PARKLANE URBANJOY- WING B
RG-MH-16445 · RERA P52100026272 · Last updated on MahaRERA portal: 18 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 42 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- All 3 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PARKLANE URBANJOY- WING B is a Residential / Group Housing project by Parklane Construction LLP in Pune, Maharashtra, registered with MahaRERA as P52100026272 on 4 Sep 2020. Possession is promised by 31 Dec 2027. The completion date has moved by 42 months from the original filing.
At a glance
Project
- NamePARKLANE URBANJOY- WING B
- TypeResidential / Group Housing
- Location
- Sus Nande Road
- Sus Gaon
- Sus
- Mulshi
- Pune
- 411021
- Pincode411021
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100026272
- ReraGenie IDRG-MH-16445
Builder
- NameParklane Construction LLP
- Entity typePartnership
- LLPINAAH-5950
- GSTIN27AATFP4446L1ZH
- LLPIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnersKaran Vijay Porwal, Jitendrakumar Mohanlal Jain, Mamik Jain, Pratik Bherumal Jain
- Other registrations3 more →
- Completed1 of 4
- Declared earlier projects3 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on4 Sep 2020
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 30 Jun 2024)
- Buildings1 building record
- Documents filed123 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing B | NA | 21 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 18 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 80%.
Wing B: 41% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 5% |
| Plinth | 100% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 50% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 20% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 18 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed50
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership5
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Eknath Shivram Hinge | Ambegaon | Pune |
| Ravindra Vasant Tambade | Parvati | Pune |
| Macchindra Bajirao Chandere | Sus | Pune |
| Jalindar Bajirao Chandere | Sus | Pune |
| Surendra Bajirao Chandere | Sus | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Element Five Mr Jaideep Deshpande |
| Engineer | VS Academy & Consultancy Pratik Jain |
| Chartered Accountant | KAPIL MUNOT |
| Partner | Role in project |
|---|---|
| PARKLANE CONSTRUCTION LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterExtend project
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 May 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jan 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 10 May 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed123
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 123 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: PUJ B FORM 1 JUNE 2025.pdf | 18 Jun 2026 |
| Form 2File: PUJ B FORM 2 JUNE 2025.pdf | 18 Jun 2026 |
| Form 3File: PUJ B FROM 3 JUNE 2025_compressed.pdf | 18 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: PUJ B DISCLOSURE OF SOLD UNSOLD June 2025.pdf | 18 Jun 2026 |
| Form 1File: PUJ B Q2 FORM 1 Sept 2025.pdf | 18 Jun 2026 |
| Form 2File: PUJ B Q2 FORM 2 Sept 2025.pdf | 18 Jun 2026 |
| Form 3File: PUJ B Q2 FORM 3 Sept 2025.pdf | 18 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: PUJ B DISCLOSURE OF SOLD UNSOLD Sept 2025.pdf | 18 Jun 2026 |
| Form 1File: PUJ B Q3 Form 1 Dec 2025.pdf | 18 Jun 2026 |
| Form 2File: PUJ B Q3 Form 2 Dec 2025.pdf | 18 Jun 2026 |
| Form 3File: PUJ B Q3 Form 3 Dec 2025.pdf | 18 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: PUJ B DISCLOSURE OF SOLD UNSOLD Dec 25.pdf | 18 Jun 2026 |
| Form 1File: PUJ B Q4 FORM 1 Mar 2026.pdf | 18 Jun 2026 |
| Form 2File: PUJ B Q4 FORM 2 Mar 2026.pdf | 18 Jun 2026 |
| Form 3File: PUJ B Q4 FORM 3 Mar 2026.pdf | 18 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: PUJ B DISCLOSURE OF SOLD UNSOLD Mar 2026.pdf | 18 Jun 2026 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FROM 3 july 25 (1).pdf | 28 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 June 2025.pdf | 23 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FROM 3 july 25.pdf | 23 Jul 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 PUJ B 10-12-24.pdf | 23 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD FORMAT 23-7-25.pdf | 23 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Parklane From 3 WING B 25-3-25.pdf | 26 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Wing B.pdf | 3 Feb 2025 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Undertaking Cum Declaration bank change.pdf | 3 Feb 2025 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Undertaking Cum Declaration bank change.pdf | 3 Feb 2025 |
| Other - FinanceFile: Undertaking Cum Declaration bank change.pdf | 3 Feb 2025 |
| Other - FinanceFile: Undertaking Cum Declaration bank change.pdf | 3 Feb 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate 288-1,261-14,,261-5,287 - 16-01-2025.pdf | 21 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 19-12-24.pdf | 20 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 7-12-2024.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD FORMAT.pdf | 20 Jan 2025 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank details Changed Annexure All.pdf | 20 Jan 2025 |
| Declaration about Commencement CertificateFile: Commencement certificate Dt 16-01-2025.pdf | 17 Jan 2025 |
| Other - LegalFile: Pan Declaration.pdf | 21 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31-9-24.pdf | 20 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 16-11-24.pdf | 20 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 PUJ B.pdf | 20 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 PUJ B 10-12-24.pdf | 20 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 10-12-24.pdf | 20 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Parklane Contruction FROM 5 (1).pdf | 20 Dec 2024 |
| Details of encumbrances concerned to FinanceFile: Self Declaration of Loan Wing B.pdf | 9 Oct 2024 |
| Details of encumbrances concerned to LegalFile: Self Declaration of Loan Wing B.pdf | 9 Oct 2024 |
| Details of encumbrances concerned to FinanceFile: Parklane Contruction CA Confirmation.pdf | 9 Oct 2024 |
| Details of encumbrances concerned to LegalFile: Parklane Contruction CA Confirmation.pdf | 9 Oct 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Separate Bank Account WING B.pdf | 9 Oct 2024 |
| Other - FinanceFile: Parklane Contruction CA Confirmation.pdf | 9 Oct 2024 |
| Details of encumbrances concerned to FinanceFile: Parklane Contruction CA Confirmation.pdf | 9 Oct 2024 |
| Details of encumbrances concerned to FinanceFile: Self Declaration of Loan Wing B.pdf | 9 Oct 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Separate Bank Account WING B.pdf | 9 Oct 2024 |
| Details of encumbrances concerned to LegalFile: Self Declaration of Loan Wing B.pdf | 9 Oct 2024 |
| Details of encumbrances concerned to LegalFile: Parklane Contruction CA Confirmation.pdf | 9 Oct 2024 |
| Other - FinanceFile: Parklane Contruction CA Confirmation.pdf | 9 Oct 2024 |
| Proforma of Agreement for saleFile: Agreement Draft New Wing B 31-7-24.pdf | 7 Oct 2024 |
| Proforma of Agreement for saleFile: Agreement Draft New Wing B 31-7-24.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 PUJ - B 2022-23.pdf | 4 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA Form 3.pdf | 15 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 1-1-24.pdf | 24 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate PUJ B.pdf | 3 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A Engineer certificate.pdf | 3 Jan 2024 |
| Declaration in FORM BFile: Form B .pdf | 19 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 11-04-2023.pdf | 19 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A Engineer certificate FY 20-21.pdf | 19 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A Engineer certificate FY 21-22.pdf | 19 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - CA Certificate - 23-3-23 - Wing B.pdf | 19 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 PUJ - B 2020-21.pdf | 19 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 PUJ - B 2021-22.pdf | 19 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - CA Certificate - 23-3-23 - Wing B_compressed.pdf | 18 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Parklane construction FY 20-21.pdf | 12 May 2023 |
| Proforma of Allotment letterFile: Allotment letter -order no 30.pdf | 11 May 2023 |
| Building plan approvalFile: Building Plan with B wing in RED.pdf | 10 May 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan with B wing in RED.pdf | 10 May 2023 |
| Declaration in FORM BFile: FORM B Affidavit cum Declaration New.pdf | 10 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 10 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A Engineer certificate.pdf | 10 May 2023 |
| Copy of the legal title reportFile: Search Report 03-05-2023.pdf | 3 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 PUJ - B 2021-22 (1).pdf | 20 Apr 2023 |
| Building plan approvalFile: PMRDA SACNTION RERA.pdf | 19 Apr 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: PMRDA SACNTION RERA.pdf | 19 Apr 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC PMRDA 1477_22-23_1202 RERA.pdf | 19 Apr 2023 |
| Declaration about Commencement CertificateFile: CC PMRDA 1477_22-23_1202 RERA.pdf | 19 Apr 2023 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SHANTI ELIXIR | KESHAV NAGAR | 122 | Completed | Sep 2019 | Sep 2019 |
| PARKLANE PREMIER | WAGHOLI HAVELI PUNE 412207 | 158 | Completed | Dec 2018 | Jul 2017 |
| ANAND VASTU | KOREGAON MUL PUNE | 48 | Completed | Dec 2016 | Aug 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 123 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep PARKLANE URBANJOY- WING B on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Sus Gaon13,700+ in Pune
Filed coordinates, straight-line distance. 111 registered projects within 2 km.
NYATI EQUINOX I
MIHIR HOMES ENTERPRISE LLP
Puraniks Abitante Fiore, Phase 2A
Puranik Buildcon Private Limited
Puraniks Abitante Fiore, Phase 2B
Puranik Buildcon Private Limited
cloud 51
OREE REALITY PVT LTD
CIELO BY VTP LUXE
DELAS REALCON LLP
Puraniks Abitante Fiore Phase 2C1
Puranik Buildcon Private Limited
Builder: Parklane Construction LLP
Parklane Construction LLP has 4 registrations on MahaRERA, including Parklane Urbanjoy -Wing A and PARKLANE URBANJOY- WING B. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if PARKLANE URBANJOY- WING B is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PARKLANE URBANJOY- WING B?
The registered promoter entity is Parklane Construction LLP, a partnership as per the filing. Its LLPIN AAH-5950 and GSTIN 27AATFP4446L1ZH can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PARKLANE URBANJOY- WING B?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for PARKLANE URBANJOY- WING B?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PARKLANE URBANJOY- WING B?
The professionals named in the filing: Architect: Element Five Mr Jaideep Deshpande; Engineer: VS Academy & Consultancy Pratik Jain; Chartered Accountant: KAPIL MUNOT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PARKLANE URBANJOY- WING B?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback