ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / Parshvanath Heights

Completed No litigation declared Residential / Group Housing project

Parshvanath Heights

By Saroj Kirtikumar Bafna

RG-MH-53115 · RERA P99000015097 · Last updated on MahaRERA portal: 2 Oct 2023

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Oct 2023Possession promisedregistration recorded completed
0 of 33Construction stages doneacross 3 buildings; furthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 45 documents Report an error

Parshvanath Heights is a Residential / Group Housing project by Saroj Kirtikumar Bafna in Palghar, Maharashtra, registered with MahaRERA as P99000015097 on 24 Jan 2018. The registration is recorded completed; possession was promised by 30 Oct 2023.

At a glance

Project

  • NameParshvanath Heights
  • TypeResidential / Group Housing
  • Location
    • Veoor Road
    • Palghar
    • 401404
  • Pincode401404
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000015097
  • ReraGenie IDRG-MH-53115

Builder

  • NameSaroj Kirtikumar Bafna
  • Entity typeIndividual
  • Other registrations1 more →
  • Completed2 of 2

Key dates

this monthRegisteredJan 2018PromisedOct 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on24 Jan 2018
  • Promised completion30 Oct 2023
  • Revised completionNone
  • Buildings3 building records
  • Documents filed45 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ShubhNA50000
LabhNA50000
AmrutNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 2 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 0%.

Shubh0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Labh0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Amrut0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 2 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed320

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots320
Open Space320
BuildingOpen SpaceTotal
Shubh9090
Labh150150
Amrut8080

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,600 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Saroj Kirtikumar BafnaPalghar Palghar

Approvals and building plan

Permissible FSI4723.61
Proposed, not sanctioned4,724 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch Vedant Villa Acharya Wada, Opposite Manisha Dairy Mahim Road, Palghar West, Thane

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPranav Deshmukh
EngineerAwhad Consulting Engineers & Architect
PartnerRole in project
Saroj Kirtikumar Bafna-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Jan 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 May 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 May 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 May 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Aug 2020

Documents filed45

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of ConveyanceFile: 121255-compressed (1) (1).pdf2 Oct 2023
Status of ConveyanceFile: 541848488_compressed.pdf2 Oct 2023
CERSAI detailsFile: CERSAI_Search_Report_200232606347_Paarshvanath Heights.pdf16 Mar 2022
Declaration about Commencement CertificateFile: Declaration About Commencement Certificate.pdf4 Jan 2022
Disclosure of sold/ booked inventoryFile: Disclosure Of Sold Inventory (1).pdf4 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Asssurance Certificate 2019-20.pdf1 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate 2020-21.pdf1 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Stage completions Certificates Parshvanath Hrights.pdf31 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019_20.pdf4 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: PARSVANATH HEIGHTS Form 5 20-21.pdf4 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate.pdf3 Sep 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 RERA FY 2018-19.pdf3 Sep 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Declaration for cancellation.pdf7 Aug 2020
Certificates of Architect (Form 4)File: Declaration for cancellation.pdf7 Aug 2020
Status of Formation of Legal Entity (Society/Co Op etc.)File: Building Shubh society certificate (1).pdf7 Aug 2020
OtherFile: Declaration for cancellation.pdf7 Aug 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Cert_PO_70295_279yfK1rSign.pdf22 Feb 2020
Annual Audit Report of Statutory CA (Form 5)File: FORM 5 RERA.pdf18 Oct 2019
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Architect Certificate.pdf18 Oct 2019
Proforma of Allotment letterFile: Revised Final kirti_bafna_RERA_document.pdf3 Dec 2018
Layout approvalFile: Drg 1 - Site and Layout Plan Revised 260418.PDF19 May 2018
Building plan approvalFile: Drg 2 - Bldg 1 Revised 260418-Compressed.pdf19 May 2018
Building plan approvalFile: Drg 3 - Bldg 2 Grd Flr Rev 260418.PDF19 May 2018
Building plan approvalFile: Drg 4 - Bldg 2 1-4th Flr Rev 260418.PDF19 May 2018
Building plan approvalFile: Drg 5 - Bldg 3 Rev 260418.PDF19 May 2018
Copy of Layout Approval (in case of layout)File: Drg 1 - Site and Layout Plan Revised 260418.PDF19 May 2018
Building Plan Approval (IOD)File: Drg 2 - Bldg 1 Revised 260418-Compressed.pdf19 May 2018
Building Plan Approval (IOD)File: Drg 3 - Bldg 2 Grd Flr Rev 260418.PDF19 May 2018
Building Plan Approval (IOD)File: Drg 4 - Bldg 2 1-4th Flr Rev 260418.PDF19 May 2018
Building Plan Approval (IOD)File: Drg 5 - Bldg 3 Rev 260418.PDF19 May 2018
Commencement Certificates / NA Order for plotted developmentFile: Building Commencement Certificate Rev ised.pdf19 May 2018
Commencement Certificates / NA Order for plotted developmentFile: Building Commencement Certificate KB Infra.pdf19 Apr 2018
Building plan approvalFile: Annexure C-1 - Final Layout Plan Pdf.pdf16 Jan 2018
Layout approvalFile: Annexure C-1 - Final Layout Plan Pdf.pdf16 Jan 2018
PAN CardFile: Saroj Bafna Pan Card (2).pdf16 Jan 2018
Copy of the legal title reportFile: Annexure A - Certificate Of Title- compressed.pdf16 Jan 2018
Details of encumbrancesFile: Details Of Encumbrance Certificate.pdf16 Jan 2018
Copy of Layout Approval (in case of layout)File: Annexure C-1 - Final Layout Plan Pdf.pdf16 Jan 2018
Building Plan Approval (IOD)File: Annexure C-1 - Final Layout Plan Pdf.pdf16 Jan 2018
Declaration in FORM BFile: Notarised Form B.pdf16 Jan 2018
Declaration in FORM BFile: kb POA 1 to 6.pdf16 Jan 2018
Declaration in FORM BFile: KB POA 7 to12.pdf16 Jan 2018
Declaration in FORM BFile: KB POA 12 to 18.pdf16 Jan 2018
Certificates of CA (Form 3)File: Form 3- CA Certificate BRK.pdf16 Jan 2018
Proforma of Allotment letterFile: Final kirti_bafna_RERA_document.pdf16 Jan 2018

How this compares with Palghar

31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Parshvanath Heights on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Palghar3,200+ in Palghar

2 kmParshvanath HeightsCompleted 15Lapsed / revoked 13Other 21Dot size: filed unitsN

Filed coordinates, straight-line distance. 49 registered projects within 2 km.

Builder: Saroj Kirtikumar Bafna

Saroj Kirtikumar Bafna has 2 registrations on MahaRERA, including Parshvanath Heights and Shraddha Mansion. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if Parshvanath Heights is delayed beyond 30 Oct 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Parshvanath Heights?

The registered promoter entity is Saroj Kirtikumar Bafna, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Parshvanath Heights?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Parshvanath Heights?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Parshvanath Heights?

The professionals named in the filing: Architect: Pranav Deshmukh; Engineer: Awhad Consulting Engineers & Architect. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Parshvanath Heights?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Parshvanath Heights. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Parshvanath Heights to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.