ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / PARKWOODS D5

Registered No litigation declared Residential / Group Housing project

PARKWOODS D5

By Aniline Construction Company Private Limited

RG-MH-24554 · RERA P51700007024 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • 8 complaints at MahaRERA
  • Completion date moved by 9 months
  • 1 extension taken
  • Rs 25.00 crore secured on the land, in favour of Sundaram Alternative Opportunities Series High Yield Secured Real Estate Fund IV

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 9 months from the original
3 of 11Construction stages donefurthest along: Internal walls, 92%
0 of 420Units unsoldnot recorded sold or booked
8Complaints at MahaRERAon this registration
Jump to the 318 documents Report an error

PARKWOODS D5 is a Residential / Group Housing project by Aniline Construction Company Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700007024 on 17 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 9 months from the original filing. 420 of the 420 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 8 complaints are on record with the regulator.

At a glance

Project

  • NamePARKWOODS D5
  • TypeResidential / Group Housing
  • Location
    • Godhbunder Road
    • D-Mart
    • Kavesar
    • Thane (M Corp.)
    • Thane
    • 400615
  • Pincode400615
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700007024
  • ReraGenie IDRG-MH-24554

Builder

  • NameAniline Construction Company Private Limited
  • Entity typeCompany
  • Managing DirectorASHISH GIRDHARILAL VAID
  • Other registrations2 more →
  • Completed1 of 3
  • Declared earlier projects3 →

Key dates

this monthRegisteredAug 2017First promiseMar 2026Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Mar 2026)
  • Buildings1 building record
  • Documents filed318 files

Current status

100%420 of 420 units booked
71.5%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Parkwoods Building D5NA62554200420

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 92%.

Parkwoods Building D5: 65% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)77%
Podiums (if any)30%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises92%
Sanitary Fittings within the flats / premises72%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed390

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots390
Closed/Covered390

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area683 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofSundaram Alternative Opportunities Series High Yield Secured Real Estate Fund IV
Secured amountRs 25.00 crore
CERSAI search filedYes
Declared on16 Jul 2025

Approvals and building plan

Sanctioning authorityThane Municipal Corporation
Permissible FSI22391.0
Proposed, not sanctioned22,391 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNANIK MOTWANI MARG FORT MUMBAI 400001
Estimated costRs 195.00 cr
Cost incurredRs 139.51 cr
Work done71.54%
BuildingWingEstimatedIncurred
Parkwoods Building D5NARs 191.85 crRs 137.93 cr
-NARs 3.15 crRs 1.58 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSaakaar Architects
ArchitectSaakaar
EngineerJ W Consultants LLP
EngineerVP Consultants
Chartered AccountantNehali & Co
Chartered AccountantNehali & Co.
Chartered AccountantN. A. Shah Associates LLP
PartnerRole in project
Aniline Construction Company Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA25032620377Mar 2026 → Dec 2026

Reason as filed by the promoterReasons for Delay: a.) Unanticipated Geological Conditions Affecting Excavation; b) Imposed Restrictions on Working Hours; c) Covid-19 Pandemic; d) Mandatory Compliance with Air-Pollution Mitigation Orders; e) Extreme Climatic Conditions and Labour Shortages (March-May 2025); f) Prolonged and Intense Monsoon (2025); g) Industry-Wide Material Supply Chain Disruptions (2022-2025); h) Structural Labour Availability Constraints (Beyond Seasonal Cycles); i) Reverse Migration and Election-Period Disruptions (April-June 2024; November 2024); j) Present disruptions to critical material supplies due to

Complaints filed with MahaRERA8

Case no.ComplainantRespondentFiled
CC006000000197644SUMIT MAHABIR FOGLAAniline Construction Company Private Limited18/07/2021
CC006000000210293Chaitali TopkarDynamix Group08/03/2022
CC12605341Harshala Prashant ManchalwarAniline Construction Company Private Limited21/08/2026
CC12603918AMOL GHADGEAniline Construction Company Private Limited24/06/2026
CC12604599Sameer Maruti JadhavAniline Construction Company Private Limited22/07/2026
CC12604593Swish GuptaAniline Construction Company Private Limited22/07/2026
CC12604661Mandar Sunil PatilAniline Construction Company Private Limited25/07/2026
CC12605381Sandesh Namdev SalaskarAniline Construction Company Private Limited22/08/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Jan 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed318

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 318 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Parkwoods D5 - Form 1 - 30-06-2026.pdf20 Jul 2026
Withdrawal Update Form 2File: Parkwoods D5 - Form 2 - 30-06-2026.pdf20 Jul 2026
Withdrawal Update Form 3File: Parkwoods D5 - Form 3 - 30-06-2026.pdf20 Jul 2026
Form 2A (FY 2018-2019)File: Form 2A - March 2019.pdf28 Apr 2026
Form 2A (FY 2017-2018)File: Form 2A - March 2018.pdf28 Apr 2026
Form 5 (FY 2020-2021)File: Form 5 - 2020 - 2021.pdf28 Apr 2026
Form 5 (FY 2019-2020)File: Form 5 - 2019 - 2020.pdf28 Apr 2026
Form 5 (FY 2018-2019)File: Form 5 - 2018 - 2019.pdf28 Apr 2026
Form 5 (FY 2017-2018)File: Form 5 - 2017 - 2018.pdf28 Apr 2026
Form 1File: Form 1 - 31-03-2022.pdf27 Apr 2026
Form 2File: Form 2 - 31-03-2022.pdf27 Apr 2026
Form 3File: Form 3 - 31-03-2022.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - 31-03-2022.pdf27 Apr 2026
Form 1File: Form 1 - 31-12-2021.pdf27 Apr 2026
Form 2File: Form 2 - 31-12-2021.pdf27 Apr 2026
Form 3File: Form 3 - 31-12-2021.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - 31-12-2021.pdf27 Apr 2026
Form 1File: Form 1 - 30-09-2021.pdf27 Apr 2026
Form 2File: Form 2 - 30-09-2021.pdf27 Apr 2026
Form 3File: Form 3 - 30-09-2021.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - 30-09-2021.pdf27 Apr 2026
Form 1File: Form 1 - 30-06-2021.pdf27 Apr 2026
Form 2File: Form 2 - 30-06-2021.pdf27 Apr 2026
Form 3File: Form 3 - 30-06-2021.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - 30-06-2021.pdf27 Apr 2026
Form 1File: Form 1 - 31-03-2021.pdf27 Apr 2026
Form 2File: Form 2 - 31-03-2021.pdf27 Apr 2026
Form 3File: Form 3 - 31-03-2021.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - 31-03-2021.pdf27 Apr 2026
Form 1File: Form 1 - 31-12-2020.pdf27 Apr 2026
Form 2File: Form 2 - 31-12-2020.pdf27 Apr 2026
Form 3File: Form 3 - 31-12-2020.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - 31-12-2020.pdf27 Apr 2026
Form 1File: Form 1 - 30-09-2020.pdf27 Apr 2026
Form 2File: Form 2 - 30-09-2020.pdf27 Apr 2026
Form 3File: Form 3 - 30-09-2020.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - 30-09-2020.pdf27 Apr 2026
Form 1File: Form 1 - 31-03-2020.pdf27 Apr 2026
Form 2File: Form 2 - 31-03-2020.pdf27 Apr 2026
Form 3File: Form 3 - 31-03-2020.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - 31-03-2020.pdf27 Apr 2026
Form 1File: Form 1 - 31-12-2019.pdf27 Apr 2026
Form 2File: Form 2 - 31-12-2019.pdf27 Apr 2026
Form 3File: Form 3 - 31-12-2019.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - 31-12-2019.pdf27 Apr 2026
Form 1File: Form 1 - 30-06-2020.pdf27 Apr 2026
Form 2File: Form 2 - 30-06-2020.pdf27 Apr 2026
Form 3File: Form 3 - 30-06-2020.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - 30-06-2020.pdf27 Apr 2026
Form 1File: Form 1 - 30-09-2019.pdf27 Apr 2026
Form 2File: Form 2 - 30-09-2019.pdf27 Apr 2026
Form 3File: Form 3 - 30-09-2019.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - 30-09-2019.pdf27 Apr 2026
Form 1File: Form 1 - 30-06-2019.pdf27 Apr 2026
Form 2File: Form 2 - 30-06-2019.pdf27 Apr 2026
Form 3File: Form 3 - 30-06-2019.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - 30-06-2019.pdf27 Apr 2026
Form 1File: Form 1 - 31-03-2019.pdf27 Apr 2026
Form 2File: Form 2 - 31-03-2019.pdf27 Apr 2026
Form 3File: Form 3 - 31-03-2019.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - 31-03-2019.pdf27 Apr 2026
Form 1File: Form 1 - 31-12-2018.pdf27 Apr 2026
Form 2File: Form 2 - 31-12-2018.pdf27 Apr 2026
Form 3File: Form 3 - 31-12-2018.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - 31-12-2018.pdf27 Apr 2026
Form 1File: Form 1 - 30-09-2018.pdf27 Apr 2026
Form 2File: Form 2 - 30-09-2018.pdf27 Apr 2026
Form 3File: Form 3 - 30-09-2018.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - 30-09-2018.pdf27 Apr 2026
Form 1File: Form 1 - 30-06-2018.pdf27 Apr 2026
Form 2File: Form 2 - 30-06-2018.pdf27 Apr 2026
Form 3File: Form 3 - 30-06-2018.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - 30-06-2018.pdf27 Apr 2026
Form 1File: Form 1 - 31-03-2018.pdf27 Apr 2026
Form 2File: Form 2 - 31-03-2018.pdf27 Apr 2026
Form 3File: Form 3 - 31-03-2018.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - 31-03-2018.pdf27 Apr 2026
Form 1File: Form 1 - 31-12-2017.pdf27 Apr 2026
Form 2File: Form 2 - 31-12-2017.pdf27 Apr 2026
Form 3File: Form 3 - 31-12-2017.pdf27 Apr 2026

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Parkwoods Buildings B2, B3, C4Godhbunder Road507CompletedDec 2013Dec 2013

How this compares with Thane

100%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 9 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PARKWOODS D5 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near D-Mart, Kavesar7,600+ in Thane

2 kmPARKWOODS D5Completed 97Lapsed / revoked 25Other 55Dot size: filed unitsN

Filed coordinates, straight-line distance. 177 registered projects within 2 km.

Builder: Aniline Construction Company Private Limited

Aniline Construction Company Private Limited has 3 registrations on MahaRERA, including Parkwoods Building A1 and PARKWOODS D5. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 3 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if PARKWOODS D5 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PARKWOODS D5?

The registered promoter entity is Aniline Construction Company Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PARKWOODS D5?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PARKWOODS D5?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for PARKWOODS D5?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PARKWOODS D5?

The professionals named in the filing: Architect: Saakaar Architects; Architect: Saakaar; Engineer: J W Consultants LLP; Engineer: VP Consultants; Chartered Accountant: Nehali & Co; Chartered Accountant: Nehali & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARKWOODS D5?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARKWOODS D5. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARKWOODS D5 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.