Home / Browse projects / Palghar, Maharashtra / PARAMOUNT ENCLAVE BUILDING NO 2 TYPE D A WING

Registered No litigation declared Residential / Group Housing project

PARAMOUNT ENCLAVE BUILDING NO 2 TYPE D A WING

By SKYLINE DEVELOPERS

RG-MH-28989 · RERA P99000027349 · Last updated on MahaRERA portal: 7 Jul 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 54 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 54 months from the original
5 of 11Construction stages donefurthest along: Internal walls, 95%
0Complaints at MahaRERAon this registration
Jump to the 49 documents Report an error

PARAMOUNT ENCLAVE BUILDING NO 2 TYPE D A WING is a Residential / Group Housing project by SKYLINE DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000027349 on 4 Dec 2020. Possession is promised by 31 Dec 2027. The completion date has moved by 54 months from the original filing.

At a glance

Project

  • NamePARAMOUNT ENCLAVE BUILDING NO 2 TYPE D A WING
  • TypeResidential / Group Housing
  • Location
    • MAHIM ROAD
    • PALGHAR WEST
    • Mahim
    • Palghar
    • 401404
  • Pincode401404
  • RERA no.P99000027349
  • ReraGenie IDRG-MH-28989

Builder

  • NameSKYLINE DEVELOPERS
  • Entity typePartnership
  • PartnerSHANTILAL BHURARAM PATEL
  • Other registrations14 more →
  • Completed8 of 15
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredDec 2020First promiseJun 2023Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Dec 2020
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Jun 2023)
  • Buildings1 building record
  • Documents filed49 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PARAMOUNT ENCLAVE BUILDING NO 2 TYPE D A WINGNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 7 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

PARAMOUNT ENCLAVE BUILDING NO 2 TYPE D A WING: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%

Progress on shared amenities15

As on 7 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes30%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,717 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1717.37
Proposed, not sanctioned1,717 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNALLASOPARA LINK RD AGARWAL NAGARI CHSL

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVASTU SHILP
EngineerJAY SHREE KRISHNA
Chartered AccountantCHANDAN CHOUDHARY AND ASSOCIATES
PartnerRole in project
SKYLINE DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000017361Jun 2023 → Dec 2027

Reason as filed by the promoterWE CAN'T AVAILABLE THE LABOURS, MATERIALS AND OTHER REQUIRED ESSENTIALS TO COMPLETE THE PROJECT.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Dec 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Dec 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Dec 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Dec 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Jul 2025

Documents filed49

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf7 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf7 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG CERTIFICATE.pdf7 Jul 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: DocScanner Feb 13, 2024 5-06 PM.pdf7 Jul 2025
Other - TechnicalFile: quality asurance certificate.pdf7 Jul 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A SKYLINE.pdf7 Jul 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A SKYLINE- 2025.pdf7 Jul 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: AUDIT REPORT.pdf7 Jul 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: AUDIT REPORT.pdf7 Jul 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: AUDIT REPORT.pdf7 Jul 2025
Declaration in FORM BFile: FORM B.pdf20 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: aRCHITECT cERTIFICATE.pdf20 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer certificate.pdf20 Dec 2023
CERSAI detailsFile: CERSAI.pdf20 Dec 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE SOLD.pdf20 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5.pdf20 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5.pdf20 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: centerline 2021_compressed.pdf6 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: center line 2023.pdf6 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 (2).pdf6 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A.pdf14 Aug 2023
Details of encumbrances concerned to FinanceFile: encumbrance to legal.pdf8 Aug 2023
Details of encumbrances concerned to LegalFile: encumbrance to legal.pdf8 Aug 2023
Declaration about Commencement CertificateFile: declaration.pdf8 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of interest.pdf8 Aug 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about seperate bank account.pdf8 Aug 2023
Deviation Report with respect to Allotment letterFile: Deviation report with respect of allotment letter.pdf8 Aug 2023
Deviation Report with respect to model copy of AgreementFile: Deviation report with respect of sale agreement.pdf8 Aug 2023
Layout approvalFile: layout PDF.pdf2 Dec 2020
Building plan approvalFile: BLUE PRINT PDF.pdf2 Dec 2020
PAN CardFile: SKYLINE PANCARD.pdf2 Dec 2020
Copy of the legal title reportFile: TITLE CERTIFICATE.pdf2 Dec 2020
Copy of the legal title reportFile: SEARCH CERTIFICATE.pdf2 Dec 2020
Copy of the legal title reportFile: search report OLD.PDF2 Dec 2020
Copy of the legal title reportFile: title CERT OLD.PDF2 Dec 2020
Details of encumbrancesFile: INCUMBBARENCE.pdf2 Dec 2020
Copy of Layout Approval (in case of layout)File: layout PDF.pdf2 Dec 2020
Building Plan Approval / NA Order for plotted developmentFile: BLUE PRINT PDF.pdf2 Dec 2020
Commencement Certificates / NA Order for plotted developmentFile: new cc mayank.pdf2 Dec 2020
Commencement Certificates / NA Order for plotted developmentFile: AGREEMENT ONE.pdf2 Dec 2020
Commencement Certificates / NA Order for plotted developmentFile: AGREEMENT TWO.pdf2 Dec 2020
Commencement Certificates / NA Order for plotted developmentFile: AGREEMENT THREE.pdf2 Dec 2020
Commencement Certificates / NA Order for plotted developmentFile: AGREEMENT FOUR.pdf2 Dec 2020
Declaration in FORM BFile: FORM B SKYLINE DEVELOPERS.pdf2 Dec 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT'S CERTIFICATE.pdf2 Dec 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf2 Dec 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf2 Dec 2020
Proforma of Allotment letterFile: SALE AGR PDF.pdf2 Dec 2020
Proforma of Allotment letterFile: ALLOTMENT LETTER PDF.pdf2 Dec 2020

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 54 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PARAMOUNT ENCLAVE BUILDING NO 2 TYPE D A WIN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PALGHAR WEST3,200+ in Palghar

Builder: SKYLINE DEVELOPERS

Skyline Developers has 15 registrations on MahaRERA, including Galaxy Premium Building E1 and E2 and SPRING WOOD PARK. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if PARAMOUNT ENCLAVE BUILDING NO 2 TYPE D A WING is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PARAMOUNT ENCLAVE BUILDING NO 2 TYPE D A WING?

The registered promoter entity is SKYLINE DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PARAMOUNT ENCLAVE BUILDING NO 2 TYPE D A WING?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PARAMOUNT ENCLAVE BUILDING NO 2 TYPE D A WING?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PARAMOUNT ENCLAVE BUILDING NO 2 TYPE D A WING?

The professionals named in the filing: Architect: VASTU SHILP; Engineer: JAY SHREE KRISHNA; Chartered Accountant: CHANDAN CHOUDHARY AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARAMOUNT ENCLAVE BUILDING NO 2 TYPE D A WING?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARAMOUNT ENCLAVE BUILDING NO 2 TYPE D A WING. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARAMOUNT ENCLAVE BUILDING NO 2 TYPE D A WIN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.