Home / Browse projects / PALM WORLD ONE
PALM WORLD ONE
By PALMTREE DEVELOPMENTS PVT. LTD.
RG-MH-20749 · RERA P52100012101 · Last updated on MahaRERA portal: 21 Nov 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 51 months past the filed date
- 37 complaints at MahaRERA
- Completion date moved by 43 months
- 4 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PALM WORLD ONE is a Residential / Group Housing project by PALMTREE DEVELOPMENTS PVT. LTD. in NEAR EON IT PARK, 411014, registered with MahaRERA as P52100012101 on 1 Sep 2017. Possession was promised by 31 Jul 2022 and is now 51 months past that date. The completion date has moved by 43 months from the original filing. 46 of the 66 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 37 complaints are on record with the regulator.
At a glance
Project
- NamePALM WORLD ONE
- TypeResidential / Group Housing
- Location
- GRANT ROAD
- NEAR EON IT PARK
- 411014
- Pincode411014
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100012101
- ReraGenie IDRG-MH-20749
Builder
- NamePALMTREE DEVELOPMENTS PVT. LTD.
- Entity typeCompany
- Managing DirectorsDEBAJYOTI DASGUPTA, ANURAG KHEMKA
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on1 Sep 2017
- Promised completion31 Jul 2022
- Revised completionRevised to 31 Jul 2022 (originally 31 Dec 2018)
- Buildings1 building record
- Documents filed61 files
Current status
Figures as on 21 Nov 2024, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| PALM WORLD ONE | NA | 14 | 11 | 66 | 0 | 66 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 21 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 75%.
PALM WORLD ONE: 54% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 75% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 21 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed235
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| BHUJBAL BROTHERS CONSTRUCTION CO | Pune (CB) | Pune |
| MAHAVEER PROPERTIES | Pune (CB) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DWP INTERICS PVT LTD |
| Engineer | DESIGN WERKZ ENGINEERING PVT LTD |
| Chartered Accountant | R C Jain & Associates |
| Partner | Role in project |
|---|---|
| PALMTREE DEVELOPMENTS PVT. LTD. | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDear Sir / Madam, We, Palmtree Developments Pvt Ltd are developing residential project, PALM WORLD ONE in Survey No 63/2& 63/3, Kharadi, Haveli, Pune 411014 and we were due to complete the project on 31/12/18. Unfortunately, the project has to be stalled / stopped due to insufficient FSI sanctions to complete the project. The subject project is in joint venture with landowners i.e. Bhujbal Brothers Constructions Company & Mahaveer Properties through registered Joint Development Agreement document no 8227- 2014 dated 10th October 2014. In the mentioned agreement, the landowners have committed t
Reason as filed by the promoterDue to non corporation from the landowners, in December 2018 we decided to use our powers handed through power of Attorney to handover the Amenity space to Pune Mucipal Corporation, liaison with the Land Development and other relevant authorities and submit all the documentation required by Pune Municipal Corporation for the remembering FSI approvals. As of today we completed the full RCC till the 11th floor along with the block work and also have various agencies simultaneously working i.e. waterproofing, electrical, plumbing, gypsum, filing etc. at the site. We currently have around 40 skill
Reason as filed by the promoterConstruction work is stalled due to COVID pandamic. Lockdown and non availability of labour force has made it impossible for us to complete the work before the due date.
Reason as filed by the promoterdue to covid
Complaints filed with MahaRERA37
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000010466 | Kanchan Dadasaheb Gharge | Bhujbal Brothers Cinstruction Co. | 06/11/2017 |
| CC005000000022767 | Arif Ebrahim Contractor | Palmtree Developments Private Limited | 14/03/2019 |
| CC005000000022768 | Arif Ebrahim Contractor | Palmtree Developments Private Limited | 14/03/2019 |
| CC005000000022830 | MR VINEET RATHI FOR HUF | PALMTREE DEVELOPERS PRIVATE LIMITED | 27/03/2019 |
| CC005000000022837 | vineet rathi for HUF | PALMTREE DEVELIPERS PRIVATE LIMITED | 01/04/2019 |
| CC005000000043730 | Bhavesh Khanna | Palm World One | 30/11/2019 |
| CC005000000053860 | Mrs. Arti Sourabh Malhotra | Palmtree Developers Private Limited through its Authorized Signatory Mr. Anurag Khemka | 02/01/2020 |
| CC005000000054036 | Tilak Sood | PALMTREE DEVELOPMENTS PVT.LTD. | 13/02/2020 |
| CC005000000054109 | Punit Wani | Palm Tree Developments Pvt Ltd | 20/03/2020 |
| CC005000000064589 | Subhorov Roy | Palmtree Developments Pvt. Ltd. | 05/09/2020 |
| CC005000000064642 | Saurav Shekhar | Palm Tree Developers Pvt. Ltd | 23/09/2020 |
| CC005000000064650 | Prajakta Wani | Palm Tree Developers Pvt. Ltd | 23/09/2020 |
| CC005000000064648 | Amol More | Palm Tree Developers Pvt. Ltd | 03/10/2020 |
| CC005000000085446 | Mr. Ashish Rangrao Chamatkar | Palmtree Developments Private Limited Through its Authorized signatories Mr. Anurag Khemka | 14/04/2021 |
| CC005000000106525 | Mrs. Pooja Bhushan Raikar | Palmtree Developments Private Limited Thr. its Authorized Signatory Mr. Anurag Khemka | 22/01/2022 |
| CC005000000127094 | Anurag Khemka | Mr.Amol More | 14/05/2022 |
| CC005000000127110 | Anurag Khemka | Prajakta Ashok Wani & Hemangi Ashok Wani | 09/06/2022 |
| CC005000000167568 | Martin Prasad | Palm Tree Developers Pvt. Ltd. | 24/09/2022 |
| CC005000000218300 | Mrs Manju Purshottam Lohia | palmtree Development Pvt.Ltd through its Directors | 11/02/2023 |
| CC005000000290038 | Rajesh Chandrakant Sawant | PALMTREE DEVELOPMENTS PRIVATE LIMITED | 09/01/2024 |
| CC005000000310343 | ISHA BALAKANT JHA | PALMTREE DEVELOPMENT PRIVATE LIMITED | 14/02/2024 |
| CC12400153 | Shubham Prashant Kolhe | PALMTREE DEVELOPMENTS PVT. LTD. | 18/09/2024 |
| CC12400152 | Ashish Gajanan Naik | PALMTREE DEVELOPMENTS PVT. LTD. | 18/09/2024 |
| CC12401200 | SUJATA ANIL CHAUTHAIWALE | PALMTREE DEVELOPMENTS PVT. LTD. | 21/12/2024 |
| CC12500286 | SHIVAJI SURESH BHATKHANDE | PALMTREE DEVELOPMENTS PVT. LTD. | 26/01/2025 |
| CC12500138 | KARTIK DATTATRYA KAWARE | PALMTREE DEVELOPMENTS PVT. LTD. | 15/01/2025 |
| CC12500285 | MAHESH MAHADEV NARTAWADEKAR | PALMTREE DEVELOPMENTS PVT. LTD. | 26/01/2025 |
| CC12500287 | PRATIK BHIMRAO NIMBARTE | PALMTREE DEVELOPMENTS PVT. LTD. | 26/01/2025 |
| CC12500284 | VEENY RAINA | PALMTREE DEVELOPMENTS PVT. LTD. | 26/01/2025 |
| CC12500290 | RAJABHAU SUBRAO LONDHE | PALMTREE DEVELOPMENTS PVT. LTD. | 26/01/2025 |
| CC12500292 | Omkar Anirudha Walke | PALMTREE DEVELOPMENTS PVT. LTD. | 27/01/2025 |
| CC12500304 | RAKESH SUBHASH PATNI | PALMTREE DEVELOPMENTS PVT. LTD. | 28/01/2025 |
| CC12500395 | Vaibhav katiyar | PALMTREE DEVELOPMENTS PVT. LTD. | 06/02/2025 |
| CC12500442 | Gaurav Raja Bhandari | PALMTREE DEVELOPMENTS PVT. LTD. | 10/02/2025 |
| CC12500518 | VIVEK BHAUSAHEB JAGTAP | PALMTREE DEVELOPMENTS PVT. LTD. | 15/02/2025 |
| CC12503235 | Palm World One | PALMTREE DEVELOPMENTS PVT. LTD. | 12/09/2025 |
| CC12503819 | Sushant Vidyasagar Soundatte | PALMTREE DEVELOPMENTS PVT. LTD. | 01/11/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Dec 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 21 Nov 2024
Documents filed61
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part-OC Certificate 161024 - Palm Tree.pdf | 21 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part-OC Certificate 161024 - Palm Tree.pdf | 21 Nov 2024 |
| Certificates of CA (Form 3)File: DEC-17.pdf | 11 Sep 2023 |
| Certificates of CA (Form 3)File: MAR-18.pdf | 11 Sep 2023 |
| Certificates of CA (Form 3)File: JUNE-18.pdf | 11 Sep 2023 |
| Certificates of CA (Form 3)File: SEP-18.pdf | 11 Sep 2023 |
| Certificates of CA (Form 3)File: DEC-18.pdf | 11 Sep 2023 |
| Certificates of CA (Form 3)File: MAR-19.pdf | 11 Sep 2023 |
| Certificates of CA (Form 3)File: JUNE -19.pdf | 11 Sep 2023 |
| Certificates of CA (Form 3)File: SEP-19.pdf | 11 Sep 2023 |
| Certificates of CA (Form 3)File: DEC-19.pdf | 11 Sep 2023 |
| Certificates of CA (Form 3)File: MAR-20.pdf | 11 Sep 2023 |
| Certificates of CA (Form 3)File: JUNE-20.pdf | 11 Sep 2023 |
| Certificates of CA (Form 3)File: SEP-20.pdf | 11 Sep 2023 |
| Certificates of CA (Form 3)File: DEC-20.pdf | 11 Sep 2023 |
| Certificates of CA (Form 3)File: MAR-21.pdf | 11 Sep 2023 |
| Certificates of CA (Form 3)File: JUNE-21.pdf | 11 Sep 2023 |
| Certificates of CA (Form 3)File: SEP-21.pdf | 11 Sep 2023 |
| Certificates of CA (Form 3)File: DEC-21.pdf | 11 Sep 2023 |
| Certificates of CA (Form 3)File: MAR-22.pdf | 11 Sep 2023 |
| CERSAI detailsFile: Cersai Certificate.pdf | 23 Mar 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21 Palm tree.pdf | 22 Mar 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 2018-2019 Palm tree.pdf | 4 Mar 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 19-20.pdf | 4 Mar 2022 |
