Home / Browse projects / Pune, Maharashtra / OM MANGALAM CHAITANYA
OM MANGALAM CHAITANYA
RG-MH-22417 · RERA P52100031241 · Last updated on MahaRERA portal: 24 Nov 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Possession 1 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
OM MANGALAM CHAITANYA is a Others project by SHRI ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100031241 on 11 Oct 2021. Possession was promised by 30 Sep 2026 and is now 1 months past that date. 514 of the 518 units on this registration are recorded sold or booked, and 45 of 55 construction stages are filed complete.
At a glance
Project
- NameOM MANGALAM CHAITANYA
- TypeOthers
- Location
- ADDJOING MUMBAI PUNE EXPRESS HIGHWAY
- VILLAGE KIWALE
- Kiwale
- Haveli
- Pune
- 412101
- Pincode412101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100031241
- ReraGenie IDRG-MH-22417
Builder
- NameSHRI ASSOCIATES
- Entity typeOthers
- GSTIN27AAKAS6978E2ZU
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnersNARESH THAKURDAS WADHWANI WADHWANI, AJAY DEVELOPERS DEVELOPERS, NIRMAL THAKURDAS WADHWANI WADHWANI, DHARMESH THAKURDAS WADHWANI WADHWANI
- Other registrations4 more →
- Completed1 of 5
- Past their filed date1
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on11 Oct 2021
- Promised completion30 Sep 2026
- Revised completionNone
- Buildings5 building records
- Documents filed219 files
Current status
Figures as on 24 Nov 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| C BUILDING | NA | 15 | 14 | 138 | 0 | 138 |
| E BUILDING | NA | 1 | 1 | 0 | 3 | 3 |
| D BUILDING - MHADA | NA | 8 | 8 | 56 | 4 | 60 |
| A BUILDING | NA | 15 | 14 | 138 | 0 | 138 |
| B BUILDING | NA | 15 | 14 | 179 | 0 | 179 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 24 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
45 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Podiums (if any), at 0%.
C BUILDING82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
E BUILDING82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
D BUILDING - MHADA82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
A BUILDING82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B BUILDING82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities19
As on 24 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
| TOP TERRACE GARDEN | Yes | 100% |
| SWIMMING POOL | Yes | 100% |
| SOLAR SYSTEM | Yes | 100% |
| MULTILEVEL CAR PARKING | Yes | 100% |
Parking filed358
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| C BUILDING | 78 | 13 | 91 |
| E BUILDING | 5 | 2 | 7 |
| D BUILDING - MHADA | 51 | 2 | 53 |
| A BUILDING | 87 | 20 | 107 |
| B BUILDING | 89 | 11 | 100 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SANKALP DESIGNER |
| Architect | G A BHILARE CONSULTANT PVT LTD |
| Architect | GREE MEP CONSULTANT |
| Engineer | VIJAY GAVADE |
| Chartered Accountant | V L JAIN AND CO |
| Chartered Accountant | V S A P AND COMPANY |
| Partner | Role in project |
|---|---|
| SHRI ASSOCIATES | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Sep 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Sep 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 Aug 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 24 Mar 2025
Documents filed219
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 219 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2024-2025)File: FORM 5 FY 2024-25-OMC.pdf | 24 Nov 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Coporation Email to RERA.pdf | 24 Mar 2025 |
| Other - TechnicalFile: Coporation Email to RERA.pdf | 24 Mar 2025 |
| Other - TechnicalFile: OM MANGALAM CHAITANYA FORM 4.pdf | 24 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Chaitanya Q3.pdf | 1 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Chaitanya Q3.pdf | 1 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Chaitanya Q3.pdf | 1 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Promoter Disclosure Chaitanya Q3.pdf | 1 Feb 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: OM MANGALAM CHAITANYA FORM 4.pdf | 4 Jan 2025 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: OM MANGALAM CHAITANY SOC REG CERTI.pdf | 4 Jan 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: completion certificate - omc.pdf | 4 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: SA-FY2324-FORM 5-CHAITANYA.pdf | 4 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - OMC FY 24-25 Q-2.pdf | 5 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ARCHITECT CERTIFICATE FY24-25 Q2 CHAITANYA.pdf | 26 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 ENGINEER CERTIFICATE - CHAITANYA Q2.pdf | 26 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: PROMOTERS DISCLOSURE - CHAITANYA Q2.pdf | 26 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 24-25 Q1.pdf | 6 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 FY 24-25 Q1.pdf | 6 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: PROMOTERS DISCLOSURE CHAITANYA.pdf | 6 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form -3 FY 2024-25 Q1 OMC.pdf | 6 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Promoter Disclosure OMC FY 23-24 Q4.pdf | 16 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA CERTIFICATE OMC FY 23-24 Q4.pdf | 16 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 OMC FY 23-24 Q4.pdf | 9 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 OMC FY 23-24 Q4.pdf | 9 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A OMC FY 23-24.pdf | 9 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE - CHAITANYA FY 23-24 Q 3.pdf | 12 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERTIFICATE - CHAITANYA FY 23-24 Q 3.pdf | 12 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: CHAITANYA ENGG CERT FY 2023 24 Q3.pdf | 12 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: CHAITANYA PROMOTER DISCLOSURE FY 23-24 Q3.pdf | 12 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3 - Q3 OMC.pdf | 12 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Q1 OMC Revised.pdf | 14 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CA Certificate Form 5 (OMC) FY 2022-23.pdf | 22 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: CA Certificate Form 5 (OMC) FY 2022-23.pdf | 22 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SA CHAITANYA - ARCHITECTS CERTIFICATE FY 23-24 Q2.pdf | 8 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SA-CHAITANYA-FORM 2 ENGG CERT.pdf | 8 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: SA- CHAITANYA PROMOTER DISCLOSURE FY 23-24 Q2.pdf | 8 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: OMC - CA Certificate -Form 3 FY 23-24 -Q2.pdf | 8 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Compressed.pdf | 25 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf | 25 Jul 2023 |
| Details of encumbrances concerned to FinanceFile: Encum Letter OMC.pdf | 24 Jul 2023 |
| Details of encumbrances concerned to LegalFile: Encum Letter OMC.pdf | 24 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Q1 -OMC.pdf | 22 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Q1-OMC.pdf | 22 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Promoter Disclosure Q1 OMC.pdf | 22 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form-3 Q1-OMC.pdf | 22 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineers Certificate on Quality Assurance, Form 2A FY 21-22 OMC.pdf | 13 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A FY 22-23 OMC.pdf | 13 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate Q-4 OMC.pdf | 3 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate Q-4 OMC.pdf | 3 May 2023 |
| Disclosure of sold/ booked inventoryFile: Promoters Disclosure.pdf | 3 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Q-4 OMC.pdf | 3 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CHAITANYA ARCH CERTIFICATE FY 22-23 Q3.pdf | 21 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: CHAITANYA ENGG CER FY 22-23 Q3.pdf | 21 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: CHAITANYA PROMOTERS DISCLOSURE FY 22-23 Q3.pdf | 21 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Q3 OMC Sized.pdf | 21 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CA Certificate Form 5 FY 2021-22-OMC.pdf | 23 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Q2 OMC.pdf | 6 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Q2 OMC.pdf | 5 Nov 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Enggineer Certificate FY 22-23 Q2.pdf | 5 Nov 2022 |
| Disclosure of sold/ booked inventoryFile: Promoters Disclosure Q2 OMC.pdf | 5 Nov 2022 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CER DT 29-7-22.pdf | 24 Sep 2022 |
| Proforma of Allotment letterFile: AGR TO SALE - OMC DT 29-7-22 .pdf | 24 Sep 2022 |
| Building plan approvalFile: Plan 01.pdf | 2 Aug 2022 |
| Building plan approvalFile: Plan 02.pdf | 2 Aug 2022 |
| Building plan approvalFile: Plan 03.pdf | 2 Aug 2022 |
| Building plan approvalFile: Plan 04.pdf | 2 Aug 2022 |
| Building plan approvalFile: Plan 05.pdf | 2 Aug 2022 |
| Building plan approvalFile: Plan 06.pdf | 2 Aug 2022 |
| Building plan approvalFile: Plan 07.pdf | 2 Aug 2022 |
| Building plan approvalFile: Plan 08.pdf | 2 Aug 2022 |
| Building plan approvalFile: Plan 09.pdf | 2 Aug 2022 |
| Building plan approvalFile: Plan 10.pdf | 2 Aug 2022 |
| Building plan approvalFile: Plan 11.pdf | 2 Aug 2022 |
| Building plan approvalFile: Plan 11.pdf | 2 Aug 2022 |
| Building plan approvalFile: Plan 13.pdf | 2 Aug 2022 |
| Building plan approvalFile: Plan 14.pdf | 2 Aug 2022 |
| Building plan approvalFile: Plan 15.pdf | 2 Aug 2022 |
| Building plan approvalFile: Plan 16.pdf | 2 Aug 2022 |
| Building plan approvalFile: Plan 17.pdf | 2 Aug 2022 |
| Building plan approvalFile: Plan 18.pdf | 2 Aug 2022 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Sai Paradise | Plot No C S No 12-1 To 7 Bangalore Pune Highway Punavale Pune- 411033 | 368 | Completed | Dec 2021 | Late, Mar 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 219 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep OM MANGALAM CHAITANYA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near VILLAGE KIWALE13,700+ in Pune
Filed coordinates, straight-line distance. 234 registered projects within 2 km.
Godrej Park Greens
Godrej Skyline Developers Limited
FOREST GROVE AT GODREJ PARK GREENS
Godrej Skyline Developers Limited
Om Mangalam Samruddhi
NDG Homes LLP
PCMC EWS KIWALE
Pimpri Chinchwad Municipal Corporation
Godrej Nurture
Godrej Skyline Developers Limited
My Home Sanctuary Phase I
MAMURDI DEVELOPERS LLP
Builder: SHRI ASSOCIATES
SHRI ASSOCIATES has 5 registrations on MahaRERA, including OM MANGALAM CHAITANYA and OM MANGALAM YASH. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if OM MANGALAM CHAITANYA is delayed beyond 30 Sep 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of OM MANGALAM CHAITANYA?
The registered promoter entity is SHRI ASSOCIATES, an others as per the filing. Its GSTIN 27AAKAS6978E2ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in OM MANGALAM CHAITANYA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for OM MANGALAM CHAITANYA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at OM MANGALAM CHAITANYA?
The professionals named in the filing: Architect: SANKALP DESIGNER; Architect: G A BHILARE CONSULTANT PVT LTD; Architect: GREE MEP CONSULTANT; Engineer: VIJAY GAVADE; Chartered Accountant: V L JAIN AND CO; Chartered Accountant: V S A P AND COMPANY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in OM MANGALAM CHAITANYA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback