Home / Browse projects / Pune, Maharashtra / OXY DESIRE

Registration lapsed No litigation declared Residential / Group Housing project

OXY DESIRE

By VENKATESH ASSOCIATES

RG-MH-10130 · RERA P52100002355 · Last updated on MahaRERA portal: 8 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 28 months past the filed date
  • Completion date moved by 66 months
  • 5 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2024Possession promised28 months past this date
18 of 22Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 95%
0Complaints at MahaRERAon this registration
Jump to the 69 documents Report an error

OXY DESIRE is a Residential / Group Housing project by VENKATESH ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100002355 on 31 Jul 2017. Possession was promised by 30 Jun 2024 and is now 28 months past that date. The completion date has moved by 66 months from the original filing.

At a glance

Project

  • NameOXY DESIRE
  • TypeResidential / Group Housing
  • Location
    • BAKORI ROAD
    • GADE VASTI
    • WAGHOLI
    • Haveli
    • Pune
    • 412207
  • Pincode412207
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100002355
  • ReraGenie IDRG-MH-10130

Builder

  • NameVENKATESH ASSOCIATES
  • Entity typePartnership
  • PartnersKIRAN VASANT PAWAR, SANDIP KONDIBA SATAV, SUNIL DILIP DEOKAR, RAHUL KONDIBA SATAV
  • Other registrations13 more →
  • Completed7 of 14
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects12 →

Key dates

28 months past promisethis monthRegisteredJul 2017First promiseDec 2018Revised toJun 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Jul 2017
  • Promised completion30 Jun 2024
  • Revised completionRevised to 30 Jun 2024 (originally 31 Dec 2018)
  • Buildings2 building records
  • Documents filed69 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA140000
BNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 8 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 95%.

A90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
B90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 8 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed220

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots220
Closed/Covered115
Open Space105
BuildingClosed/CoveredOpen SpaceTotal
A425496
B7351124

Land and ownership6

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,100 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
LandownerVillageDistrict
RAMHARI BABUSHA GADEWAGHOLIPune
ARUN BABUSHA GADEWAGHOLIPune
Mr. Dilip Sadashiv Deokar-Pune
MR DILIP SADASHIV DEOKAR-Pune
MR ARUN BABUSHA GADEWAGHOLIPune
RAM HARI GADEWAGHOLIPune

Approvals and building plan

Permissible FSI10794.99
Proposed, not sanctioned8,508 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOFFICE NO 2,GOODWILL LANDMARK,KHARADI BYPASS ROAD ,PUNE 411014

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMR ATIT ADMULWAR
EngineerMR R K RANDHAVE
PartnerRole in project
VENKATESH ASSOCIATES-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100012091Dec 2018 → Jun 2023

Reason as filed by the promoterDear sir , As per Rera Authority guideline section 7(3) We are apply for extension of proposed completion date upto 30/06/2023 . Project are delay due to Covid -19 Lockdown effect , Booking Shortage , Labour shortage and Building Permission authority Complication of new Rules and Regulation But till date upto 90 % project are completed and we have taken 51 % consent of sold tenement so pls consider this request and exend the proposed completion date upto 30/06/2023 Thanking You ,

EXT52100001158Dec 2018 → Apr 2020

Reason as filed by the promoterReason for delay which is mentioned below uploaded document

EXT52100005802Dec 2018 → Apr 2020

Reason as filed by the promoterLOCAL LEVEL BUILDING PERMISSION AUTHORITY PMRDA CHANGES SANCTIONING NORMS AND RULES DUE TO DELAY REVISED /FINAL SANCTION

EXT52100006241Dec 2018 → Dec 2021

Reason as filed by the promoterAs per Extension application Number EXT52100005802 We apply for extension for 1 year i.e Dec 2019 to Dec 2020 but as per Rera Authority its Approved till 30/04/2020 then As per discussion to Rera Helpline and Rera Authority require 51 % of concern letter of allotee on mail dated 27/04/2020 and As per MahaRERA Order No : - 14 /2020 No. MahaRERA / Secy /Order/ 26 /2020 Date- 18/05/2020 vide Extension already 6 month i.e 31/10/2020 But As per Previous Extension application and Rera Authority requirement We are uploaded 51 % of Conern of allotee so please consider and Update extension Date i.e 30/

EXT52100017095Dec 2018 → Jun 2024

Reason as filed by the promoterDear sir , Till date about 98 % project work are completed , Society formation also completed out of 238 tenement 223 tenement are sold only few i.e 10 tenement remaning for sale . And after 4-5 months PMRDA planning authority New Development Plan are finalized then Project completion certificate process start from our side and within 1-2 months given Completion Certificate also , We are uploaded 51 % of Consent of allotee so please consider and Update extension Date upto 30/06/2024

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Oct 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Mar 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Jun 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed69

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: form 4 desire.pdf8 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM- 1 DESIRE_0001.pdf20 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM -2 DESIRE_0001_compressed.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: BOOKING DESIRE_0001_compressed.pdf20 Oct 2023
Certificates of CA (Form 3)File: FORM-3 DESIRE_compressed.pdf20 Oct 2023
Declaration in FORM BFile: DEVELOPER.pdf21 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM - 5.pdf21 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Desire Arch Certificate_0001.pdf8 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Desire Engg Cert_0001_compressed.pdf8 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Desire Quality Certificate_0001.pdf8 Jul 2023
Disclosure of sold/ booked inventoryFile: A wing Sold Flat_0001.pdf8 Jul 2023
Disclosure of sold/ booked inventoryFile: B wing Sold Flat_0001_compressed.pdf8 Jul 2023
Certificates of CA (Form 3)File: Desire CA Certificate_0001_compressed.pdf8 Jul 2023
Certificates of CA (Form 5)File: Desire Form-5_0001.pdf8 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf5 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf5 May 2023
Certificates of CA (Form 3)File: FORM 3 (2)_compressed.pdf5 May 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration Certificate.pdf5 May 2023
Building plan approvalFile: jpg2pdf (1)_compressed.pdf3 Mar 2023
Building Plan Approval (IOD)File: jpg2pdf (1)_compressed.pdf3 Mar 2023
Disclosure of sold/ booked inventoryFile: Booking_compressed.pdf28 Feb 2023
Declaration about Commencement CertificateFile: CC DECLARATION.pdf22 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 A 2019-20.pdf22 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 A 2020-21.pdf22 Jun 2022
CERSAI detailsFile: cersai 4-6_compressed.pdf22 Jun 2022
Disclosure of sold/ booked inventoryFile: Booking details_compressed.pdf22 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: RERA FORM 5 18-19.pdf22 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA FORM 5 19-20.pdf22 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 2 A 2020-21.pdf22 Jun 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Oxy Desire Architect Letter.pdf16 Sep 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf16 Sep 2020
Certificates of CA (Form 3)File: C A certificate.pdf16 Sep 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Oxy Desire Engineer Certificate 1-1-2020.PDF22 Feb 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate.PDF13 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Oxy Desire 24-9-2019_compressed.pdf25 Oct 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Oxy Desire Engineer Certificate 1-10-2019.PDF25 Oct 2019
Layout approvalFile: PLAN 1.pdf4 Oct 2019
Details of encumbrancesFile: ECL Finance.pdf4 Oct 2019
Copy of Layout Approval (in case of layout)File: PLAN 1.pdf4 Oct 2019
Building plan approvalFile: 1.pdf22 Jun 2019
Building Plan Approval (IOD)File: 1.pdf22 Jun 2019
Commencement Certificates / NA Order for plotted developmentFile: 12_compressed.pdf22 Jun 2019
Certificates of CA (Form 5)File: form 5 desire.pdf3 Apr 2019
Certificates of CA (Form 3)File: Desire-Certificate Sept-18-ilovepdf-compressed.pdf5 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: DESIRE ARCHITECTS CERTIFICATE 01-10-2018.PDF24 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: DESIRE ARCHITECTS CERTIFICATE 01-07-2018.PDF3 Aug 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Oxy Desire 1-07-2018.PDF3 Aug 2018
Certificates of CA (Form 3)File: Rera Certificet-Oxy Desire-July 18.pdf3 Aug 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Oxy Desire.pdf26 Jul 2017
Certificates of CA (Form 3)File: C A Certifice Oxy Desire.PDF26 Jul 2017
Layout approvalFile: layout.pdf19 Jul 2017
Building plan approvalFile: wing A.pdf19 Jul 2017
Building plan approvalFile: wing A1.pdf19 Jul 2017
Building plan approvalFile: wing B.pdf19 Jul 2017
Building plan approvalFile: wing B1.pdf19 Jul 2017
Building plan approvalFile: open space club house.pdf19 Jul 2017
PAN CardFile: ASSOCITES.PDF19 Jul 2017
Copy of the legal title reportFile: New Search Title Oxy Desire .pdf19 Jul 2017
Details of encumbrancesFile: DCB INDEX II.pdf19 Jul 2017
Copy of Layout Approval (in case of layout)File: layout.pdf19 Jul 2017
Building Plan Approval (IOD)File: wing A.pdf19 Jul 2017
Building Plan Approval (IOD)File: wing A1.pdf19 Jul 2017
Building Plan Approval (IOD)File: wing B.pdf19 Jul 2017
Building Plan Approval (IOD)File: wing B1.pdf19 Jul 2017
Building Plan Approval (IOD)File: open space club house.pdf19 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Desire Commencement Certificate.pdf19 Jul 2017
Declaration in FORM BFile: Oxy Desire FORM B PROMOTER.pdf19 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE (OXY DESIRE).PDF19 Jul 2017
Proforma of Allotment letterFile: allotment letter and agreement to sale.pdf19 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
OXY PRIMOGAT NO 559 1 WAGHOLI TAL HAVELI PUNE231CompletedJun 2015Late, Sep 2016

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 66 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep OXY DESIRE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GADE VASTI13,700+ in Pune

2 kmOXY DESIRECompleted 31Lapsed / revoked 11Other 20Dot size: filed unitsN

Filed coordinates, straight-line distance. 62 registered projects within 2 km.

Builder: VENKATESH ASSOCIATES

VENKATESH ASSOCIATES has 14 registrations on MahaRERA, including OXY EVOLVE and OXY DESIRE. Its filings disclose 12 earlier MahaRERA projects: declares 6 of 9 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that OXY DESIRE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if OXY DESIRE is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of OXY DESIRE?

The registered promoter entity is VENKATESH ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in OXY DESIRE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for OXY DESIRE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at OXY DESIRE?

The professionals named in the filing: Architect: MR ATIT ADMULWAR; Engineer: MR R K RANDHAVE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in OXY DESIRE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About OXY DESIRE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save OXY DESIRE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.