| Disclosure of sold/ booked inventoryFile: DISCOLSURE SOLD AND UNSOLD.pdf | 2 Mar 2022 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CERTIFICATE_1.pdf | 16 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: March 2020.pdf | 16 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: December 2020.pdf | 16 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Certificate.pdf | 3 Jan 2020 |
| Building plan approvalFile: 01.pdf | 5 Dec 2019 |
| Building plan approvalFile: 02.pdf | 5 Dec 2019 |
| Building plan approvalFile: 03.pdf | 5 Dec 2019 |
| Building Plan Approval (IOD)File: 01.pdf | 5 Dec 2019 |
| Building Plan Approval (IOD)File: 02.pdf | 5 Dec 2019 |
| Building Plan Approval (IOD)File: 03.pdf | 5 Dec 2019 |
| Certificates of CA (Form 5)File: Audit_FORM 5.pdf | 14 Dec 2018 |
| Proforma of Allotment letterFile: Draft Allotment Letter.pdf | 3 Dec 2018 |
| Proforma of Allotment letterFile: Draft Agreement to Sale.pdf | 3 Dec 2018 |
| Declaration in FORM BFile: 10 Form B - Declaration of Promoter.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 11 Form 1 - Architect Certificate.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 12 Form 2 - Engineer Certificate.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: 13 Form 3 - CA Certificate.pdf | 31 Jul 2017 |
| Building plan approvalFile: 15 Building Plan IOD 01.pdf | 30 Jul 2017 |
| Building plan approvalFile: 15 Building Plan IOD 02.pdf | 30 Jul 2017 |
| Building plan approvalFile: 15 Building Plan IOD 03.pdf | 30 Jul 2017 |
| Layout approvalFile: 08 Palm World One - Santioned Plan 02.pdf | 30 Jul 2017 |
| Layout approvalFile: 08 Palm World One - Santioned Plan 03.pdf | 30 Jul 2017 |
| Layout approvalFile: 08 Palm World One - Santioned Plan 01.pdf | 30 Jul 2017 |
| PAN CardFile: 05 Palmtree Developments Pvt Ltd - PAN Card.pdf | 30 Jul 2017 |
| Copy of the legal title reportFile: 06 Palm World One - Title Investigation Report 01.pdf | 30 Jul 2017 |
| Copy of the legal title reportFile: 06 Palm World One - Title Investigation Report 02.pdf | 30 Jul 2017 |
| Copy of the legal title reportFile: 06 Palm World One - Title Investigation Report 03.pdf | 30 Jul 2017 |
| Details of encumbrancesFile: 07 RERA Emburances Declaration.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 08 Palm World One - Santioned Plan 01.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 08 Palm World One - Santioned Plan 02.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 08 Palm World One - Santioned Plan 03.pdf | 30 Jul 2017 |
| Building Plan Approval (IOD)File: 15 Building Plan IOD 01.pdf | 30 Jul 2017 |
| Building Plan Approval (IOD)File: 15 Building Plan IOD 02.pdf | 30 Jul 2017 |
| Building Plan Approval (IOD)File: 15 Building Plan IOD 03.pdf | 30 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: 14 Palm World One - Revised Commencement Certificate 140815.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: 09 Declaration of AFS and AL.pdf | 30 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 61 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep PALM WORLD ONE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NEAR EON IT PARK
Filed coordinates, straight-line distance. 68 registered projects within 2 km.
VJ IndiLife Kharadi
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
VJ Central Avenue
Vilas Javdekar Eco Homes
VJ IndiWorks Kharadi Central
Vilas Javdekar Eco Homes
RIVERDALE GRAND
DUVILLE ESTATES PRIVATE LIMITED
Yashwin Orizzonte Phase II
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
ZEN ESTATE
DESTINATION KHARADI DEVELOPERS LLP
Builder: PALMTREE DEVELOPMENTS PVT. LTD.
PALMTREE DEVELOPMENTS PVT. LTD. has 1 registration on MahaRERA, including PALM WORLD ONE. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What does it mean that PALM WORLD ONE shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if PALM WORLD ONE is delayed beyond 31 Jul 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PALM WORLD ONE?
The registered promoter entity is PALMTREE DEVELOPMENTS PVT. LTD., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PALM WORLD ONE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against PALM WORLD ONE?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for PALM WORLD ONE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PALM WORLD ONE?
The professionals named in the filing: Architect: DWP INTERICS PVT LTD; Engineer: DESIGN WERKZ ENGINEERING PVT LTD; Chartered Accountant: R C Jain & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PALM WORLD ONE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback