Home / Browse projects / Pune, Maharashtra / OJASVI GOLD

Registration lapsed No litigation declared Others project

OJASVI GOLD

By KRISHNA RENUKA REALTY

RG-MH-68217 · RERA P52100049782 · Last updated on MahaRERA portal: 1 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
5 of 11Construction stages donefurthest along: Internal walls, 90%
33 of 63Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 74 documents Report an error

OJASVI GOLD is a Others project by KRISHNA RENUKA REALTY in Pune, Maharashtra, registered with MahaRERA as P52100049782 on 24 Feb 2023. Possession was promised by 30 Jun 2025 and is now 16 months past that date. 30 of the 63 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameOJASVI GOLD
  • TypeOthers
  • Location
    • NEAR CITY PRIDE SCHOOL
    • RAVET
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • RERA no.P52100049782
  • ReraGenie IDRG-MH-68217

Builder

  • NameKRISHNA RENUKA REALTY
  • Entity typePartnership
  • PartnersRAHUL MULJI PATEL, HARESH MULJI PATEL, AJAY BABU MEHETRE
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

16 months past promisethis monthRegisteredFeb 2023PromisedJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on24 Feb 2023
  • Promised completion30 Jun 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed74 files

Current status

48%30 of 63 units booked

Figures as on 1 Feb 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
OJASVI GOLDNA9963063

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

OJASVI GOLD: 66% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 1 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed189

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots189
Closed/Covered36
Open Space153

Land and ownership13

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,056 sq m
Land owned byThe promoter, with other names on the file
Named landowners13
LandownerVillageDistrict
YUVRAJ VIHWANATH RAJEPimpri Chinchawad (M Corp.)Pune
HANUMAN VISHWANTH RAJEPimpri Chinchawad (M Corp.)Pune
JYOTI HANUMAN RAJEPimpri Chinchawad (M Corp.)Pune
VIJAY SHIVRAM SAWANTPune (M Corp.)Pune
NITIN GOVIND DALVIPimpri Chinchawad (M Corp.)Pune
GAUTAM VAMAN KAMBLEPimpri Chinchawad (M Corp.)Pune
KAMAL GAUTAM KAMBLEPimpri Chinchawad (M Corp.)Pune
ADITYA GAUTAM KAMBLEPimpri Chinchawad (M Corp.)Pune
GAURAV GAUTAM KAMBLEPimpri Chinchawad (M Corp.)Pune
SUNITA ARUN DHASPimpri Chinchawad (M Corp.)Pune
ARUN SHANKAR DHASPimpri Chinchawad (M Corp.)Pune
SACHIN ARUN DHASPimpri Chinchawad (M Corp.)Pune
JYOTI ARUN DHASPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI5055.7
Proposed, not sanctioned2,314 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch1st floor the metropoiten commercial complex pimpri chinchwadpune 411033

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKALPRACHANAARCHITECH
EngineerRAJESH SHANKARRAO PANHALKAR
Chartered AccountantVAISHALI ROHIDAS GOLE
PartnerRole in project
KRISHNA RENUKA REALTY-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed74

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KRR-OG-Arch Certi-Q3-2425.pdf1 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KRR-OG-CA Certi-Form 3-Q3-2425_compressed.pdf1 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KRR-OG-Engr Certi Form-2-Q3-2425.pdf1 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KRR-OG-Q2-2425 Architect Certi.pdf20 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KRR-OG-Engr Certificate -Q1-2425.pdf20 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engr Certi-Form 2- Q2-2425.pdf20 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE FROM 3compressed.pdf20 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE Q2_compressed.pdf20 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KRR-OG-Q2-2425 Architect Certi.pdf20 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE FROM 3compressed.pdf20 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE Q2_compressed.pdf20 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KRR-OG-Engr Certificate -Q1-2425.pdf20 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engr Certi-Form 2- Q2-2425.pdf20 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KRR-OG-Q1-2425 Architect Certi.pdf19 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: KRR-OG-Engr Certificate -Q1-2425.pdf19 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KRR-OG-Q1-2425-CA Certificate.pdf19 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KRR-OG-Q1-2425 Architect Certi.pdf19 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KRR-OG-Q1-2425-CA Certificate.pdf19 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: KRR-OG-Engr Certificate -Q1-2425.pdf19 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Q4 KRR- BANK AMENDMEND.pdf13 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KRR-OG-Q4-2324-Architect Certificate.pdf4 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KRR-OG-Q4-2324-Engineer_Certificate.pdf4 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: KRR-OG-Q4-2324-Quality_Assurance-Form2A.pdf4 May 2024
Disclosure of sold/ booked inventoryFile: KRR-OG-Q4-2324-Sold_Unsold_Inventory.pdf4 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Q4 KRR_compressed.pdf4 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE_page-0001 (2).pdf14 Mar 2024
Layout approvalFile: L PLAN.PDF12 Mar 2024
Building plan approvalFile: PLAN 1.PDF12 Mar 2024
Building plan approvalFile: PLAN 2.PDF12 Mar 2024
Building plan approvalFile: PLAN 3.PDF12 Mar 2024
Copy of Layout Approval (in case of layout)File: L PLAN.PDF12 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: PLAN 1.PDF12 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: PLAN 2.PDF12 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: PLAN 3.PDF12 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf12 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KRR-OG-Arch Certificate Q3-2324.pdf12 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KRR-OG-Engr Certi Q3-2324.pdf12 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: KRR-OG-Engineer Certificate_Q2_Bank update_Revised.pdf1 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: KRR FORM 5 FY 22-23.pdf1 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KRR-OG-Q2-2324 Arch Certification 04-10-2023.pdf10 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KRR FORM 3_compressed.pdf10 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KRR-OG-Q1-2324 RERA Arch Certificate_0001.pdf11 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KalparachanaAssociates_RERA Certificate 03Apr2023.pdf9 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KRR ENGINEERS CERTIFICATE 30-09-2023_compressed.pdf9 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KRR ENGINEERS CERTIFICATE 04-10-2023_compressed.pdf9 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE 30-09-2023 SCAN COPY_compressed.pdf9 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE 04-10-2023 SCAN COPY_compressed.pdf9 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSER LETTER.pdf6 Feb 2023
Other - LegalFile: letter.pdf6 Feb 2023
Other - LegalFile: Plan 0001.PDF6 Feb 2023
Other - LegalFile: Bank decleration.pdf6 Feb 2023
CERSAI detailsFile: CERSAI FINAL 010202023.pdf1 Feb 2023
Proforma of Agreement for saleFile: RERA Draft (2).pdf28 Jan 2023
Deviation Report with respect to model copy of AgreementFile: NO DEVATION.pdf28 Jan 2023
Details of encumbrances concerned to FinanceFile: 1 a Details of encumbrances concerned to Finance_page-0001.pdf18 Jan 2023
Details of encumbrances concerned to LegalFile: 1 a Details of encumbrances concerned to Finance_page-0001.pdf18 Jan 2023
PAN CardFile: FIRM Pan card.pdf16 Jan 2023
Copy of the legal title reportFile: SEARCH REPORT.pdf16 Jan 2023
Layout approvalFile: Plan 0001.PDF7 Jan 2023
Layout approvalFile: Plan 0002.PDF7 Jan 2023
Layout approvalFile: Plan 0003.PDF7 Jan 2023
Building plan approvalFile: NA ORDER.pdf7 Jan 2023
Copy of Layout Approval (in case of layout)File: Plan 0001.PDF7 Jan 2023
Copy of Layout Approval (in case of layout)File: Plan 0002.PDF7 Jan 2023
Copy of Layout Approval (in case of layout)File: Plan 0003.PDF7 Jan 2023
Building Plan Approval / NA Order for plotted developmentFile: NA ORDER.pdf7 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: Commensment Certifiacte.pdf7 Jan 2023
Declaration about Commencement CertificateFile: DECLARATION COMMENCEMENT.pdf7 Jan 2023
Declaration in FORM BFile: FORM B KRISHNA RENUKA REALITY.pdf7 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHTICH RERA_FORM_1.pdf7 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certfiacte_compressed.pdf7 Jan 2023
Proforma of Allotment letterFile: Allotment lettre_merged.pdf7 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank decleration.pdf7 Jan 2023
Deviation Report with respect to Allotment letterFile: Devation Letter ALLOTMENT.pdf7 Jan 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
OJASVIPLOT NO 94116CompletedJun 2022Apr 2022

How this compares with Pune

48%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep OJASVI GOLD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near RAVET13,700+ in Pune

Builder: KRISHNA RENUKA REALTY

KRISHNA RENUKA REALTY has 2 registrations on MahaRERA, including OJASVI and OJASVI GOLD. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that OJASVI GOLD shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if OJASVI GOLD is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of OJASVI GOLD?

The registered promoter entity is KRISHNA RENUKA REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in OJASVI GOLD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for OJASVI GOLD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at OJASVI GOLD?

The professionals named in the filing: Architect: KALPRACHANAARCHITECH; Engineer: RAJESH SHANKARRAO PANHALKAR; Chartered Accountant: VAISHALI ROHIDAS GOLE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in OJASVI GOLD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About OJASVI GOLD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save OJASVI GOLD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.