ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / OM JAI KAVISH ROYAL VILLAS

Registered No litigation declared Residential / Group Housing project

OM JAI KAVISH ROYAL VILLAS

By OM JAI KAVISH REALTORS

RG-MH-17821 · RERA P99000055676 · Last updated on MahaRERA portal: 21 Jun 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 4 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedno revision filed
28 of 286Construction stages doneacross 26 buildings; furthest along: Slabs of Super Structure, 50%
16 of 26Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 72 documents Report an error

OM JAI KAVISH ROYAL VILLAS is a Residential / Group Housing project by OM JAI KAVISH REALTORS in Palghar, Maharashtra, registered with MahaRERA as P99000055676 on 8 Apr 2024. Possession is promised by 31 Dec 2029. 10 of the 26 units on this registration are recorded sold or booked, and 28 of 286 construction stages are filed complete.

At a glance

Project

  • NameOM JAI KAVISH ROYAL VILLAS
  • TypeResidential / Group Housing
  • Location
    • SATPATI ROAD
    • ALIYALI
    • Palghar
    • 401404
  • Pincode401404
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000055676
  • ReraGenie IDRG-MH-17821

Builder

  • NameOM JAI KAVISH REALTORS
  • Entity typeOthers
  • GSTIN27ABAPY8176A1ZG
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Named personDHIRAJ JAGPATI YADAV
  • Other registrations4 more →
  • Completed1 of 5
  • Declared earlier projects1 →

Key dates

this monthRegisteredApr 2024PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on8 Apr 2024
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings26 building records
  • Documents filed72 files

Current status

38%10 of 26 units booked
25.9%Work done, per cost certificate

Figures as on 21 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUNGALOW NO 1 TYPE ANA11101
BUNGALOW NO 2 TYPE ANA11101
BUNGALOW NO 3 TYPE ANA11101
BUNGALOW NO 4 TYPE ANA11101
BUNGALOW NO 5 TYPE ANA11101
BUNGALOW NO 6 TYPE ANA11101
BUNGALOW NO 7 TYPE ANA11101
BUNGALOW NO 8 TYPE ANA11101
BUNGALOW NO 9 TYPE ANA11101
BUNGALOW NO 10 TYPE ANA11101
BUNGALOW NO 11 TYPE ANA11101
BUNGALOW NO 12 TYPE ANA11101
BUNGALOW NO 13 TYPE ANA11101
BUNGALOW NO 14 TYPE ANA11101
BUNGALOW NO 15 TYPE ANA11101
BUNGALOW NO 16 TYPE CNA11101
BUNGALOW NO 17 TYPE BNA11101
BUNGALOW NO 18 TYPE BNA11101
BUNGALOW NO 19 TYPE BNA11101
BUNGALOW NO 20 TYPE BNA11101
BUNGALOW NO 21 TYPE BNA11101
BUNGALOW NO 22 TYPE BNA11101
BUNGALOW NO 23 TYPE ANA11101
BUNGALOW NO 24 TYPE ANA11101
BUNGALOW NO 25 TYPE ANA11101
BUNGALOW NO 26 TYPE ANA11101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 21 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 26 buildings; the table lists the first 20.

28 of 286 construction stages are filed complete across 26 buildings. The stage furthest along is Slabs of Super Structure, at 50%.

BUNGALOW NO 1 TYPE A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 2 TYPE A32%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 3 TYPE A18%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 4 TYPE A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 5 TYPE A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 6 TYPE A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 7 TYPE A18%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 8 TYPE A32%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 9 TYPE A32%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 10 TYPE A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 11 TYPE A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 12 TYPE A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 13 TYPE A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 14 TYPE A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 15 TYPE A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 16 TYPE C0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 17 TYPE B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 18 TYPE B45%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 19 TYPE B45%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 20 TYPE B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 21 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes30%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed52

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots52
Open Space52
BuildingOpen SpaceTotal
BUNGALOW NO 1 TYPE A22
BUNGALOW NO 2 TYPE A22
BUNGALOW NO 3 TYPE A22
BUNGALOW NO 4 TYPE A22
BUNGALOW NO 5 TYPE A22
BUNGALOW NO 6 TYPE A22
BUNGALOW NO 7 TYPE A22
BUNGALOW NO 8 TYPE A22
BUNGALOW NO 9 TYPE A22
BUNGALOW NO 10 TYPE A22
BUNGALOW NO 11 TYPE A22
BUNGALOW NO 12 TYPE A22
BUNGALOW NO 13 TYPE A22
BUNGALOW NO 14 TYPE A22
BUNGALOW NO 15 TYPE A22
BUNGALOW NO 16 TYPE C22
BUNGALOW NO 17 TYPE B22
BUNGALOW NO 18 TYPE B22
BUNGALOW NO 19 TYPE B22
BUNGALOW NO 20 TYPE B22
BUNGALOW NO 21 TYPE B22
BUNGALOW NO 22 TYPE B22
BUNGALOW NO 23 TYPE A22
BUNGALOW NO 24 TYPE A22
BUNGALOW NO 25 TYPE A22
BUNGALOW NO 26 TYPE A22

Land and ownership10

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,500 sq m
Land owned byThe promoter, with other names on the file
Named landowners10
LandownerVillageDistrict
KASHINATH KESHAV MOREDhansarPalghar
GULAB TUKARAM MOREDhansarPalghar
SANTOSH SITARAM MOREDhansarPalghar
NIRMALA SANDESH PATILShirgaon Palghar
SUNANDA SITARAM MOREDhansarPalghar
ARTI ARUN MORESatpatiPalghar
BHARATI SETARAM MOREDhansarPalghar
BANDYA KESHAV MOREDhansarPalghar
SHALINI KAMLAKAR MOREShirgaon Palghar
SUNIL SITARAM MOREDhansarPalghar

Approvals and building plan

Sanctioning authorityPALGHAR MUNICIPAL COUNCIL
Permissible FSI3634.96
Proposed, not sanctioned3,635 sq m
Buildings approved26
Buildings sanctioned26

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGR FLOOR SATYAM COMMERCIAL COMPLEX MAHIM ROAD PALGHAR WEST PINCODE 401404
Estimated costRs 2.48 cr
Cost incurredRs 64.20 lakh
Work done25.89%
BuildingWingEstimatedIncurred
-NARs 90.00 lakhRs 20.00 lakh
BUNGALOW NO 1 TYPE ANARs 6.08 lakhRs 1.70 lakh
BUNGALOW NO 2 TYPE ANARs 6.08 lakhRs 1.70 lakh
BUNGALOW NO 3 TYPE ANARs 6.08 lakhRs 1.70 lakh
BUNGALOW NO 4 TYPE ANARs 6.08 lakhRs 1.70 lakh
BUNGALOW NO 5 TYPE ANARs 6.08 lakhRs 1.70 lakh
BUNGALOW NO 6 TYPE ANARs 6.08 lakhRs 1.70 lakh
BUNGALOW NO 7 TYPE ANARs 6.08 lakhRs 1.70 lakh
BUNGALOW NO 8 TYPE ANARs 6.08 lakhRs 1.70 lakh
BUNGALOW NO 9 TYPE ANARs 6.08 lakhRs 1.70 lakh
BUNGALOW NO 10 TYPE ANARs 6.08 lakhRs 1.70 lakh
BUNGALOW NO 11 TYPE ANARs 6.08 lakhRs 1.70 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSIDDHIVINAYAK ASSOCIATES
EngineerGR CONSULTANTS
Chartered AccountantABHISHEK A SINGH AND COMPANY
Chartered AccountantABHISHEK A SINGH & COMPANY
PartnerRole in project
OM JAI KAVISH REALTORS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Mar 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Feb 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Feb 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed72

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 OM JAY.pdf21 Jun 2026
Withdrawal Update Form 2File: FORM 2 OM JAY.pdf21 Jun 2026
Withdrawal Update Form 3File: form 3 march 026.pdf21 Jun 2026
Withdrawal Update Form 1File: Form 1 June 2025.pdf24 Jan 2026
Withdrawal Update Form 1File: Form 1 Sept 2025.pdf24 Jan 2026
Withdrawal Update Form 1File: Form 1 Dec 2025.pdf24 Jan 2026
Withdrawal Update Form 2File: Form 2 June 2025.pdf24 Jan 2026
Withdrawal Update Form 2File: Form 2 Sept 2025.pdf24 Jan 2026
Withdrawal Update Form 2File: Form 2 Dec 2025.pdf24 Jan 2026
Withdrawal Update Form 3File: Form 3 June 2025.pdf24 Jan 2026
Withdrawal Update Form 3File: FORM 3 Sept 2025.pdf24 Jan 2026
Withdrawal Update Form 3File: Form 3 Dec 2025.pdf24 Jan 2026
Form 1File: Form 1 OM Highness Homes 30 Sept 2024.pdf16 Aug 2025
Form 2File: Form 2 Om Highness Homes 30 sept 2024.pdf16 Aug 2025
Form 3File: Form 3 Om Highness Homes 30 sept 2024.pdf16 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Booked and Sold Inventory Highness Homes 30sept 2024.pdf16 Aug 2025
Form 1File: Form-1 3103025 om jai kavish.pdf12 Jun 2025
Form 2File: Form-2 31032025 -omm jai kavish.pdf12 Jun 2025
Form 3File: Form-3 31032025-0m jai kavish.pdf12 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold unsold 31032025om jai kavish.pdf12 Jun 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Om jai kavish royal villas.pdf7 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 OM JAI KAVISH ROYAL VILLAS 30 Sept 2024.pdf12 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 OM JAI KAVISH ROYAL VILLAS 30 Sept 2024.pdf12 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 OM Royal Villas 30 sept 2024.pdf12 Nov 2024
Other - TechnicalFile: Declaration cum undertaking for no duplicate registration(Annexure A).pdf1 Apr 2024
Other - TechnicalFile: Explanation (2).pdf1 Apr 2024
Other - TechnicalFile: 2 Commencement Certificates _ NA Order for plotted development (1).pdf31 Mar 2024
Copy of the legal title reportFile: ilovepdf_merged (17).pdf15 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: fORM-3 OMJAI KAVISH VILLAS LATEST.pdf11 Mar 2024
Details of encumbrances concerned to FinanceFile: Declaration Finance encumbrances.pdf6 Mar 2024
Details of encumbrances concerned to LegalFile: Declaration Finance encumbrances.pdf6 Mar 2024
CERSAI detailsFile: Declaration Cersai - Copy.pdf6 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: RERA Bank Ac declaration - Copy.pdf6 Mar 2024
Other - FinanceFile: Explanation for proprietorship firm - Copy.pdf6 Mar 2024
Other - FinanceFile: gst certif.pdf6 Mar 2024
Layout approvalFile: 1 Copy of Layout Approval (in case of layout) (10).pdf26 Feb 2024
Building plan approvalFile: 1 Building Plan Approval _ NA Order for plotted development (7).pdf26 Feb 2024
Building plan approvalFile: 2 Building Plan Approval _ NA Order for plotted development (2).pdf26 Feb 2024
Building plan approvalFile: 3 Building Plan Approval _ NA Order for plotted development (2).pdf26 Feb 2024
Building plan approvalFile: 4 Building Plan Approval _ NA Order for plotted development (1).pdf26 Feb 2024
Building plan approvalFile: 5 Building Plan Approval _ NA Order for plotted development.pdf26 Feb 2024
Building plan approvalFile: 6 Building Plan Approval _ NA Order for plotted development.pdf26 Feb 2024
Building plan approvalFile: 7 Building Plan Approval _ NA Order for plotted development.pdf26 Feb 2024
Building plan approvalFile: 8 Building Plan Approval _ NA Order for plotted development.pdf26 Feb 2024
Building plan approvalFile: 9 Building Plan Approval _ NA Order for plotted development.pdf26 Feb 2024
Building plan approvalFile: 10 Building Plan Approval _ NA Order for plotted development.pdf26 Feb 2024
PAN CardFile: 1 PAN Card (6).pdf26 Feb 2024
PAN CardFile: 2 PAN Card (3).pdf26 Feb 2024
Details of encumbrances concerned to FinanceFile: 2 b Details of encumbrances concerned to Legal.pdf26 Feb 2024
Details of encumbrances concerned to LegalFile: 2 b Details of encumbrances concerned to Legal.pdf26 Feb 2024
Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout) (10).pdf26 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: 1 Building Plan Approval _ NA Order for plotted development (7).pdf26 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: 2 Building Plan Approval _ NA Order for plotted development (2).pdf26 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: 3 Building Plan Approval _ NA Order for plotted development (2).pdf26 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: 4 Building Plan Approval _ NA Order for plotted development (1).pdf26 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: 5 Building Plan Approval _ NA Order for plotted development.pdf26 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: 6 Building Plan Approval _ NA Order for plotted development.pdf26 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: 7 Building Plan Approval _ NA Order for plotted development.pdf26 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: 8 Building Plan Approval _ NA Order for plotted development.pdf26 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: 9 Building Plan Approval _ NA Order for plotted development.pdf26 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: 10 Building Plan Approval _ NA Order for plotted development.pdf26 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: 1 Commencement Certificates _ NA Order for plotted development (6).pdf26 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: 2 Commencement Certificates _ NA Order for plotted development.pdf26 Feb 2024
Declaration about Commencement CertificateFile: 1 Declaration about Commencement Certificate (5).pdf26 Feb 2024
Declaration in FORM BFile: 1 Declaration in FORM B (2).pdf26 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (6).pdf26 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineer’s Certificate on Cost Incurred on Project (Form 2) (15).pdf26 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations (3).pdf26 Feb 2024
Proforma of Agreement for saleFile: 1 Proforma of Agreement for sale (18).pdf26 Feb 2024
Proforma of Allotment letterFile: 1 Proforma of Allotment letter (5).pdf26 Feb 2024
Deviation Report with respect to Allotment letterFile: 1 Deviation Report with respect to Allotment letter.pdf26 Feb 2024
Deviation Report with respect to model copy of AgreementFile: 1 Deviation Report with respect to model copy of Agreement (1).pdf26 Feb 2024

How this compares with Palghar

38%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep OM JAI KAVISH ROYAL VILLAS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ALIYALI3,200+ in Palghar

2 kmOM JAI KAVISH ROYAL VILLCompleted 2Lapsed / revoked 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: OM JAI KAVISH REALTORS

OM JAI KAVISH REALTORS has 5 registrations on MahaRERA, including OM KAVISH EXCELLENCY and HIGHNESS HOMES. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if OM JAI KAVISH ROYAL VILLAS is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of OM JAI KAVISH ROYAL VILLAS?

The registered promoter entity is OM JAI KAVISH REALTORS, an others as per the filing. Its GSTIN 27ABAPY8176A1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in OM JAI KAVISH ROYAL VILLAS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for OM JAI KAVISH ROYAL VILLAS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at OM JAI KAVISH ROYAL VILLAS?

The professionals named in the filing: Architect: SIDDHIVINAYAK ASSOCIATES; Engineer: GR CONSULTANTS; Chartered Accountant: ABHISHEK A SINGH AND COMPANY; Chartered Accountant: ABHISHEK A SINGH & COMPANY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in OM JAI KAVISH ROYAL VILLAS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About OM JAI KAVISH ROYAL VILLAS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save OM JAI KAVISH ROYAL VILLAS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.