ReraGenieLog inGet a buyer report

Home / Browse projects / Latur, Maharashtra / P S PATIL RESIDENTIAL BUILDING

Registration lapsed No litigation declared Residential / Group Housing project

P S PATIL RESIDENTIAL BUILDING

By Mukesh Nilkhantrao Jadhav

RG-MH-33280 · RERA P52400080633 · Last updated on MahaRERA portal: 25 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 5 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Latur registration emailed to you, free during the pilot beta.
May 2026Possession promised5 months past this date
1 of 11Construction stages donefurthest along: Basement (if any), 80%
20 of 20Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 43 documents Report an error

P S PATIL RESIDENTIAL BUILDING is a Residential / Group Housing project by Mukesh Nilkhantrao Jadhav in Latur, Maharashtra, registered with MahaRERA as P52400080633 on 23 Jun 2025. Possession was promised by 30 May 2026 and is now 5 months past that date. 0 of the 20 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NameP S PATIL RESIDENTIAL BUILDING
  • TypeResidential / Group Housing
  • Location
    • MOTI NAGAR LATUR MOUJE KANHERI
    • kanheri
    • Latur (M Cl)
    • Latur
    • 413512
  • Pincode413512
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52400080633
  • ReraGenie IDRG-MH-33280

Builder

  • NameMukesh Nilkhantrao Jadhav
  • Entity typeIndividual
  • GSTIN27AFQPJ9298A1ZY
  • Named personmukesh nilkhantrao jadhav
  • Other registrations5 more →
  • Completed5 of 6
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

5 months past promisethis monthRegisteredJun 2025PromisedMay 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on23 Jun 2025
  • Promised completion30 May 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed43 files

Current status

0%0 of 20 units booked

Figures as on 25 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
P S PATIL RESIDENTIAL BUILDING ResidentialNA7520020

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 80%.

P S PATIL RESIDENTIAL BUILDING Residential: 24% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)0%
Plinth80%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 25 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes90%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes25%
Fire protection and fire safety requirementsYes15%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed27

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots27
Closed/Covered27

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area372 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on26 May 2026
LandownerVillageDistrict
MS SAI PREM CONSTRUCTIONLatur (M Cl)Latur

Approvals and building plan

Sanctioning authorityLatur Municipal Corporations
Permissible FSI916.8
Proposed, not sanctioned917 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch4323 KHADGAON, Old Ausa Road, Latur 413512

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSAGAR NANDKUMAR AMBEKAR NANDKUMAR AMBEKAR
EngineerPATHAN SHAHARUKHKHAN INUS
Chartered AccountantRAJGOPAL SARDA
PartnerRole in project
Mukesh Nilkhantrao Jadhav-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Jun 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Jun 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Jun 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 May 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed43

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement certificateFile: CC.pdf25 May 2026
Withdrawal Update Form 1File: FORM 1 ARCHITECT.pdf25 May 2026
Withdrawal Update Form 1File: FORM 1 ARCHITECT.pdf25 May 2026
Withdrawal Update Form 1File: FORM 1 ARCHITECT.pdf25 May 2026
Withdrawal Update Form 1File: FORM 1 ARCHITECT.pdf25 May 2026
Withdrawal Update Form 2File: Form 2 B.pdf25 May 2026
Withdrawal Update Form 2File: Form 2 B.pdf25 May 2026
Withdrawal Update Form 2File: Form 2 B.pdf25 May 2026
Withdrawal Update Form 2File: Form 2 B.pdf25 May 2026
Withdrawal Update Form 3File: CA CERTIFICATE.pdf25 May 2026
Withdrawal Update Form 3File: CA CERTIFICATE.pdf25 May 2026
Withdrawal Update Form 3File: CA CERTIFICATE.pdf25 May 2026
Withdrawal Update Form 3File: CA CERTIFICATE.pdf25 May 2026
Other - TechnicalFile: Explaination-sai prem construction.PDF19 Jun 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Bank Certificate 5-6-25.pdf6 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final form 3 ca to be uploaded on MahaRERA_compressed.pdf17 Apr 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: 1 declaration format A final.pdf17 Apr 2025
Other - FinanceFile: Disclosure for secured-unsecured finance availed for the project-PS Patil Bldg.pdf5 Mar 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for secured-unsecured finance availed for the project-PS Patil Bldg.pdf5 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: Rera Mail sent by LMC latur.pdf20 Jan 2025
Details of encumbrances concerned to FinanceFile: Finance.pdf22 Dec 2024
Other - LegalFile: mail sent by LMC latur.pdf22 Dec 2024
CERSAI detailsFile: CERSAI_Search_Report_200332528930_For_Asset_Based_Search_22_12_2024_12_03_03_329.pdf22 Dec 2024
Details of encumbrances concerned to LegalFile: Finance.pdf22 Dec 2024
Proforma of Agreement for saleFile: AFS draft.pdf22 Dec 2024
Proforma of Allotment letterFile: MODEL FORM OF ALLOTMENT LETTER.pdf1 Dec 2024
Declaration in FORM BFile: Form B Promoter.pdf23 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT.pdf23 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 B.pdf23 Nov 2024
Other - TechnicalFile: Annexure A.pdf23 Nov 2024
Deviation Report with respect to Allotment letterFile: 1 Deviation Report with respect to Allotment letter.pdf1 Aug 2024
Deviation Report with respect to model copy of AgreementFile: 1 Deviation Report with respect to model copy of Agreement.pdf1 Aug 2024
Layout approvalFile: layout.pdf7 Jun 2024
Building plan approvalFile: PLAN.pdf7 Jun 2024
PAN CardFile: Pan Mukesh Jadhav.pdf7 Jun 2024
Copy of the legal title reportFile: title report p s patil.pdf7 Jun 2024
Details of encumbrances concerned to FinanceFile: Legal.pdf7 Jun 2024
Copy of Layout Approval (in case of layout)File: layout.pdf7 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf7 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: PLAN.pdf7 Jun 2024
Declaration about Commencement CertificateFile: Format D.pdf7 Jun 2024
Details of encumbrances concerned to LegalFile: Legal.pdf7 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Other rera.pdf7 Jun 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SAI PREM COMPLEXOLD AUSA ROAD26CompletedSep 2017Jul 2017

How this compares with Latur

0%of this project is bookeddistrict median 0%
10%of Latur projects moved their completion datethis one has not
31%of Latur registrations have lapsed or been cancelledthis one is among them

Computed across the 150+ Latur projects on ReraGenie, from their own filings.

Keep P S PATIL RESIDENTIAL BUILDING on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near kanheri150+ in Latur

2 kmP S PATIL RESIDENTIAL BUCompleted 1Lapsed / revoked 3Other 8Dot size: filed unitsN

Filed coordinates, straight-line distance. 12 registered projects within 2 km.

Builder: Mukesh Nilkhantrao Jadhav

Mukesh Nilkhantrao Jadhav has 6 registrations on MahaRERA, including SAI YASH APARTMENT and SAI MADHUSINDHU APARTMENT. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Latur district page.

Frequently asked questions

What does it mean that P S PATIL RESIDENTIAL BUILDING shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if P S PATIL RESIDENTIAL BUILDING is delayed beyond 30 May 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of P S PATIL RESIDENTIAL BUILDING?

The registered promoter entity is Mukesh Nilkhantrao Jadhav, an individual as per the filing. Its GSTIN 27AFQPJ9298A1ZY can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in P S PATIL RESIDENTIAL BUILDING?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for P S PATIL RESIDENTIAL BUILDING?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at P S PATIL RESIDENTIAL BUILDING?

The professionals named in the filing: Architect: SAGAR NANDKUMAR AMBEKAR NANDKUMAR AMBEKAR; Engineer: PATHAN SHAHARUKHKHAN INUS; Chartered Accountant: RAJGOPAL SARDA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in P S PATIL RESIDENTIAL BUILDING?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About P S PATIL RESIDENTIAL BUILDING. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save P S PATIL RESIDENTIAL BUILDING to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.