PERCEPT BOUNTY 3
By PRIME ESTATE
RG-MH-16654 · RERA P52100027530 · Last updated on MahaRERA portal: 10 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 18 complaints at MahaRERA
- Completion date moved by 30 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PERCEPT BOUNTY 3 is a Residential / Group Housing project by PRIME ESTATE in Pune, Maharashtra, registered with MahaRERA as P52100027530 on 14 Dec 2020. Possession is promised by 15 Dec 2026. The completion date has moved by 30 months from the original filing. 19 of the 56 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 18 complaints are on record with the regulator.
At a glance
Project
- NamePERCEPT BOUNTY 3
- TypeResidential / Group Housing
- Location
- PLOT NO 55
- 56
- 57 SUEVEY NO 1
- VADGAONSHERI
- VADGAONSHERI
- Pune (M Corp.)
- Pune City
- Pune
- 411014
- Pincode411014
- RERA no.P52100027530
- ReraGenie IDRG-MH-16654
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on14 Dec 2020
- Promised completion15 Dec 2026
- Revised completionRevised to 15 Dec 2026 (originally 1 Jun 2024)
- Buildings1 building record
- Documents filed156 files
Current status
Figures as on 10 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| PERCEPT BOUNTY 3 WING A AND WING B | NA | 7 | 7 | 56 | 0 | 56 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 10 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.
PERCEPT BOUNTY 3 WING A AND WING B: 78% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 85% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 85% |
Progress on shared amenities15
As on 10 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed34
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership3
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| JAYANT RAMCHANDRA PAWAR | Pune (M Corp.) | Pune |
| SURESH DAMODAR KARNIK | Pune (M Corp.) | Pune |
| SHRIKANT SITARAM HASBNIS | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| PERCEPT BOUNTY 3 WING A AND WING B | NA | Rs 13.50 cr | Rs 12.67 cr |
| - | NA | Rs 1.50 cr | Rs 40.00 lakh |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AR GANESH BHAGWAT |
| Architect | R S ASSOCIATES |
| Engineer | ER NAVNATH JARAG |
| Engineer | VINOD SHIVSHARAN |
| Chartered Accountant | SPCM AND ASSOCIATES |
| Chartered Accountant | CA Nikita A Bajaj |
| Chartered Accountant | SIDDHANT ABHAY BORA |
| Partner | Role in project |
|---|---|
| PRIME ESTATE | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterPromoter of the Project PERCEPT BOUNTY 3 holding MahaRERA Registration No. P52100027530, hereby apply for revision in the project completion date. The erstwhile project completion date was 01/06/2024, however, the same seems to be unachievable due to reasons beyond our control such as: 1. Non-availability of Skilled Labour; 2. Non-availability of Requisite Material; 3. Overall distress caused due to COVID-19 pandemic; 4. Unforeseen Lockdown Conditions. 5. Insufficient Cash flow and funds due to untimely payments of the Allottes Further, as of this date, the project is 60% Complete. (Appended i
Reason as filed by the promoterApply to Pune Municipal Corporation for an Occupancy Certificate. also the 10% Internal and external is pedning which we will complete on or before 15.12.2026.
Complaints filed with MahaRERA18
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12503173 | Ganesh Dinkar Kumbhar | PRIME ESTATE | 08/09/2025 |
| CC12503167 | SUMIT NANDKUMAR UJAWANE | PRIME ESTATE | 08/09/2025 |
| CC12503161 | shubhambhai nandkishor shimpi | PRIME ESTATE | 08/09/2025 |
| CC12503175 | VAIBHAV DATTATRAYA KARKAR | PRIME ESTATE | 09/09/2025 |
| CC12503190 | Kusum Jairoop Choudhary | PRIME ESTATE | 10/09/2025 |
| CC12503185 | PARAG SHARAD BHATTAD | PRIME ESTATE | 09/09/2025 |
| CC12503186 | RAHUL RAMDAS GAIKE | PRIME ESTATE | 09/09/2025 |
| CC12503208 | SANDIP ASHOKRAO REDDEWAR | PRIME ESTATE | 10/09/2025 |
| CC12503195 | Taterao Bajirao Ghavate | PRIME ESTATE | 10/09/2025 |
| CC12503196 | Sidram Bapu Gaikwad | PRIME ESTATE | 10/09/2025 |
| CC12503210 | Karan Ratan Pandey | PRIME ESTATE | 11/09/2025 |
| CC12503223 | Sachin Dhanaji Satpute | PRIME ESTATE | 12/09/2025 |
| CC12503336 | Shweta Sathe | PRIME ESTATE | 18/09/2025 |
| CC12503275 | Sudhir Ganpatrao Pawar | PRIME ESTATE | 14/09/2025 |
| CC12503338 | Leena Vijay Sathe | PRIME ESTATE | 18/09/2025 |
| CC12503363 | Amit Lala Shinde | PRIME ESTATE | 20/09/2025 |
| CC12503372 | Shuddhodhan Narayanrao Moon | PRIME ESTATE | 21/09/2025 |
| CC12605212 | Sandeep S Salvi | PRIME ESTATE | 16/08/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Sep 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Aug 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Aug 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 22 Sep 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 15 Dec 2026
Documents filed156
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 156 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: PB3 Form 1 Architect Certificate.pdf | 10 Aug 2026 |
| Withdrawal Update Form 1File: Form1 Architect Certificate Signed.pdf | 10 Aug 2026 |
| Withdrawal Update Form 2File: PB3 Form 2.pdf | 10 Aug 2026 |
| Withdrawal Update Form 2File: Form2.pdf | 10 Aug 2026 |
| Withdrawal Update Form 3File: FORM 3 FINAL.pdf | 10 Aug 2026 |
| Withdrawal Update Form 3File: Signed Form 3.pdf | 10 Aug 2026 |
| Form 2A (FY 2025-2026)File: Foem2A.pdf | 31 Jul 2026 |
| Form 2A (FY 2024-2025)File: Form 2A B3 2024 25.pdf | 31 Jul 2026 |
| Form 2A (FY 2023-2024)File: Form 2A B3.pdf | 31 Jul 2026 |
| Form 2A (FY 2022-2023)File: 2 Form 2A B3 2024 25.pdf | 31 Jul 2026 |
| Form 2A (FY 2021-2022)File: 1 Form 2A B3.pdf | 31 Jul 2026 |
| Form 2A (FY 2020-2021)File: 1 Form 2A B3.pdf | 31 Jul 2026 |
| Form 2A (FY 2026-2027)File: PB3 Form 2A.pdf | 31 Jul 2026 |
| Withdrawal Update Form 1File: Form1 Architect Certificate Signed.pdf | 30 Jul 2026 |
| Withdrawal Update Form 1File: Form1 Architect Certificate Signed.pdf | 30 Jul 2026 |
| Withdrawal Update Form 1File: PB3 Form 1 Architect Certificate.pdf | 30 Jul 2026 |
| Withdrawal Update Form 2File: Form2.pdf | 30 Jul 2026 |
| Withdrawal Update Form 2File: Form2.pdf | 30 Jul 2026 |
| Withdrawal Update Form 2File: PB3 Form 1 Architect Certificate.pdf | 30 Jul 2026 |
| Withdrawal Update Form 3File: Signed Form 3.pdf | 30 Jul 2026 |
| Withdrawal Update Form 3File: Signed Form 3.pdf | 30 Jul 2026 |
| Withdrawal Update Form 3File: FORM 3 FINAL.pdf | 30 Jul 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 27 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 PB3 Q3.pdf | 27 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Q2.pdf | 27 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 PB3 Q3.pdf | 27 Feb 2026 |
| Withdrawal Update Form 3File: signed form 3 oct.pdf | 27 Feb 2026 |
| Withdrawal Update Form 3File: signed form 3 PB3 Q3.pdf | 27 Feb 2026 |
| Form 1File: Form 1 Q1.pdf | 16 Oct 2025 |
| Form 2File: Form 2 Q1.pdf | 16 Oct 2025 |
| Form 3File: FORM 3 Q1.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf | 16 Oct 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PB3-Form1.pdf | 6 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 B3 Q2.pdf | 6 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 6 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 6 Jun 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 6 Jun 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 6 Jun 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 6 Jun 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 B3 Q2.pdf | 6 Jun 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 6 Jun 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 6 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory.pdf | 6 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory.pdf | 6 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory.pdf | 6 Jun 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A B3 Q2.pdf | 6 Jun 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf | 6 Jun 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf | 6 Jun 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed (9).pdf | 26 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 26 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf | 26 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf | 26 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 BOUNTY 3.pdf | 18 Oct 2024 |
| CERSAI detailsFile: CERSAI DECLARATION PB3.pdf | 29 Jun 2024 |
| CERSAI detailsFile: 2 CERSAI details (2) (1).pdf | 29 Jun 2024 |
| CERSAI detailsFile: CERSAI Report.pdf | 27 Jun 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A MB.pdf | 27 Jun 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A PB.pdf | 27 Jun 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: PB3 Format A.pdf | 27 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 BOUNTY 3_compressed.pdf | 24 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 21 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 21 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 21 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 21 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 21 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 21 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 21 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 21 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 21 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 21 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf | 21 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf | 21 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf | 21 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf | 21 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf | 21 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf | 21 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf | 21 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf | 21 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SIGNED.pdf | 21 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SIGNED.pdf | 21 Jun 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| PERCEPT BOUNTY 1 | PLOT NO 114 SUEVEY NO 1 VADGAONSHERI PUNE 411014 | 1 | Completed | Apr 2016 | Late, Jan 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 156 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep PERCEPT BOUNTY 3 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near VADGAONSHERI13,700+ in Pune
VJ IndiLife Kharadi
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
VJ Central Avenue
Vilas Javdekar Eco Homes
VJ IndiWorks Kharadi Central
Vilas Javdekar Eco Homes
RIVERDALE GRAND
DUVILLE ESTATES PRIVATE LIMITED
Yashwin Orizzonte Phase II
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
ZEN ESTATE
DESTINATION KHARADI DEVELOPERS LLP
Builder: PRIME ESTATE
PRIME ESTATE has 2 registrations on MahaRERA, including PERCEPT BOUNTY 3 and PERCEPT BOUNTY 4. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if PERCEPT BOUNTY 3 is delayed beyond 15 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PERCEPT BOUNTY 3?
The registered promoter entity is PRIME ESTATE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PERCEPT BOUNTY 3?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against PERCEPT BOUNTY 3?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for PERCEPT BOUNTY 3?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PERCEPT BOUNTY 3?
The professionals named in the filing: Architect: AR GANESH BHAGWAT; Architect: R S ASSOCIATES; Engineer: ER NAVNATH JARAG; Engineer: VINOD SHIVSHARAN; Chartered Accountant: SPCM AND ASSOCIATES; Chartered Accountant: CA Nikita A Bajaj. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PERCEPT BOUNTY 3?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback