Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 39 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 39 months from the original
6 of 11Construction stages donefurthest along: External plumbing and external plaster, 90%
26 of 37Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 99 documents Report an error

Paramount Enclave, Phase-II, Building No 3, Wing-A, Type-C is a Residential / Group Housing project by BRAJBHOOMI DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000029292 on 18 May 2021. Possession is promised by 30 Jun 2027. The completion date has moved by 39 months from the original filing. 11 of the 37 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameParamount Enclave, Phase-II, Building No 3, Wing-A, Type-C
  • TypeResidential / Group Housing
  • Location
    • Mahim Road
    • Palghar West
    • Mahim
    • Palghar
    • 401404
  • Pincode401404
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000029292
  • ReraGenie IDRG-MH-29812

Builder

  • NameBRAJBHOOMI DEVELOPERS
  • Entity typePartnership
  • PartnersDinesh Yashwant Patil, Vikas Lalpratap Singh

Key dates

this monthRegisteredMay 2021First promiseMar 2024Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 May 2021
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 31 Mar 2024)
  • Buildings1 building record
  • Documents filed99 files

Current status

30%11 of 37 units booked

Figures as on 6 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Paramount Enclave, Building No-3, Wing-A, Type-CNA5537037

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 90%.

Paramount Enclave, Building No-3, Wing-A, Type-C: 75% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises55%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,680 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on6 May 2026
LandownerVillageDistrict
Mayank RealityVasai-Virar City (M Corp)Palghar

Approvals and building plan

Sanctioning authorityVasai Virar City Municipal Corporation
Permissible FSI1680.01
Proposed, not sanctioned1,680 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSiddhivinayak Complex, Station Road, Nallasopara West, Pincode-401203

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNishant P Patil
EngineerMukesh Kumar
Chartered AccountantChandan Choudhary
Chartered AccountantA K Parmar and Co
Chartered AccountantDesmond Fargoes
PartnerRole in project
BRAJBHOOMI DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000019426Mar 2024 → Mar 2025

Reason as filed by the promoterExplanatory note regarding the state of development works in the projects and reason for being not completing development works of the projects within the period declared in the declaration submitted in FORM ‘B’ at the time of making the application for the registration of ‘Paramount Enclave, Phase-II, Building No 3, Wing-A, Type-C’ As per the details mentioned at the time of registration of the project at the MahaRERA Website we had mentioned 31/03/2024 as the project completion date, we will not be able to complete the project due to various unavoidable reasons. Such as 1) After the impact o

EXT99000028089Mar 2024 → Mar 2026

Reason as filed by the promoterExplanatory note regarding the reasoning of Delays for Completion of the Real Estate Project Impact of Pandemic and Rising Construction Material Costs: The COVID-19 pandemic has had a profound and far-reaching impact on the construction industry, both locally and globally. As a direct consequence of the pandemic, there has been a significant and sustained increase in the prices of essential construction materials, including but not limited to cement, steel, copper, electrical components, plumbing materials, and paints. This escalation in material costs has resulted in severe financial strain,

EA07052620861Mar 2024 → Jun 2027

Reason as filed by the promoterImpact of Pandemic and Rising Construction Material Costs: The COVID-19 pandemic has had a profound and far-reaching impact on the construction industry, both locally and globally. As a direct consequence of the pandemic, there has been a significant and sustained increase in the prices of essential construction materials, including but not limited to cement, steel, copper, electrical components, plumbing materials, and paints. This escalation in material costs has resulted in severe financial strain, disrupting the supply chain and leading to delays in procurement and delivery of these materi

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12500651BRAJBHOOMI DEVELOPERSNITIN SANTOSH KHALE24/02/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 May 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 May 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Apr 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 May 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed99

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 99 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 March 26.pdf6 May 2026
Form 2File: Form 2 March 26.pdf6 May 2026
Form 3File: Form 3 March 26 Brajbhoomi Dev.pdf6 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold March 26 - Brajbhoomi Dev.pdf6 May 2026
Form 5 (FY 2025-2026)File: Form 5 FY 25-26 Brajbhoomi Dev.pdf6 May 2026
Form 5 (FY 2024-2025)File: Form 5 Brajbhoomi - FY 24-25.pdf6 May 2026
Form 1File: Form 1 Sept 25.pdf29 Apr 2026
Form 2File: Form 2 Sept 25.pdf29 Apr 2026
Form 3File: Form 3 Sept 25.pdf29 Apr 2026
Disclosure of Sold and Booked InventoryFile: Sold unsold Sept 25.pdf29 Apr 2026
Form 1File: Form 1 Dec 25.pdf29 Apr 2026
Form 2File: Form 2 Dec 25.pdf29 Apr 2026
Form 3File: Form 3 Dec 25.pdf29 Apr 2026
Disclosure of Sold and Booked InventoryFile: Sold unsold Dec 25.pdf29 Apr 2026
Form 1File: Form 1 - architect certificate april to june 25.pdf15 Dec 2025
Form 2File: Form 2 - engineer certificate april to june 2025.pdf15 Dec 2025
Form 3File: Form 3 April - June 25.pdf15 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold June 25 Final.pdf15 Dec 2025
Form 1File: Form 1 - Architect certificate Brajbhoomi- March 25.pdf15 Dec 2025
Form 2File: Form 2 engineer certificate - March 25.pdf15 Dec 2025
Form 3File: Form 3 Brajbhoomi March 25.pdf15 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold March 25.pdf15 Dec 2025
Form 1File: Form 1 Dec 24.pdf15 Dec 2025
Form 2File: Form 2 Dec 24.pdf15 Dec 2025
Form 3File: Form 3 - Dec 24 Signed.pdf15 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Dec 24 Correct.pdf15 Dec 2025
Form 1File: Form 1 Sept 24.pdf15 Dec 2025
Form 2File: Form 2 Eng Sept 24.pdf15 Dec 2025
Form 3File: Form 3 - Sept 24.pdf15 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Sept 24.pdf15 Dec 2025
Form 1File: Form 1 June 24.pdf15 Dec 2025
Form 2File: Form 2 Eng June 24.pdf15 Dec 2025
Form 3File: Form 3 - June 24.pdf15 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory June 24.pdf15 Dec 2025
Form 5 (FY 2024-2025)File: Form 5 Brajbhoomi - FY 24-25.pdf15 Dec 2025
Form 5 (FY 2023-2024)File: Form 5 Signed.pdf15 Dec 2025
Form 5 (FY 2022-2023)File: Form 5 March 2023.pdf15 Dec 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 June 24.pdf7 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sept 24.pdf7 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 24.pdf7 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Eng June 24.pdf7 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Eng Sept 24.pdf7 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec 24.pdf7 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory June 24.pdf7 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Sept 24.pdf7 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Dec 24.pdf7 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Dec 24 Correct.pdf7 Apr 2025
Declaration in FORM BFile: 5 FORM B PROMOTER.pdf2 Apr 2025
Other - LegalFile: 4 Declaration about Litigation.pdf29 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf29 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Signed.pdf17 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - June 24.pdf6 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Sept 24.pdf6 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Dec 24.pdf6 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: braj bhumi develovpers.pdf4 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory .pdf28 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Vikas Singh.pdf28 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Dinesh Patil .pdf28 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form-1 Brajbhoomi -Dec 23.pdf1 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: certificate form-2.pdf1 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - June 23 - Signed.pdf29 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Sept 23 - Signed Copy.pdf29 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Dec 23 - Signed Copy.pdf29 Feb 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf4 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 2023_compressed.pdf4 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 March 2023.pdf4 Jul 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BRAJBHOOMI DEVELOPERS.pdf2 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Scanned Documents.pdf2 Dec 2022
Deviation Report with respect to Allotment letterFile: BRAJBHOOMI DEVELOPERS.pdf2 Dec 2022
Deviation Report with respect to model copy of AgreementFile: BRAJBHOOMI DEVELOPERS.pdf2 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Quality Certificate.pdf23 Nov 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf23 Nov 2022
Proforma of Agreement for saleFile: Proforma Agreement of Sale.pdf23 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Anilkumar Parmar-compressed (1).pdf11 Nov 2022
Details of encumbrances concerned to FinanceFile: Paramount-legal encumbrance .pdf4 Nov 2022
Details of encumbrances concerned to LegalFile: Paramount-legal encumbrance .pdf4 Nov 2022
Declaration about Commencement CertificateFile: Paramount - declaration CC.pdf4 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Paramount - promoters declaration .pdf4 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Paramount - promoters declaration .pdf4 Nov 2022
CERSAI detailsFile: Paramount-CERSAI.pdf4 Nov 2022

How this compares with Palghar

30%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 39 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Paramount Enclave, Phase-II, Building No 3, on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Palghar West3,200+ in Palghar

2 kmParamount Enclave, PhaseCompleted 44Lapsed / revoked 30Other 43Dot size: filed unitsN

Filed coordinates, straight-line distance. 117 registered projects within 2 km.

Builder: BRAJBHOOMI DEVELOPERS

BRAJBHOOMI DEVELOPERS has 1 registration on MahaRERA, including Paramount Enclave, Phase-II, Building No 3, Wing-A, Type-C. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if Paramount Enclave, Phase-II, Building No 3, Wing-A, Type-C is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Paramount Enclave, Phase-II, Building No 3, Wing-A, Type-C?

The registered promoter entity is BRAJBHOOMI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Paramount Enclave, Phase-II, Building No 3, Wing-A, Type-C?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Paramount Enclave, Phase-II, Building No 3, Wing-A, Type-C?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Paramount Enclave, Phase-II, Building No 3, Wing-A, Type-C?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Paramount Enclave, Phase-II, Building No 3, Wing-A, Type-C?

The professionals named in the filing: Architect: Nishant P Patil; Engineer: Mukesh Kumar; Chartered Accountant: Chandan Choudhary; Chartered Accountant: A K Parmar and Co; Chartered Accountant: Desmond Fargoes. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Paramount Enclave, Phase-II, Building No 3, Wing-A, Type-C?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Paramount Enclave, Phase-II, Building No 3, Wing-A, Type-C. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Paramount Enclave, Phase-II, Building No 3, to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.