2025 |
| CC12500529 | MAHESH GUNDU CHIMANE | Poddar Housing and Development Limited | 15/02/2025 |
| CC12502056 | MANOJ CHAMPAKLAL DEORA | Poddar Housing and Development Limited | 24/06/2025 |
| CC12502564 | Amar Prakash Pawar | Poddar Housing and Development Limited | 25/07/2025 |
| CC12502961 | Srishti S Saha | Poddar Housing and Development Limited | 22/08/2025 |
| CC12504595 | Aditi Suhas Dalvi | Poddar Housing and Development Limited | 23/12/2025 |
| CC12600439 | Rajesh Anil Badadhe | Poddar Housing and Development Limited | 23/01/2026 |
| CC12600768 | Amar balaji Pannase | Poddar Housing and Development Limited | 10/02/2026 |
| CC12600165 | DIVYA DIGAMBER DALVI | Poddar Housing and Development Limited | 10/01/2026 |
| CC12602436 | Diana Leona Abel | Poddar Housing and Development Limited | 26/04/2026 |
| CC12602423 | MANOJ CHAMPAKLAL DEORA | Poddar Housing and Development Limited | 25/04/2026 |
| CC12602425 | MANOJ CHAMPAKLAL DEORA | Poddar Housing and Development Limited | 25/04/2026 |
| CC12602444 | Adesh Shankar Ghatage | Poddar Housing and Development Limited | 26/04/2026 |
| CC12602555 | Sneha Kiran Naik | Poddar Housing and Development Limited | 01/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 1 Mar 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Sep 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Mar 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed88
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engin PW II Sept 22.pdf | 28 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Wcity PH II 22-23.pdf | 28 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Poddar Wondercity Phase-II - Form 2A Quality Certificate_Mar-22.pdf | 14 Mar 2023 |
| Certificates of CA (Form 3)File: PHDL WONDERCITY PHASE II RERA Sept 22.pdf | 15 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Wcity II Engineering Mar 22.PDF | 13 Oct 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Wcity II Engineering June 22.PDF | 13 Oct 2022 |
| Certificates of CA (Form 3)File: RERA June 2022 Wondercity Ph II.pdf | 22 Sep 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Wcity PH II Mar 22.pdf | 8 Aug 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Wcity PH II June 22.pdf | 8 Aug 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: WonderCity PH II Engineer Mar 22.pdf | 8 Aug 2022 |
| Certificates of CA (Form 3)File: Wonder City Cert -2.pdf | 3 Aug 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: WCity PH II Archtiect Dec 21.pdf | 4 May 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate WCITY PH II Dec 21.pdf | 4 May 2022 |
| Certificates of CA (Form 3)File: Wonder City Phase-2 (1).pdf | 16 Apr 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Wonder City Badlapur Phase II - FORM 1 - ARCHITECT'S CERTIFICATE 30-09-2021 (1).pdf | 7 Jan 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Wonder city Phase II (1).pdf | 7 Jan 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 0277_220104182018_001.pdf | 5 Jan 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 0278_220104182040_001.pdf | 5 Jan 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 0302_220105165324_001.pdf | 5 Jan 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Wonder City Badlapur Phase II - FORM 1 - ARCHITECT'S CERTIFICATE 30-06-2021.pdf | 4 Jan 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: WONDERCITY PH II Engineer JUNE-2021.pdf | 4 Jan 2022 |
| Certificates of CA (Form 3)File: 2021 10 14 PG PHDL WONDER CITY RERA JUNE 2021 PHASE II.pdf | 9 Dec 2021 |
| Proforma of Allotment letterFile: AFS post new approvals Wondercity Phase II.pdf | 11 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Wondercity II_Compressed.pdf | 28 Sep 2021 |
| Layout approvalFile: UDCPR Layout Approval.pdf | 17 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: UDCPR Layout Approval.pdf | 17 Sep 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: UDCPR CC.pdf | 17 Sep 2021 |
| Declaration about Commencement CertificateFile: Format D_Declaration about CC.pdf | 26 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked Inventory Circular No 29_Disclosure of sold_booked inventory.pdf | 26 Aug 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Wonder City Badlapur Phase II - FORM 1 - ARCHITECT'S CERTIFICATE 31-03-2021.pdf | 14 Jul 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Form-2_Engineers Certificate_Poddar Wondercity - II_Mar-21.pdf | 14 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Poddar Wondercity Phase_II_Form 2A Quality Mar-21.pdf | 14 Jul 2021 |
| Certificates of CA (Form 3)File: 2021 07 13 PG PHDL WONDERCITY RERA MARCH 2021- PHASE II.pdf | 14 Jul 2021 |
| Details of encumbrancesFile: Encumbrance_Phase - II.pdf | 1 Jun 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PW PH2.pdf | 4 Mar 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality certificate - all RERA project - PHDL-4 - PW 2.pdf | 4 Mar 2021 |
| Certificates of CA (Form 3)File: PHDL PW PhII FORM3.pdf | 3 Mar 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Wonder City Badlapur Phase II - FORM 1 - ARCHITECT'S CERTIFICATE 31-12-2020-compressed.pdf | 2 Mar 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PW Ph2.pdf | 4 Jan 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PW Ph2.pdf | 4 Jan 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: PW Ph2.pdf | 4 Jan 2021 |
| Certificates of CA (Form 3)File: Wonder city Ph 2.pdf | 4 Jan 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Ph 2.pdf | 7 Oct 2020 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: PW Ph2.pdf | 7 Oct 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PW Ph2.pdf | 1 Oct 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PW Ph2.pdf | 1 Oct 2020 |
| Certificates of CA (Form 3)File: 2020 09 16 PHDL WONDERCITY RERA JUNE 2020 PHASE II.pdf | 1 Oct 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Wondercity Ph II.pdf | 30 Sep 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Wondercity Ph II.pdf | 30 Sep 2020 |
| Certificates of CA (Form 3)File: 2020 09 09 PHDL WONDERCITY RERA MARCH 2020 PHASE II.pdf | 30 Sep 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Certificate WC 2-min.pdf | 30 Sep 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: Poddar Wondercity_Further CC upto 20th Floor.pdf | 10 Jul 2020 |
| Details of Restarting of Construction work post lockdownFile: PODDAR WONDERCITY PHASE - II.pdf | 26 Jun 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Wonder City Badlapur Phase II - FORM 1.pdf | 4 Mar 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate PH-2.pdf | 4 Mar 2020 |
| Certificates of CA (Form 3)File: Wonder City Phase 2.pdf | 4 Mar 2020 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: PODDAR WONDERCITY PHASE - II - B4,B5,B6 Jun-19.pdf | 7 Jan 2020 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: PODDAR WONDERCITY PHASE - II - B4,B5,B6 Sep-19.pdf | 7 Jan 2020 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: PODDAR WONDERCITY PHASE - II - B4,B5,B6 Dec-19.pdf | 7 Jan 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Wonder City Badlapur Phase II - FORM 1 - ARCHITECT'S CERTIFICATE 30-09-2019.pdf | 18 Dec 2019 |
| Proforma of Allotment letterFile: 10 Allotement letter declaration_Poddar Wondercity.pdf | 12 Dec 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2019 12 08 PHDL WONDERCITY RERA FORM 2 PH-2.pdf | 11 Dec 2019 |
| Certificates of CA (Form 3)File: 2019 12 08 PHDL WONDERCITY RERA FORM 3 PH-2.pdf | 11 Dec 2019 |
| Details of encumbrancesFile: Encumbrance_Phase - II.pdf | 9 Dec 2019 |
| Declaration in FORM BFile: Form B - PHASE-II.pdf | 9 Dec 2019 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Wonder City Badlapur Phase II - FORM 1 - ARCHITECT'S CERTIFICATE 31-03-2019_Min.pdf | 4 Oct 2019 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Wonder City Badlapur Phase II - FORM 1 - ARCHITECT'S CERTIFICATE 30-06-2019_Min.pdf | 4 Oct 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate Phase - II.pdf | 1 Oct 2019 |
| Certificates of CA (Form 3)File: CA Certificate - Form 3 - Phase II-min.pdf | 1 Oct 2019 |
| Annual Audit Report of Statutory CA (Form 5)File: Wondercity II_Form 5.pdf | 20 Sep 2019 |
| Proforma of Allotment letterFile: B 4 to B 6 RERA Agreement Wondercity_Final-Aug-19.pdf | 1 Aug 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Wondercity PH-II.pdf | 6 Jul 2019 |
| Certificates of CA (Form 3)File: Certificates of CA PHDL WONDERCITY PH-II.pdf | 6 Jul 2019 |
| OtherFile: Poddar Wondercity Environment Clearance.pdf | 29 May 2019 |
| Building plan approvalFile: IOD.pdf | 16 Mar 2019 |
| Building Plan Approval (IOD)File: IOD.pdf | 16 Mar 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 16 Mar 2019 |
| Declaration in FORM BFile: Poddar Wondercity 2 - New.pdf | 12 Mar 2019 |
| Layout approvalFile: Layout Approval.pdf | 8 Mar 2019 |
| Copy of Layout Approval (in case of layout)File: Layout Approval.pdf | 8 Mar 2019 |
Promoter's earlier projects10
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| PODDAR RIVIERA PHASE - IP51700023508 | MHARAL, Thane | 720 | Dec 2019 | Ongoing | Sep 2025 | Not delivered |
| SAMRUDDHI EVERGREENS-PHASE-4B | BADLAPUR | 178 | - | Completed | Mar 2019 | Aug 2018 |
| SAMRUDDHI EVERGREENS-PHASE-4A | BADLAPUR | 160 | - | Completed | Mar 2018 | Mar 2018 |
| PODDAR EVERGREEN PHASE 3 | BADLAPUR | 796 | - | Completed | Dec 2015 | Late, Mar 2016 |
| PODDAR BRIO INTERNATIONAL SCHOOL | BADLAPUR | - | - | Completed | Aug 2015 | Aug 2015 |
| CENTRAL HOSPITAL | BADLAPUR | - | - | Completed | Mar 2015 | Mar 2015 |
| PODDAR EVERGREEN PHASE 2 | BADLAPUR | 672 | - | Completed | Dec 2014 | Dec 2014 |
| SAMRUDDHI COMPLEX | BHIVPURI KARJAT | 1,264 | - | Completed | Apr 2014 | Apr 2014 |
| SAMRUDDHI COMMERCIAL COMPLEX | BHIVPURI KARJAT | 45 | - | Completed | Apr 2014 | Apr 2014 |
| PODDAR EVERGREEN PHASE 1 | BADLAPUR | 516 | - | Completed | Aug 2013 | Aug 2013 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 12 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 88 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep PODDAR WONDERCITY PHASE - II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near JOVELI VILLAGE7,600+ in Thane
Filed coordinates, straight-line distance. 394 registered projects within 2 km.
PRADHAN MANTRI AWAS YOJANA - URBAN
KULGAON BADLAPUR MUNICIPAL COUNCIL
Mohan Alcoves I
MOHAN LIFESPACES LLP
MANOHAR VIKAS SHREEJI PARAISO PHASE - 2
DEEPLAXMI DEVELOPERS
SHREEJI MILESTONE
DEEP LAXMI ASSOCIATES
Mohan Willows III
MOHAN LIFESPACES LLP
SHREEJI SQUARE PHASE I
SHREEJI DEVELOPERS
See every Thane project, with the district possession charts
Builder: Poddar Housing and Development Limited
Poddar Housing and Development Limited has 13 registrations on MahaRERA, including PODDAR SPRAHA DIAMOND PHASE-I and SAMRUDDHI EVERGREENS-PHASE-4A. Its filings disclose 11 earlier MahaRERA projects: declares 8 of 9 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that PODDAR WONDERCITY PHASE - II shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if PODDAR WONDERCITY PHASE - II is delayed beyond 30 Jun 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PODDAR WONDERCITY PHASE - II?
The registered promoter entity is Poddar Housing and Development Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PODDAR WONDERCITY PHASE - II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against PODDAR WONDERCITY PHASE - II?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for PODDAR WONDERCITY PHASE - II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PODDAR WONDERCITY PHASE - II?
The professionals named in the filing: Architect: ARCHITECT HAFEEZ CONTRACTOR; Architect: ubarchitects; Engineer: Chetan Kubal; Chartered Accountant: Bansal Bansal & Company; Chartered Accountant: M. S. Bajaj & Co.; Chartered Accountant: V A SHIMPI & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PODDAR WONDERCITY PHASE - II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback