Home / Browse projects / Pune, Maharashtra / PARKLANE URBANJOY WING C

Registered No litigation declared Residential / Group Housing project

PARKLANE URBANJOY WING C

By Parklane Construction LLP

RG-MH-31760 · RERA P52100080095 · Last updated on MahaRERA portal: 18 Jun 2026

Source: official MahaRERA filing

Red flags

  • Rs 30.00 crore secured on the land, in favour of Aditya Birla Housing Finance LTD
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 3 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedno revision filed
2 of 11Construction stages donefurthest along: Stilt Floor, 60%
56 of 144Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 50 documents Report an error

PARKLANE URBANJOY WING C is a Residential / Group Housing project by Parklane Construction LLP in Pune, Maharashtra, registered with MahaRERA as P52100080095 on 24 Apr 2025. Possession is promised by 31 Dec 2028. 88 of the 144 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete.

At a glance

Project

  • NamePARKLANE URBANJOY WING C
  • TypeResidential / Group Housing
  • Location
    • SUS NANDE ROAD
    • SUS GAON
    • Sus
    • Mulshi
    • Pune
    • 411021
  • Pincode411021
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100080095
  • ReraGenie IDRG-MH-31760

Builder

  • NameParklane Construction LLP
  • Entity typeLimited Liability Partnership
  • LLPINAAH-5950
  • GSTIN27AATFP4446L1ZH
  • PartnersKaran Vijay Porwal, Jitendrakumar Mohanlal Jain, Mamik Jain, Pratik Bherumal Jain
  • Other registrations3 more →
  • Completed1 of 4
  • Declared earlier projects3 →

Key dates

this monthRegisteredApr 2025PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on24 Apr 2025
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed50 files

Current status

61%88 of 144 units booked
23.6%Work done, per cost certificate

Figures as on 18 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PARKLANE URBANJOY WING CNA21181440144

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 60%.

PARKLANE URBANJOY WING C: 29% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth0%
Stilt Floor60%
Slabs of Super Structure47%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises11%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed272

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots272
Closed/Covered224
Open Space48

Land and ownership5

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area12,700 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
Encumbrance on the landDeclared present
Charge in favour ofAditya Birla Housing Finance LTD
Secured amountRs 30.00 crore
CERSAI search filedYes
Declared on4 Mar 2026
LandownerVillageDistrict
EKNATH SHIVRAM HINGEAmbegaonPune
JALINDAR BAJIRAO CHANDERESusPune
SURENDRA BAJIRAO CHANDERESusPune
RAVINDRA VASANT TAMBADEParvatiPune
MACCHINDRA BAJIRAO CHANDERESusPune

Approvals and building plan

Sanctioning authorityPMRDA
Permissible FSI13790.09
Proposed, not sanctioned13,790 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 1 PART GERA GRAND SUB PLOT NO 7 T O NO 438 TPS III SALISBURY PARK GULTEKDI PUNE MH 411037
Estimated costRs 48.12 cr
Cost incurredRs 11.35 cr
Work done23.59%
BuildingWingEstimatedIncurred
PARKLANE URBANJOY WING CNARs 43.85 crRs 10.71 cr
-NARs 4.27 crRs 64.34 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectElement Five Mr Jaideep Deshpande
EngineerVS Academy & Consultancy
EngineerVS Academy & Consultancy Pratik Jain
Chartered AccountantKAPIL MUNOT
PartnerRole in project
PARKLANE CONSTRUCTION LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Mar 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jan 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Nov 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Nov 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed50

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: PUJ C Q3 Form 1 Dec 2025.pdf18 Jun 2026
Withdrawal Update Form 1File: PUJ C Q4 Form 1 Mar 2026.pdf18 Jun 2026
Withdrawal Update Form 2File: PUJ C Q3 Form 2 Dec 25 pdf.pdf18 Jun 2026
Withdrawal Update Form 2File: PUJ C Q4 Form 2 Mar 2026.pdf18 Jun 2026
Withdrawal Update Form 3File: PUJ C Q 3 form 3 Dec 2025.pdf18 Jun 2026
Withdrawal Update Form 3File: PUJ C Q4 Form 3 Mar 2026.pdf18 Jun 2026
Building plan approvalFile: Wing C Sanction Plan.pdf5 Nov 2025
Building plan approvalFile: PLan 261_.pdf1 Nov 2025
Commencement certificateFile: CC SEPT 2025.pdf1 Nov 2025
Withdrawal Update Form 1File: Form1 PUJ WING C 16-10-25.pdf1 Nov 2025
Withdrawal Update Form 2File: FORM 2 27-10-25.pdf1 Nov 2025
Withdrawal Update Form 3File: Form 3 PUJ Wing C 27-10-25.pdf1 Nov 2025
Form 1File: Form 1 PUJ Wing C.pdf28 Oct 2025
Form 2File: Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf28 Oct 2025
Form 3File: Form 3 Rera 07-04-25_ UPDATD UDIN new.pdf28 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold - booked inventory.pdf28 Oct 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Rera 07-04-25_ UPDATD UDIN.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold - booked inventory.pdf21 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Land Are Nil Undertaking.pdf9 Apr 2025
Other - TechnicalFile: Area Additional Letter And Receipt.pdf9 Apr 2025
Other - TechnicalFile: RERA Format for area declaration Architech confirmation.pdf9 Apr 2025
CERSAI detailsFile: CERSAI Declaration And Certificate.pdf7 Apr 2025
Other - LegalFile: Sale Deed And 7-12.pdf4 Apr 2025
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to model copy of Agreement 2.pdf4 Apr 2025
Proforma of Agreement for saleFile: Proforma of Agreement draft with DEV Highlight.pdf4 Apr 2025
Other - TechnicalFile: DECLARATION LAND VALUE NILL.pdf29 Mar 2025
Copy of the legal title reportFile: PUJ Wing C Search Report.pdf20 Mar 2025
Other - FinanceFile: LAND OWNER AND UNIT CLARIFICATION LETTER.pdf20 Mar 2025
Other - TechnicalFile: LETTER AND PLAN.pdf20 Mar 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: FORMAT B RERA 19-3-25.pdf20 Mar 2025
Other - TechnicalFile: ANNEXURE A Other Technical Tab.pdf18 Mar 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for securedunsecured - finance availed for the project.pdf18 Mar 2025
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf17 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration about all RERA Designated Bank Accounts (Format A).pdf17 Mar 2025
Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Finance - Legal.pdf15 Mar 2025
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Finance - Legal.pdf15 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf15 Mar 2025
Declaration in FORM BFile: PUJ Wing C Form B.pdf25 Feb 2025
Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Finance - Legal.pdf22 Feb 2025
Proforma of Allotment letterFile: Proforma of Allotment letter.pdf22 Feb 2025
Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Allotment lette.pdf22 Feb 2025
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Finance - Legal.pdf22 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf13 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 PUJ Wing C.pdf7 Feb 2025
Layout approvalFile: PUJ C LAYOUT.pdf31 Jan 2025
Building plan approvalFile: Building Plan Approval.pdf31 Jan 2025
Copy of Layout Approval (in case of layout)File: PUJ C LAYOUT.pdf31 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan Approval.pdf31 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate 288-1,261-14,,261-5,287.pdf22 Jan 2025
PAN CardFile: pan card parklane llp (1).pdf3 Jul 2024

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SHANTI ELIXIRKESHAV NAGAR122CompletedSep 2019Sep 2019
PARKLANE PREMIERWAGHOLI HAVELI PUNE 412207158CompletedDec 2018Jul 2017
ANAND VASTUKOREGAON MUL PUNE48CompletedDec 2016Aug 2015

How this compares with Pune

61%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PARKLANE URBANJOY WING C on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SUS GAON13,700+ in Pune

2 kmPARKLANE URBANJOY WING CCompleted 62Lapsed / revoked 17Other 32Dot size: filed unitsN

Filed coordinates, straight-line distance. 111 registered projects within 2 km.

Builder: Parklane Construction LLP

Parklane Construction LLP has 4 registrations on MahaRERA, including Parklane Urbanjoy -Wing A and PARKLANE URBANJOY- WING B. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if PARKLANE URBANJOY WING C is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PARKLANE URBANJOY WING C?

The registered promoter entity is Parklane Construction LLP, a limited liability partnership as per the filing. Its LLPIN AAH-5950 and GSTIN 27AATFP4446L1ZH can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PARKLANE URBANJOY WING C?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PARKLANE URBANJOY WING C?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PARKLANE URBANJOY WING C?

The professionals named in the filing: Architect: Element Five Mr Jaideep Deshpande; Engineer: VS Academy & Consultancy; Engineer: VS Academy & Consultancy Pratik Jain; Chartered Accountant: KAPIL MUNOT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARKLANE URBANJOY WING C?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARKLANE URBANJOY WING C. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARKLANE URBANJOY WING C to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.