Petal Greens
RG-MH-47043 · RERA P52100052059 · Last updated on MahaRERA portal: 13 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 24 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Petal Greens is a Residential / Group Housing project by A R Associates in Pune, Maharashtra, registered with MahaRERA as P52100052059 on 19 Jul 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 103 of the 124 units on this registration are recorded sold or booked, and 29 of 41 construction stages are filed complete.
At a glance
Project
- NamePetal Greens
- TypeResidential / Group Housing
- Location
- Sr no. 281
- Sangvade
- Sangavade
- Mawal
- Pune
- 412101
- Pincode412101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100052059
- ReraGenie IDRG-MH-47043
Builder
- NameA R Associates
- Entity typePartnership
- PartnerAkash Vishnu Auti
- PatnersBabasaheb Laxman Auti, Nikhil Babasaheb Auti
- Other registrations2 more →
- Completed1 of 3
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on19 Jul 2023
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2024)
- Buildings4 building records
- Documents filed172 files
Current status
Figures as on 13 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| B wing | NA | 5 | 4 | 32 | 0 | 32 |
| C wing | NA | 5 | 4 | 32 | 0 | 32 |
| D wing | NA | 5 | 4 | 32 | 0 | 32 |
| A Wing | NA | 5 | 4 | 28 | 0 | 28 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 13 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
29 of 41 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 99%.
B wing82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 99% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
C wing73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 99% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
D wing73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 99% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
A Wing100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 99% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 13 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 95% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 85% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 70% |
| Street Lighting | Yes | 90% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 85% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 85% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed466
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| B wing | 120 | 120 |
| C wing | 120 | 120 |
| D wing | 120 | 120 |
| A Wing | 106 | 106 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A Wing | NA | Rs 5.67 cr | Rs 5.62 cr |
| B wing | NA | Rs 5.19 cr | Rs 5.14 cr |
| C wing | NA | Rs 4.66 cr | Rs 4.62 cr |
| D wing | NA | Rs 4.50 cr | Rs 4.45 cr |
| - | NA | Rs 2.92 cr | Rs 2.48 cr |
Certifying professionals and partners9
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Kimaya Associates |
| Engineer | Rohinee Badgujar |
| Engineer | Vikram Payghan |
| Engineer | Rushikesh Balsaheb Kasbe |
| Engineer | Shubham Sampat Gawade |
| Chartered Accountant | Vijay D Kotkar & Associates |
| Chartered Accountant | Manish Sharma |
| Chartered Accountant | Akshay Malpani |
| Chartered Accountant | ANSHUL JAIN |
| Partner | Role in project |
|---|---|
| A R Associates | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe are unable to commence construction due to Sanction plan has been revised. Changes to the building design, layout, or specifications to better align with market demands, functional re-quirements, or regulatory updates. Coordination with municipal or governmental agencies to ensure the revised plans comply with updated laws, zoning codes, and safety standards. The time taken by authorities to review, suggest changes (if any), and grant final approval extended beyond the anticipated timeline. While unforeseen, was necessary to ensure the project remains compliant with legal and structural sta
Reason as filed by the promoterWe are unable to commence construction due to the Sanction plan having been revised. Changes to the building design, layout, or specifications to better align with market demands, functional requirements, or regulatory updates. Coordination with municipal or governmental agencies to ensure the revised plans comply with updated laws, zoning codes, and safety standards. The time taken by authorities to review, suggest changes (if any), and grant final approval extended beyond the anticipated timeline. While unforeseen, it was necessary to ensure the project remains compliant with legal and struc
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Jun 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Feb 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 17 Feb 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed172
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 172 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2023-2024)File: Engg certificate 2024 petal.pdf | 13 Jun 2026 |
| Form 2A (FY 2024-2025)File: Engg certificate petal 2025.pdf | 13 Jun 2026 |
| Form 2A (FY 2025-2026)File: 2026 Engg certificate (1) (1).pdf | 13 Jun 2026 |
| Form 2A (FY 2026-2027)File: Engg certificate petal 2027.pdf | 13 Jun 2026 |
| Withdrawal Update Form 1File: Form 1_compressed.pdf | 20 Apr 2026 |
| Withdrawal Update Form 1File: Form 1_compressed.pdf | 20 Apr 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 20 Apr 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 20 Apr 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 20 Apr 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 20 Apr 2026 |
| Layout approvalFile: LAYOUT PLANS HIGHLIGHTED.pdf | 17 Feb 2026 |
| Building plan approvalFile: ELEVATION PLAN HIGHLIGHTED.pdf | 17 Feb 2026 |
| Building plan approvalFile: Renewed plan 02.pdf | 17 Feb 2026 |
| Building plan approvalFile: Renewed plan 04.pdf | 17 Feb 2026 |
| Building plan approvalFile: Renewed plan 05.pdf | 17 Feb 2026 |
| Withdrawal Update Form 1File: FORM 1 (5).pdf | 6 Feb 2026 |
| Withdrawal Update Form 2File: WU F2.pdf | 6 Feb 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 6 Feb 2026 |
| Form 5 (FY 2024-2025)File: Form 5_FY 2024-25_Final_signed_V1 (1).pdf | 10 Dec 2025 |
| Form 5 (FY 2023-2024)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24) (2).pdf | 5 Dec 2025 |
| Form 1File: Form 1.pdf | 3 Nov 2025 |
| Form 2File: Form 2 s.pdf | 3 Nov 2025 |
| Form 3File: Form 3.pdf | 3 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 3 Nov 2025 |
| Form 1File: Form 1 s.pdf | 3 Nov 2025 |
| Form 2File: Form 2 s.pdf | 3 Nov 2025 |
| Form 3File: Form 3 s.pdf | 3 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD _ UNSOLD PETAL GREENS JUNE 2025.pdf | 3 Nov 2025 |
| Form 1File: f1 march 25 (1).pdf | 10 Aug 2025 |
| Form 2File: f2 march 25.pdf | 10 Aug 2025 |
| Form 3File: A R Associates_Form 3_Q4_jun 2025 (1).pdf | 10 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: sold un.pdf | 10 Aug 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf | 22 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: march 25 petal green.pdf | 22 May 2025 |
| Form 1File: form 1 sep 23.pdf | 22 May 2025 |
| Form 2File: form 2 sep 23.pdf | 22 May 2025 |
| Form 3File: form 3 sept 23.pdf | 22 May 2025 |
| Disclosure of Sold and Booked InventoryFile: sold sep 23.pdf | 22 May 2025 |
| Form 1File: form 1 dec 23 petal.pdf | 22 May 2025 |
| Form 2File: form 2 dec 23 petal.pdf | 22 May 2025 |
| Form 3File: dec 23 form 3 petal.pdf | 22 May 2025 |
| Disclosure of Sold and Booked InventoryFile: dec 23 sold.pdf | 22 May 2025 |
| Form 1File: form 1 march 24 petal.pdf | 22 May 2025 |
| Form 2File: march 24 form 2 petal.pdf | 22 May 2025 |
| Form 3File: form 3 march 24 petal.pdf | 22 May 2025 |
| Disclosure of Sold and Booked InventoryFile: march 24 sold petal.pdf | 22 May 2025 |
| Form 1File: form 1 june 24.pdf | 22 May 2025 |
| Form 2File: form 2 june 24 petal.pdf | 22 May 2025 |
| Form 3File: june 24 form 3 petal.pdf | 22 May 2025 |
| Disclosure of Sold and Booked InventoryFile: june 24 sold petal.pdf | 22 May 2025 |
| Form 1File: sept 24 petal form 1.pdf | 22 May 2025 |
| Form 2File: form 2 sept 24.pdf | 22 May 2025 |
| Form 3File: sept 2024 form 3 petal.pdf | 22 May 2025 |
| Disclosure of Sold and Booked InventoryFile: sept 24 sold petal.pdf | 22 May 2025 |
| Form 1File: dec 24 form 1 petal.pdf | 22 May 2025 |
| Form 2File: form 2 dec 24 petal.pdf | 22 May 2025 |
| Form 3File: form 3 dec 24.pdf | 22 May 2025 |
| Disclosure of Sold and Booked InventoryFile: sold dec 24 petal.pdf | 22 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 CA Certificate Sep 2023.pdf | 13 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 CA Certificate Dec 2023.pdf | 13 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 8 CA Certificate Sep 2024.pdf | 13 May 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD - UNSOLD PETAL GREENS 31 MARCH 2025_11zon.pdf | 3 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GetUserDocumentFileContent (18).pdf | 21 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: PETAL GREENS FORM 3_SCANNED.pdf | 20 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Site Supervisor Certificate.pdf | 20 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24) (1).pdf | 20 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (5) (1).pdf | 13 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GetUserDocumentFileContent (2) (2).pdf | 13 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GetUserDocumentFileContent (2) (1).pdf | 13 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 Architect’s Certificate of Percentage of Completion of Work (Form 1) (1).pdf | 13 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 Architect’s Certificate of Percentage of Completion of Work (Form 1) (2).pdf | 13 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7 Architect’s Certificate of Percentage of Completion of Work (Form 1) (1) (1).pdf | 13 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 Architect’s Certificate of Percentage of Completion of Work (Form 1) (3) (1).pdf | 13 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 Architect’s Certificate of Percentage of Completion of Work (Form 1) (1) (1).pdf | 13 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineer’s Certificate on Cost Incurred on Project (Form 2) (2) (2).pdf | 13 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineer’s Certificate on Cost Incurred on Project (Form 2) (2) (3).pdf | 13 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1).pdf | 13 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1).pdf | 13 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1).pdf | 13 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Adobe Scan Mar 13, 2025 (1).pdf | 13 Mar 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 172 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Petal Greens on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Sangvade13,700+ in Pune
Godrej Park Greens
Godrej Skyline Developers Limited
FOREST GROVE AT GODREJ PARK GREENS
Godrej Skyline Developers Limited
Om Mangalam Samruddhi
NDG Homes LLP
PCMC EWS KIWALE
Pimpri Chinchwad Municipal Corporation
Godrej Nurture
Godrej Skyline Developers Limited
My Home Sanctuary Phase I
MAMURDI DEVELOPERS LLP
Builder: A R Associates
A.R ASSOCIATES has 3 registrations on MahaRERA, including A.R VINTAGE and SHREE HARI NAGAR. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Petal Greens is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Petal Greens?
The registered promoter entity is A R Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Petal Greens?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Petal Greens?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Petal Greens?
The professionals named in the filing: Architect: Kimaya Associates; Engineer: Rohinee Badgujar; Engineer: Vikram Payghan; Engineer: Rushikesh Balsaheb Kasbe; Engineer: Shubham Sampat Gawade; Chartered Accountant: Vijay D Kotkar & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Petal Greens?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback