Home / Browse projects / Pune, Maharashtra / OM MANGALAM DISHA
OM MANGALAM DISHA
RG-MH-71002 · RERA P52100048442 · Last updated on MahaRERA portal: 3 Jun 2026
Source: official MahaRERA filing
Red flags
- Completion date moved by 5 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
OM MANGALAM DISHA is a Others project by SHRI ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100048442 on 3 Jan 2023. The registration is recorded completed; possession was promised by 30 Sep 2026. The completion date has moved by 5 months from the original filing. 104 of the 130 units on this registration are recorded sold or booked, and 27 of 33 construction stages are filed complete.
At a glance
Project
- NameOM MANGALAM DISHA
- TypeOthers
- Location
- Near Express Highway
- Village Kiwale
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 412101
- Pincode412101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100048442
- ReraGenie IDRG-MH-71002
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on3 Jan 2023
- Promised completion30 Sep 2026
- Revised completionRevised to 30 Sep 2026 (originally 1 Apr 2026)
- Buildings3 building records
- Documents filed154 files
Current status
Figures as on 3 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A Wing | NA | 12 | 10 | 36 | 7 | 43 |
| B Wing | NA | 12 | 10 | 36 | 8 | 44 |
| C Wing | NA | 12 | 10 | 36 | 7 | 43 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 3 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
27 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.
A Wing82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B Wing82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
C Wing82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 3 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed220
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A Wing | 70 | 3 | 73 |
| B Wing | 70 | 3 | 73 |
| C Wing | 70 | 4 | 74 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| B Wing | NA | Rs 11.99 cr | Rs 11.99 cr |
| C Wing | NA | Rs 11.88 cr | Rs 11.88 cr |
| A Wing | NA | Rs 11.83 cr | Rs 11.83 cr |
| - | NA | Rs 3.30 cr | Rs 3.20 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | The Zine Studio |
| Engineer | Vijay Gawade |
| Chartered Accountant | V L JAIN & CO |
| Chartered Accountant | V S A P AND COMPANY |
| Chartered Accountant | V L JAIN AND CO |
| Partner | Role in project |
|---|---|
| SHRI ASSOCIATES | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterProject is complete in all respect within timelines and OC is obtained for 108 units of total 130 units. The entire structural and civil construction work of the project has been completed. Architect certificate for completion for entire project along with NOCs from Water, Fire, Drainage, Lift, Garden are also obtained for entire project and submitted with this application. The balance work is limited to amenities, one side ramp and road & footpaths, which is presently under progress. The pending work is expected to be completed within 30 to 45 days, i.e., before May 2026. Further, possession
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Nov 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 May 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 May 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed154
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 154 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: Occupancy Certificate.pdf | 3 Jun 2026 |
| Layout approvalFile: Plan 01.pdf | 21 May 2026 |
| Building plan approvalFile: Plan 02.pdf | 21 May 2026 |
| Building plan approvalFile: Plan 2.pdf | 3 May 2026 |
| Building plan approvalFile: plan 3.pdf | 3 May 2026 |
| Building plan approvalFile: plan 4.pdf | 3 May 2026 |
| Building plan approvalFile: plan 5.pdf | 3 May 2026 |
| Building plan approvalFile: plan 6.pdf | 3 May 2026 |
| Building plan approvalFile: plan 7.pdf | 3 May 2026 |
| Withdrawal Update Form 1File: Form 1 for FY 2025-26 Q4- OMD.pdf | 2 May 2026 |
| Withdrawal Update Form 2File: Form 2 for FY 2025-26 Q4- OMD.pdf | 2 May 2026 |
| Withdrawal Update Form 3File: Form 3 for FY 2025-26 Q4 - OMD.pdf | 2 May 2026 |
| Withdrawal Update Form 1File: Form 1 for FY 2025-26 Q4- OMD.pdf | 9 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 for FY 2025-26 Q4- OMD.pdf | 9 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 for FY 2025-26 Q4 - OMD.pdf | 9 Apr 2026 |
| Form 2A (FY 2025-2026)File: Form 2A FY 2025-26 OMD final.pdf | 9 Apr 2026 |
| Withdrawal Update Form 1File: ARCHITECT CERTIFICATE FY 25-26 Q1 DISHA.pdf | 27 Mar 2026 |
| Withdrawal Update Form 1File: Final Form 1 for FY 2025-26 Q2.pdf | 27 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 for FY 2025-26 Q3- OMD.pdf | 27 Mar 2026 |
| Withdrawal Update Form 2File: ENGINEER CERTIFICATE DISHA FY 2025-26 Q1.pdf | 27 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 FY 2025-26 Q2.pdf | 27 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 for FY 2025-26 Q3- OMD.pdf | 27 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 for FY 2025-26 Q1 OMD FINAL.pdf | 27 Mar 2026 |
| Withdrawal Update Form 3File: CA Certificate Om Mangalam Disha FY 2025-2026 Q2.pdf | 27 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 for FY 2025-26 Q3- OMD Final.pdf | 27 Mar 2026 |
| Form 2A (FY 2024-2025)File: MahaRera-New-Format-of-Form-2A- DISHA.pdf | 15 Dec 2025 |
| Form 5 (FY 2024-2025)File: FORM 5 FY 2024-25-OMD.pdf | 24 Nov 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf | 30 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 6 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE Form 2- Disha Q4.pdf | 6 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: ENGINEER CERTIFICATE 2A- Disha Q4.pdf | 6 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: om managalam disha form 3 Q4.pdf | 3 May 2025 |
| Disclosure of sold/ booked inventoryFile: Promoter Diclosure Disha.pdf | 3 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - Disha Q3 Resize.pdf | 1 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Disha Q3.pdf | 1 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - Disha Q3.pdf | 1 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Promoter Disclosure - Disha Q3.pdf | 1 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A FY 22-23.pdf | 13 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A OMD FY 23-24 Q4.pdf | 13 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: SA-FY2324-FORM 5-DISHA.pdf | 4 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form -2 OMD FY 24-25 Q-2.pdf | 5 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 24-25 Q2 PATH.pdf | 28 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 FY 24-25 Q2 OMD.pdf | 28 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 ENGINEER CERTIFICATE DISHA Q2.pdf | 28 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: PROMOTERS DISCLOSURE - DISHA Q2.pdf | 28 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE DISHA.pdf | 8 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE DISHA.pdf | 8 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: PROMOTERS DISCLOSURE DISHA.pdf | 8 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 FY 2024-25 Q1 OMD.pdf | 8 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Promoter Disclosure FY 23-24 Q4.pdf | 16 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 OMD FY 23-24 Q4.pdf | 16 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 OMD FY 23-24 Q4.pdf | 9 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 OMD FY 23-24 Q4.pdf | 9 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DISHA ARCH CERT FY 23-24 Q3.pdf | 13 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DISHA ENGG CERT FY 23-24 Q3.pdf | 13 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: DISHA PROMOTER DISCLOSURE FY 23-24 Q3.pdf | 13 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate OMD FY 23-24 Q3.pdf | 13 Feb 2024 |
| Proforma of Agreement for saleFile: AGR TO SALE -DRAFT -DISHA -PLOT NO-4B MHADA DT 18-01-2024.pdf | 18 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate OMD Q1 FY 22-23 Revised.pdf | 14 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: SA-FY2223-OM MANGALAM DISHA-FORM 5 FY 2022-23.pdf | 22 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DISHA ARCH CERT FY 23-24 Q2.pdf | 8 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SA-DISHA-FORM 2 ENGG CERT.pdf | 8 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: SA- DISHA PROMOTER DISCLOSURE FY 23-24 Q2.pdf | 8 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DISHA CA CERTIFICATE Q2.pdf | 8 Nov 2023 |
| Building plan approvalFile: Plan 1.pdf | 12 Oct 2023 |
| Building plan approvalFile: Plan 2.pdf | 12 Oct 2023 |
| Building plan approvalFile: Plan 3.pdf | 12 Oct 2023 |
| Building plan approvalFile: Plan 4.pdf | 12 Oct 2023 |
| Building plan approvalFile: Plan 5.pdf | 12 Oct 2023 |
| Building plan approvalFile: Plan 6.pdf | 12 Oct 2023 |
| Building plan approvalFile: Plan 7.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 1.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 2.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 3.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 4.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 5.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 6.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 7.pdf | 12 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 12 Oct 2023 |
| Declaration about Commencement CertificateFile: OMD-DECLARATION.pdf | 12 Oct 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Sai Paradise | Plot No C S No 12-1 To 7 Bangalore Pune Highway Punavale Pune- 411033 | 368 | Completed | Dec 2021 | Late, Mar 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 154 filed documents as one ZIP, foldered, with a manifest
Keep OM MANGALAM DISHA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Village Kiwale13,700+ in Pune
Filed coordinates, straight-line distance. 216 registered projects within 2 km.
Godrej Park Greens
Godrej Skyline Developers Limited
FOREST GROVE AT GODREJ PARK GREENS
Godrej Skyline Developers Limited
Om Mangalam Samruddhi
NDG Homes LLP
PCMC EWS KIWALE
Pimpri Chinchwad Municipal Corporation
Godrej Nurture
Godrej Skyline Developers Limited
My Home Sanctuary Phase I
MAMURDI DEVELOPERS LLP
Builder: SHRI ASSOCIATES
SHRI ASSOCIATES has 5 registrations on MahaRERA, including OM MANGALAM CHAITANYA and OM MANGALAM YASH. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if OM MANGALAM DISHA is delayed beyond 30 Sep 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of OM MANGALAM DISHA?
The registered promoter entity is SHRI ASSOCIATES, an others as per the filing. Its GSTIN 27AAKAS6978E2ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in OM MANGALAM DISHA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for OM MANGALAM DISHA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at OM MANGALAM DISHA?
The professionals named in the filing: Architect: The Zine Studio; Engineer: Vijay Gawade; Chartered Accountant: V L JAIN & CO; Chartered Accountant: V S A P AND COMPANY; Chartered Accountant: V L JAIN AND CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in OM MANGALAM DISHA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback