Poddar Housing and Development Limited: RERA track record
Company ยท attribution by exact filing name, entity resolution in progress
Poddar Housing and Development Limited has 13 registrations on MahaRERA, including PODDAR SPRAHA DIAMOND PHASE-I and SAMRUDDHI EVERGREENS-PHASE-4A. Its filings disclose 11 earlier MahaRERA projects: declares 8 of 9 past projects completed on time.
Projects by this developer
Showing all 13 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| PODDAR RIVIERA PHASE - IP51700023508 | MHARAL, Thane, 421301 | 720 | 62% | 18 Dec 2019 | Registration lapsed |
| PODDAR RIVIERA PHASE - IIIP51700023296 | MHARAL, Thane, 421301 | 675 | 8% | 9 Dec 2019 | Registered |
| PODDAR RIVIERA PHASE - IIP51700023181 | MHARAL, Thane, 421301 | 338 | 0% | 5 Dec 2019 | Registered |
| PODDAR SPRAHA DIAMOND PHASE-IP51900002986 | Subhash Nagar, Mumbai City, 400071 | - | - | 4 Aug 2017 | Registration lapsed |
| PODDAR WONDERCITY PHASE - IP51700020032 | JOVELI VILLAGE, Thane, 421503 | - | - | 19 Mar 2019 | Registration lapsed |
| PODDAR WONDERCITY PHASE - IIP51700020028 | JOVELI VILLAGE, Thane, 421503 | - | - | 19 Mar 2019 | Registration lapsed |
| PODDAR WONDERCITY PHASE - IIIP51700020038 | JOVELI VILLAGE, Thane, 421503 | - | - | 19 Mar 2019 | Registration lapsed |
| PODDAR WONDERCITY PHASE - IVP51700020041 | JOVELI VILLAGE, Thane, 421503 | - | - | 19 Mar 2019 | Registration lapsed |
| PODDAR WONDERCITY PHASE - VP51700020067 | JOVELI VILLAGE, Thane, 421503 | - | - | 25 Mar 2019 | Registration lapsed |
| PODDAR WONDERCITY PHASE - VIP51700020027 | JOVELI VILALGE, Thane, 421503 | - | - | 19 Mar 2019 | Registration lapsed |
| SAMRUDDHI EVERGREEN-PHASE-4BP51700009016 | Badlapur (M Cl), Thane, 421503 | - | - | 19 Aug 2017 | Completed |
| SAMRUDDHI EVERGREENS PHASE-4CP51700009156 | -, Thane, 421503 | - | - | 19 Aug 2017 | Registration lapsed |
| SAMRUDDHI EVERGREENS-PHASE-4AP51700009407 | Badlapur (M Cl), Thane, 421503 | - | - | 22 Aug 2017 | Completed |
What this promoter declares as its own experience
Poddar Housing and Development Limited declares experience on 11 earlier projects. 2 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
2 of these declarations can be compared with the dates those projects' own registrations hold. Every one of them gives the same original completion date its registration holds.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| PODDAR EVERGREEN PHASE 1 | 31 Aug 2013 | 31 Aug 2013 | On time |
| SAMRUDDHI COMPLEX | 30 Apr 2014 | 30 Apr 2014 | On time |
| SAMRUDDHI COMMERCIAL COMPLEX | 30 Apr 2014 | 30 Apr 2014 | On time |
| PODDAR EVERGREEN PHASE 2 | 31 Dec 2014 | 31 Dec 2014 | On time |
| CENTRAL HOSPITAL | 19 Mar 2015 | 19 Mar 2015 | On time |
| PODDAR BRIO INTERNATIONAL SCHOOL | 31 Aug 2015 | 13 Aug 2015 | On time |
| PODDAR EVERGREEN PHASE 3 | 31 Dec 2015 | 31 Mar 2016 | +3 months |
| SAMRUDDHI EVERGREENS-PHASE-4A | 31 Mar 2018 | 5 Mar 2018 | On time |
| SAMRUDDHI EVERGREENS-PHASE-4B | 31 Mar 2019 | 17 Aug 2018 | On time |
| PODDAR WONDERCITY PHASE - II P51700020028 | 30 Jun 2022 | Not completed yet | Certificate Signed |
| PODDAR RIVIERA PHASE - I P51700023508 | 30 Sep 2025 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify Poddar Housing and Development Limited as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Poddar Housing and Development Limited?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.