Home / Browse projects / OXY ETERNO
OXY ETERNO
RG-MH-17088 · RERA P52100027735 · Last updated on MahaRERA portal: 22 Jul 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 16 months past the filed date
- Completion date moved by 12 months
- 2 extensions taken
- Rs 11.00 crore secured on the land, in favour of STATE BANK OF INDIA
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
OXY ETERNO is a Residential / Group Housing project by KEYSTONE ETERNO LLP in DHANORI, 411015, registered with MahaRERA as P52100027735 on 3 Jan 2021. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 12 months from the original filing. 98 of the 99 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete.
At a glance
Project
- NameOXY ETERNO
- TypeResidential / Group Housing
- Location
- BHARAT DHABA CHOWK
- BEHIND SAI DHAM SOCIETY
- DHANORI
- 411015
- Pincode411015
- RERA no.P52100027735
- ReraGenie IDRG-MH-17088
Builder
- NameKEYSTONE ETERNO LLP
- Entity typePartnership
- GSTIN27AAVFK2465N1ZH
- PartnersKIRAN VASANT PAWAR, DEVIDAS DNYNOBA KADAM, ANIKET BHARAT MOHITE, NIKITA ASHOK BAHIRAT, SHAILESH DNYANESHWAR MOLAK
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on3 Jan 2021
- Promised completion30 Jun 2025
- Revised completionRevised to 30 Jun 2025 (originally 30 Jun 2024)
- Buildings1 building record
- Documents filed95 files
Current status
Figures as on 22 Jul 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A WING | NA | 11 | 10 | 99 | 0 | 99 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 22 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 11 construction stages are filed complete.
A WING: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 22 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed78
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| POOJA YASHODHAN SAKHARE | - | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ATIT ADMULWAR |
| Architect | ATIT SHRIKANT ADMULWAR |
| Engineer | VAIBHAV LAXAMAN MANE |
| Engineer | Vaibhav Laxman Mane |
| Chartered Accountant | YOGESH MALI |
| Chartered Accountant | YOGESH D MALI |
| Partner | Role in project |
|---|---|
| KEYSTONE ETERNO LLP | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterReason for delay is due to material cost increases, 2 Flats booking issue & Completion (NOC) issue.
Reason as filed by the promoterReason for delay is due to material cost increases, 1 Flats booking issue & Completion (MPCB CONSENT TO OPERATE & NALA NOC’S) issue.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 Dec 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 Jun 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Jun 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed95
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 95 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Proforma of Agreement for saleFile: Draft.pdf | 22 Jul 2025 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: सोसायटी प्रमाणपत्र.pdf | 23 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate RERA 31-12-2024 NEW.pdf | 4 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate RERA 31-12-2024.pdf | 4 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 Engineer Certificate RERA 31-12-2024 NEW.pdf | 4 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE 31-12-2024 NEW.pdf | 4 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD CIRCULAR 29 31-12-2024.pdf | 22 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate RERA 30-09-2024 NEW.pdf | 26 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate RERA 30-09-2024.pdf | 26 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 Engineer Certificate RERA 30-09-2024 NEW.pdf | 26 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD CIRCULAR 29 30-09-2024.pdf | 26 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE 30-09-2024 NEW.pdf | 26 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 CA Certificate RERA 31-03-2024.pdf | 26 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate RERA 30-06-2024 NEW.pdf | 28 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate RERA 30-06-2024.pdf | 28 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 Engineer Certificate RERA 30-06-2024 NEW.pdf | 28 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD CIRCULAR 29 30-06-2024.pdf | 28 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form -2 Engineer Certificate RERA 30-06-2024 NEW.pdf | 28 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate RERA 31-03-2024 NEW.pdf | 29 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE 31-03-2024 NEW.pdf | 29 May 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD CIRCULAR 29 31-03-2024.pdf | 29 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 Engineer Certificate RERA 31-03-2024 NEW.pdf | 23 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate RERA 31-03-2024.pdf | 23 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 CA Certificate RERA 31-03-2023.pdf | 8 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate RERA 31-12-2023_compressed (1).pdf | 12 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate RERA 31-12-2023 NEW.pdf | 5 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 Engineer Certificate RERA 31-12-2023 NEW.pdf | 29 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE 31-12-2023 NEW.pdf | 29 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD CIRCULAR 29 31-12-2023.pdf | 29 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 Engineer Certificate RERA 30-09-2023 NEW R1.pdf | 11 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 5 CA Certificate RERA 31-03-2023.pdf | 11 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate RERA 30-09-2023_compressed.pdf | 11 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate RERA 30-09-2023 NEW.pdf | 17 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE 30-09-2023 NEW.pdf | 14 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD CIRCULAR 29 30-09-2023.pdf | 14 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate RERA 30-06-2023 NEW.pdf | 16 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 Engineer Certificate RERA 30-06-2023 NEW.pdf | 16 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE 30-06-2023 NEW.pdf | 16 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD CIRCULAR 29 30-06-2023.pdf | 16 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 Engineer Certificate RERA 31-12-2022 NEW.pdf | 25 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate RERA 31-12-2022_compressed.pdf | 25 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: Sold unsold.pdf | 22 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate RERA 15-10-2022 NEW.pdf | 23 Nov 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 Engineer Certificate RERA 30-09-2022 NEW.pdf | 23 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE 31-03-2022 NEW.pdf | 23 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE 30-06-2022 NEW.pdf | 23 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE 30-09-2022 NEW.pdf | 23 Nov 2022 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD CIRCULAR 29 30-09-2022.pdf | 23 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate RERA 30-09-2022.pdf | 23 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 30-09-2022.pdf | 23 Nov 2022 |
| Proforma of Allotment letterFile: Keystone Eterno - 17-10-2022.pdf | 17 Oct 2022 |
| Layout approvalFile: scan (1)_compressed.pdf | 9 Jun 2022 |
| Building plan approvalFile: scan0073_compressed.pdf | 9 Jun 2022 |
| Building plan approvalFile: scan0074_compressed.pdf | 9 Jun 2022 |
| Building plan approvalFile: scan0075_compressed.pdf | 9 Jun 2022 |
| Building plan approvalFile: scan0076_compressed.pdf | 9 Jun 2022 |
| Building plan approvalFile: scan0077 (1)_compressed.pdf | 9 Jun 2022 |
| Building plan approvalFile: scan0078_compressed.pdf | 9 Jun 2022 |
| Copy of Layout Approval (in case of layout)File: scan (1)_compressed.pdf | 9 Jun 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: scan0073_compressed.pdf | 9 Jun 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: scan0074_compressed.pdf | 9 Jun 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: scan0075_compressed.pdf | 9 Jun 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: scan0076_compressed.pdf | 9 Jun 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: scan0077 (1)_compressed.pdf | 9 Jun 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: scan0078_compressed.pdf | 9 Jun 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: scan0079 (1)_compressed.pdf | 9 Jun 2022 |
| Declaration about Commencement CertificateFile: Decalaration commencement 08-06-2022.pdf | 9 Jun 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate RERA.pdf | 9 Jun 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 Engineer Certificate RERA 31-03-2022_compressed.pdf | 9 Jun 2022 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD CIRCULAR 29 08-06-2022.pdf | 9 Jun 2022 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD CIRCULAR 29 08-06-2022 (2).pdf | 9 Jun 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 Keystone Eterno Llp_compressed.pdf | 9 Jun 2022 |
| CERSAI detailsFile: CERSAI HYPOTHECATION KEYSTONE.pdf | 31 Dec 2021 |
| OtherFile: RERA Partner Letter Keystone Eterno LLP.pdf | 27 Dec 2021 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate (P- I) 01-09-2021.pdf | 19 Nov 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE 31-06-2021.pdf | 19 Nov 2021 |
| Disclosure of sold/ booked inventoryFile: unsold list 30062021.pdf | 19 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 SIGNED-compressed.pdf | 18 Nov 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE 31-03-2021-compressed.pdf | 21 Sep 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: keystone form.pdf | 21 Sep 2021 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|
| OXY BONITA PHASE IIP52100014711 | LOHGAON, Pune | Dec 2017 | Completed | Dec 2019 | Late, Mar 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- All 95 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep OXY ETERNO on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near DHANORI
Kohinoor Viva Pixel- Phase II
RISING ASSOCIATES
VIVACITY
REALCON LANDMARKS LLP
TRIAA VASANTAM CITY CENTER PHASE 1
Triaa Realtors LLP
QUE 101 PHASE I
ANNR Unique Realty LLP
NYATI ERA I
NYATI CONSTRUCTION PRIVATE LIMITED
ONE ARETHA PHASE 1
Triaa Landmarks LLP
Builder: KEYSTONE ETERNO LLP
KEYSTONE ETERNO LLP has 1 registration on MahaRERA, including OXY ETERNO. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record.
Frequently asked questions
What does it mean that OXY ETERNO shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if OXY ETERNO is delayed beyond 30 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of OXY ETERNO?
The registered promoter entity is KEYSTONE ETERNO LLP, a partnership as per the filing. Its GSTIN 27AAVFK2465N1ZH can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in OXY ETERNO?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for OXY ETERNO?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at OXY ETERNO?
The professionals named in the filing: Architect: ATIT ADMULWAR; Architect: ATIT SHRIKANT ADMULWAR; Engineer: VAIBHAV LAXAMAN MANE; Engineer: Vaibhav Laxman Mane; Chartered Accountant: YOGESH MALI; Chartered Accountant: YOGESH D MALI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in OXY ETERNO?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback