Registration lapsed No litigation declared Others project

OXY BONITA PHASE II

By SHREYAS BUILDCON

RG-MH-26772 · RERA P52100014711 · Last updated on MahaRERA portal: 12 May 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 52 months past the filed date
  • Completion date moved by 30 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2022Possession promised52 months past this date
36 of 44Construction stages doneacross 4 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 51 documents Report an error

OXY BONITA PHASE II is a Others project by SHREYAS BUILDCON in Pune, Maharashtra, registered with MahaRERA as P52100014711 on 26 Dec 2017. Possession was promised by 30 Jun 2022 and is now 52 months past that date. The completion date has moved by 30 months from the original filing.

At a glance

Project

  • NameOXY BONITA PHASE II
  • TypeOthers
  • Location
    • OFF PORWAL ROAD
    • LOHGAON
    • Haveli
    • Pune
    • 411047
  • Pincode411047
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100014711
  • ReraGenie IDRG-MH-26772

Builder

  • NameSHREYAS BUILDCON
  • Entity typePartnership
  • PartnersSANDIP KONDIBA SATAV, SUNIL DILIP DEOKAR, DEVIDAS DNYANOBA KADAM, SANDEEP RAJARAM HARPALE, VAISHALI BAJRANG KARLE
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

52 months past promisethis monthRegisteredDec 2017First promiseDec 2019Revised toJun 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on26 Dec 2017
  • Promised completion30 Jun 2022
  • Revised completionRevised to 30 Jun 2022 (originally 31 Dec 2019)
  • Buildings4 building records
  • Documents filed51 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA30000
BNA30000
FNA30000
AMENITY BUILDINGNA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 12 May 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

36 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Podiums (if any), at 0%.

A82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
F82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
AMENITY BUILDING82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 12 May 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes90%
Street LightingYes90%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes90%
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes90%
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed83

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots83
Closed/Covered83
BuildingClosed/CoveredTotal
A3030
B2323
F3030

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,119 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
JANARDAN RAGHUNATH PAWARLOHGAONPune
DNYANESHWAR RAGHUNATH PAWARLOHGAONPune

Approvals and building plan

Permissible FSI7492.26
Proposed, not sanctioned7,492 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchFURSUNGI PUNE

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectATIT ADMULWAR
EngineerVIRAJ MORE
Chartered AccountantPANDURANG BHAPKAR
PartnerRole in project
SHREYAS BUILDCON-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100003960Dec 2019 → Dec 2020

Reason as filed by the promoterAS PER ATTACHED FORM E

EXT52100010236Dec 2019 → Jun 2022

Reason as filed by the promoterWe would like to inform you that booking of Flats & recovery of sold units are totally hampered due to current Covid-19 Pandemic. Which affects on our ongoing work activity. So, we kindly request you to please give us extension for above said project for 1 year (up to 30/06/2022). Building "A" & "F" Flat 76 PMC Completion, Building "B" Landowners 32 Flats And Amenity Building 18 Shops (Landowners 8 Shops) , Amenity Building 12 Offices (Landowners 8 Offices ) Building B & Amenity Building Work in Progress

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Dec 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 May 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Dec 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 25 Mar 2023

Documents filed51

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Layout approvalFile: PLAN_compressed (1).pdf12 May 2023
Copy of Layout Approval (in case of layout)File: PLAN_compressed (1).pdf12 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 Engineer Certificate RERA 25-03-2023 NEW R1.pdf11 May 2023
Certificates of CA (Form 3)File: Form - 3_compressed (1).pdf11 May 2023
Certificates of CA (Form 5)File: Form - 5.pdf11 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate RERA 2021-2022 NEW.pdf25 Mar 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: पार्ट भोगवटा पत्र बिल्डिंग B व एमिनिटी बिल्डिंग.pdf25 Mar 2023
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf22 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019-20 SHREYAS BUILDCON.pdf22 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 2020-21 SHREYAS BUILDCON.pdf22 Jul 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Scan.pdf22 Jul 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect’s Certificate of Percentage of Completion of Work (Form 1)_compressed.pdf3 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM-2A.pdf3 Jul 2021
Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory.pdf3 Jul 2021
Certificates of CA (Form 5)File: FORM 5.pdf3 Jul 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate.pdf3 Jul 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf26 Dec 2019
PAN CardFile: PAN.pdf23 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 - OW-MB-2019-20-135 SHREYAS BUILDCON.pdf10 Dec 2019
Layout approvalFile: LAYOUT.pdf6 Dec 2019
Layout approvalFile: WING A.pdf6 Dec 2019
Building plan approvalFile: WING B.pdf6 Dec 2019
Building plan approvalFile: WING F.pdf6 Dec 2019
Building plan approvalFile: Amenity Building.pdf6 Dec 2019
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf6 Dec 2019
Copy of Layout Approval (in case of layout)File: WING A.pdf6 Dec 2019
Building Plan Approval (IOD)File: WING B.pdf6 Dec 2019
Building Plan Approval (IOD)File: WING F.pdf6 Dec 2019
Building Plan Approval (IOD)File: Amenity Building.pdf6 Dec 2019
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A.pdf27 Nov 2019
Certificates of CA (Form 5)File: Shreyas Buildcon Form No 5.PDF22 Jul 2019
Building plan approvalFile: A WING.pdf22 Oct 2018
Building plan approvalFile: B WING.pdf22 Oct 2018
Building plan approvalFile: F WING.pdf22 Oct 2018
Building Plan Approval (IOD)File: A WING.pdf22 Oct 2018
Building Plan Approval (IOD)File: B WING.pdf22 Oct 2018
Building Plan Approval (IOD)File: F WING.pdf22 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: commencement certificate.pdf20 Apr 2018
Certificates of CA (Form 3)File: CA Certificate.PDF20 Dec 2017
Layout approvalFile: Layout.pdf15 Dec 2017
Building plan approvalFile: Amenity space.pdf15 Dec 2017
Building plan approvalFile: WING B.pdf15 Dec 2017
Building plan approvalFile: WING F.pdf15 Dec 2017
Copy of the legal title reportFile: SEARCH TITILE REPORT.pdf15 Dec 2017
Details of encumbrancesFile: Bajaj Loan index II.pdf15 Dec 2017
Copy of Layout Approval (in case of layout)File: Layout.pdf15 Dec 2017
Building Plan Approval (IOD)File: Amenity space.pdf15 Dec 2017
Building Plan Approval (IOD)File: WING B.pdf15 Dec 2017
Building Plan Approval (IOD)File: WING F.pdf15 Dec 2017
Declaration in FORM BFile: Form B for Builder.pdf15 Dec 2017
Proforma of Allotment letterFile: allotment letter and agreement to sale.pdf15 Dec 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 30 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep OXY BONITA PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near LOHGAON13,700+ in Pune

2 kmOXY BONITA PHASE IICompleted 64Lapsed / revoked 23Other 80Dot size: filed unitsN

Filed coordinates, straight-line distance. 167 registered projects within 2 km.

Builder: SHREYAS BUILDCON

SHREYAS BUILDCON has 2 registrations on MahaRERA, including OXY BONITA and OXY BONITA PHASE II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that OXY BONITA PHASE II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if OXY BONITA PHASE II is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of OXY BONITA PHASE II?

The registered promoter entity is SHREYAS BUILDCON, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in OXY BONITA PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for OXY BONITA PHASE II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at OXY BONITA PHASE II?

The professionals named in the filing: Architect: ATIT ADMULWAR; Engineer: VIRAJ MORE; Chartered Accountant: PANDURANG BHAPKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in OXY BONITA PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About OXY BONITA PHASE II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save OXY BONITA PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.