Home / Browse projects / Thane, Maharashtra / PODDAR RIVIERA PHASE - II

Registered No litigation declared Residential / Group Housing project

PODDAR RIVIERA PHASE - II

By Poddar Housing and Development Limited

RG-MH-21661 · RERA P51700023181 · Last updated on MahaRERA portal: 28 Apr 2023

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
0 of 22Construction stages doneacross 2 buildings; furthest along: Excavation, 0%
338 of 338Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 72 documents Report an error

PODDAR RIVIERA PHASE - II is a Residential / Group Housing project by Poddar Housing and Development Limited in Thane, Maharashtra, registered with MahaRERA as P51700023181 on 5 Dec 2019. Possession is promised by 30 Dec 2026. 0 of the 338 units on this registration are recorded sold or booked, and 0 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NamePODDAR RIVIERA PHASE - II
  • TypeResidential / Group Housing
  • Location
    • KALYAN MURBAD ROAD
    • MHARAL
    • Mharal Kh. (N.V)
    • Kalyan
    • Thane
    • 421301
  • Pincode421301
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700023181
  • ReraGenie IDRG-MH-21661

Builder

  • NamePoddar Housing and Development Limited
  • Entity typeCompany
  • ChairpersonDipak Kumar Poddar
  • Managing DirectorRohitashwa Poddar
  • Other registrations12 more →
  • Completed2 of 13
  • No longer live9 lapsed, de-registered or revoked
  • Declared earlier projects11 →

Key dates

this monthRegisteredDec 2019PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on5 Dec 2019
  • Promised completion30 Dec 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed72 files

Current status

0%0 of 338 units booked

Figures as on 28 Apr 2023, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C3NA25231690169
C4NA25231690169

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 28 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 0%.

C30%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C40%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities25

As on 28 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%
Senior citizens’ corner, Jogging / walking trackYes0%
Swimming pool Adult pool, Kids pool, JacuzziYes0%
Terrace party area on clubYes0%
Fishing, Amphitheatre, Outdoor organic farm patchYes0%
Open air gym, Giant Jenga, Giant chess play areaYes0%
Multipurpose ground, Tennis court, Cricket pitchYes0%
Kids play area, Barbeque areaYes0%
Indoor games Pool, Table tennis, Chess, CaromYes0%
Club Gym, Open crècheYes0%
Banquet, Party LawnYes0%

Parking filed130

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots130
Closed/Covered130
BuildingClosed/CoveredTotal
C36565
C46565

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,291 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI14201.6
Proposed, not sanctioned9,844 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJEHANGIR BUILDING, M G ROAD, FORT, MUMBAI 400001

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARCHITECT HAFEEZ CONTRACTOR
Architectubarchitects
EngineerChetan Kubal
Chartered AccountantBansal Bansal & Company
Chartered AccountantM. S. Bajaj & Co.
Chartered AccountantV A SHIMPI & ASSOCIATES
PartnerRole in project
Poddar Housing and Development Limited-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000408554Manish Vinodrai MehtaPoddar Housing and Development Ltd.19/12/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Nov 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Mar 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Feb 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Feb 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2026

Documents filed72

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Riviera II Dec 21.pdf28 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engin Riviera II Sept 22.pdf28 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Riviera PH II 2021-22.pdf28 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Rivera PH II 22-23.pdf28 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Riviera RERA Sept 22 Phase II.pdf15 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Riviera PH II Form V 2021-22.pdf13 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Engineer Certificate_Riviera Phase-II_June 22.pdf22 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_Riviera Phase-II_March 22.pdf22 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_Riviera Phase-II_June 22.pdf22 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Riviera RERA June 22 Phase II.pdf22 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Riviera PH II Mar 22.pdf8 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Riviera PH II June 22.pdf8 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Riviera 2.pdf3 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Riviera Mharal Phase II - FORM 1 - ARCHITECT'S CERTIFICATE 30-12-2021 (1).pdf1 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Riviera PH II Qualtity.pdf1 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Riviera RERA PH II Dec 21.pdf1 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Riviera Mharal Phase II - FORM 1 - ARCHITECT'S CERTIFICATE 30-09-2021 (1).pdf7 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Riviera Phase II.pdf7 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 0283_220104182226_001.pdf5 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 0297_220105165139_001.pdf5 Jan 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Riviera PH II RERA Sept 2021.pdf5 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Riviera Mharal Phase II - FORM 1 - ARCHITECT'S CERTIFICATE 30-06-2021 (1) (1).pdf4 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate_PHASE - II.pdf4 Jan 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2021 10 14 PG PHDL RIVIERA RERA JUNE 2021 PHASE II.pdf9 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Rivera II_Compressed.pdf28 Sep 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Riviera Mharal Phase II - FORM 1 - ARCHITECT'S CERTIFICATE 31-03-2021.pdf14 Jul 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA Form-2_Engineers Certificate_Poddar Riviera - II_Mar-21.pdf14 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Poddar Riviera Phase_II_Form 2A Quality Mar-21.pdf14 Jul 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2021 07 13 PG PHDL RIVIERA PH II RERA MARCH 2021.pdf14 Jul 2021
Layout approvalFile: Layout Approval.pdf23 Mar 2021
Copy of Layout Approval (in case of layout)File: Layout Approval.pdf23 Mar 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Riviera - Phase 2.pdf4 Mar 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality certificate - all RERA project - PHDL-10 - Riv 2.pdf4 Mar 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: PHDL Riviera Ph II FORM3.pdf3 Mar 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Riviera Mharal Phase II - FORM 1 - ARCHITECT'S CERTIFICATE 31-12-2020-compressed.pdf2 Mar 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Riviera Mharal Phase II.pdf4 Jan 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Riviera Ph2.pdf4 Jan 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Rivera Ph2.pdf4 Jan 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: REVIERA PHASE II SEPT.pdf4 Jan 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Poddar Riviera PH-II Form 2 A_Certificate_March-20 ending.pdf7 Oct 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Ph 2.pdf7 Oct 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rivera Ph 2.pdf1 Oct 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rivera Ph2.pdf1 Oct 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2020 09 15 PHDL RIVIERA RERA JUNE 2020 PHASE II DS.pdf1 Oct 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Riviera Ph II.pdf30 Sep 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rivera Ph II.pdf30 Sep 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2020 09 09 PHDL WONDERCITY RERA MARCH 2020 PHASE II.pdf30 Sep 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Certificate Riveria Phase 2-min.pdf30 Sep 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Poddar Riviera PH-II Form 2 A_Certificate_March-20 ending.pdf17 Aug 2020
Details of Restarting of Construction work post lockdownFile: PODDAR RIVIERA PHASE - II.pdf26 Jun 2020
Layout approvalFile: Copy of Layout Approval_V1_reduced.pdf13 Apr 2020
Copy of Layout Approval (in case of layout)File: Copy of Layout Approval_V1_reduced.pdf13 Apr 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Riviera Mharal Phase II - FORM 1v1.pdf9 Mar 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate PH-2 - RIVIERA.pdf9 Mar 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Riviera Phase 2.pdf9 Mar 2020
Building plan approvalFile: 7 Mharal IOA 13-02-2020_REDUCED.pdf13 Feb 2020
Building Plan Approval / NA Order for plotted developmentFile: 7 Mharal IOA 13-02-2020_REDUCED.pdf13 Feb 2020
Commencement Certificates / NA Order for plotted developmentFile: 9 Mharal CC 13-02-2020_REDUCED.pdf13 Feb 2020
Proforma of Allotment letterFile: NON PMAY Draft Agreement for Sale Mharal_AJ_Area updated_C3,C4.pdf9 Dec 2019
Proforma of Allotment letterFile: Draft Agreement for Sale Mharal_NON PMAY_V1.pdf2 Dec 2019
Copy of the legal title reportFile: Mharal Memo on Title by DSK Legal.pdf27 Nov 2019
Layout approvalFile: 4 Copy of Layout Approvals_Reduced.pdf22 Nov 2019
Building plan approvalFile: 5 MHARAL IOA LETTER_Building Plan Approval_Reduced.pdf22 Nov 2019
PAN CardFile: 1 PAN Card.pdf22 Nov 2019
Details of encumbrancesFile: 3 Deails of Encumbrance.pdf22 Nov 2019
Copy of Layout Approval (in case of layout)File: 4 Copy of Layout Approvals_Reduced.pdf22 Nov 2019
Building Plan Approval / NA Order for plotted developmentFile: 5 MHARAL IOA LETTER_Building Plan Approval_Reduced.pdf22 Nov 2019
Commencement Certificates / NA Order for plotted developmentFile: 6 MHARAL CC for Upload.pdf22 Nov 2019
Declaration in FORM BFile: 7 Declaration in Form B_Reduced.pdf22 Nov 2019
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8 Engineering certificate-Form2.pdf22 Nov 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 9 CA certificate Form-3_Certificate Maha Rera_Reduced.pdf22 Nov 2019
Proforma of Allotment letterFile: 10 Agreement to registration and allotment declaration .pdf22 Nov 2019

Promoter's earlier projects11

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

8 delivered on promise1 delivered late2 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
PODDAR RIVIERA PHASE - IP51700023508MHARAL, Thane720Dec 2019OngoingSep 2025Not delivered
PODDAR WONDERCITY PHASE - IIP51700020028JOVELI VILLAGE, Thane-Mar 2019Certificate SignedJun 2022Not delivered
SAMRUDDHI EVERGREENS-PHASE-4BBADLAPUR178-CompletedMar 2019Aug 2018
SAMRUDDHI EVERGREENS-PHASE-4ABADLAPUR160-CompletedMar 2018Mar 2018
PODDAR EVERGREEN PHASE 3BADLAPUR796-CompletedDec 2015Late, Mar 2016
PODDAR BRIO INTERNATIONAL SCHOOLBADLAPUR--CompletedAug 2015Aug 2015
CENTRAL HOSPITALBADLAPUR--CompletedMar 2015Mar 2015
PODDAR EVERGREEN PHASE 2BADLAPUR672-CompletedDec 2014Dec 2014
SAMRUDDHI COMPLEXBHIVPURI KARJAT1,264-CompletedApr 2014Apr 2014
SAMRUDDHI COMMERCIAL COMPLEXBHIVPURI KARJAT45-CompletedApr 2014Apr 2014
PODDAR EVERGREEN PHASE 1BADLAPUR516-CompletedAug 2013Aug 2013

How this compares with Thane

0%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PODDAR RIVIERA PHASE - II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MHARAL7,600+ in Thane

2 kmPODDAR RIVIERA PHASE - ICompleted 14Lapsed / revoked 5Other 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 22 registered projects within 2 km.

Builder: Poddar Housing and Development Limited

Poddar Housing and Development Limited has 13 registrations on MahaRERA, including PODDAR SPRAHA DIAMOND PHASE-I and SAMRUDDHI EVERGREENS-PHASE-4A. Its filings disclose 11 earlier MahaRERA projects: declares 8 of 9 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if PODDAR RIVIERA PHASE - II is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PODDAR RIVIERA PHASE - II?

The registered promoter entity is Poddar Housing and Development Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PODDAR RIVIERA PHASE - II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PODDAR RIVIERA PHASE - II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for PODDAR RIVIERA PHASE - II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PODDAR RIVIERA PHASE - II?

The professionals named in the filing: Architect: ARCHITECT HAFEEZ CONTRACTOR; Architect: ubarchitects; Engineer: Chetan Kubal; Chartered Accountant: Bansal Bansal & Company; Chartered Accountant: M. S. Bajaj & Co.; Chartered Accountant: V A SHIMPI & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PODDAR RIVIERA PHASE - II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PODDAR RIVIERA PHASE - II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PODDAR RIVIERA PHASE - II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.