ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Odela

Registration lapsed No litigation declared Others project

Odela

By Lohia Jain Housing Company LLP

RG-MH-26411 · RERA P52100014706 · Last updated on MahaRERA portal: 23 Mar 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 21 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jan 2025Possession promised21 months past this date
21 of 44Construction stages doneacross 4 buildings; furthest along: Staircases, 92%
0Complaints at MahaRERAon this registration
Jump to the 101 documents Report an error

Odela is a Others project by Lohia Jain Housing Company LLP in Pune, Maharashtra, registered with MahaRERA as P52100014706 on 26 Dec 2017. Possession was promised by 30 Jan 2025 and is now 21 months past that date.

At a glance

Project

  • NameOdela
  • TypeOthers
  • Location
    • DP Road Adjacent Maratha Mandir
    • NEAR LMD CHOWK
    • Bavdhan Kh.
    • Haveli
    • Pune
    • 411021
  • Pincode411021
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100014706
  • ReraGenie IDRG-MH-26411

Builder

  • NameLohia Jain Housing Company LLP
  • Entity typePartnership
  • PartnersPurushottam Mukunddas Lohia, Ashok Kantilal Jain, Kishor Shantilal Jain, Pradeep Shantilal Jain, Aditya Purushottam Lohia, Kailas Kantilal Jain, Madan Shantilal Jain, H B Investment Co Pvt Ltd NA
  • Declared earlier projects2 →

Key dates

21 months past promisethis monthRegisteredDec 2017PromisedJan 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on26 Dec 2017
  • Promised completion30 Jan 2025
  • Revised completionNone
  • Buildings4 building records
  • Documents filed101 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ODELA A WINGNA200000
ODELA B WINGNA200000
ODELA C WINGNA200000
Odela RetailNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 23 Mar 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

21 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 92%.

ODELA A WING57%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises68%
Sanitary Fittings within the flats / premises1%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks91%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.67%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.2%
ODELA B WING58%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises77%
Sanitary Fittings within the flats / premises2%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks92%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.68%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.1%
ODELA C WING50%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises37%
Sanitary Fittings within the flats / premises1%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks87%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.19%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.1%
Odela Retail82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities18

As on 23 Mar 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes37%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%
Retaining WallYes91%
Remaining Area of Lower Upper PodiumYes85%
Compound wallYes29%

Parking filed518

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots518
Closed/Covered518
BuildingClosed/CoveredTotal
ODELA A WING244244
ODELA B WING121121
ODELA C WING125125
Odela Retail2828

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area15,663 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI38659.47
Proposed, not sanctioned31,536 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOffice No 101 102 First Floor Bahiratwadi Behind ICC Trade Tower Off Senapati Bapat Road Pune 411016

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSUBHASH SHAH & ASSOCIATES
EngineerSHREE KAMAL DEVELOPERS
Chartered AccountantCA YOGGETA R SHENVI
Chartered AccountantCA VARDHAMAN JAIN
PartnerRole in project
Lohia Jain Housing Company LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Dec 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Apr 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Mar 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 23 Mar 2023

Documents filed101

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 101 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: LJBH OFFICES.PDF23 Mar 2023
Building plan approvalFile: 3.pdf13 Mar 2023
Building plan approvalFile: 4.pdf13 Mar 2023
Building plan approvalFile: 5.pdf13 Mar 2023
Building plan approvalFile: 6.pdf13 Mar 2023
Building plan approvalFile: 7.pdf13 Mar 2023
Building Plan Approval (IOD)File: 3.pdf13 Mar 2023
Building Plan Approval (IOD)File: 4.pdf13 Mar 2023
Building Plan Approval (IOD)File: 5.pdf13 Mar 2023
Building Plan Approval (IOD)File: 6.pdf13 Mar 2023
Building Plan Approval (IOD)File: 7.pdf13 Mar 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: ODELA.PDF28 May 2022
Layout approvalFile: 3515.pdf21 Apr 2022
Layout approvalFile: 3515.pdf21 Apr 2022
Copy of Layout Approval (in case of layout)File: 3515.pdf21 Apr 2022
Copy of Layout Approval (in case of layout)File: 3515.pdf21 Apr 2022
Commencement Certificates / NA Order for plotted developmentFile: 3515.pdf21 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1.PDF21 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1.PDF21 Apr 2022
CERSAI detailsFile: CERSAISearchReport.pdf21 Apr 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COMPLETION.PDF25 Mar 2022
Declaration about Commencement CertificateFile: DECLARATIONFORMD.PDF6 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITYASSURANCE.PDF6 Dec 2021
Disclosure of sold/ booked inventoryFile: INVENTORY.pdf6 Dec 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2.PDF22 Oct 2021
Certificates of CA (Form 3)File: form3.PDF22 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM5.PDF22 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM5.PDF22 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM2A.PDF24 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1.PDF26 Mar 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2.PDF26 Mar 2021
Form 2AFile: FROM2A.PDF26 Mar 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM5.PDF26 Mar 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1.PDF2 Nov 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1.PDF2 Nov 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1.PDF2 Nov 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1.PDF2 Nov 2020
Certificates of CA (Form 3)File: FORM3.PDF2 Nov 2020
Certificates of CA (Form 3)File: form3.PDF2 Nov 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 ARCHITECT CERTIFICATE - JULY-SEP-2019.PDF29 Jan 2020
Certificates of CA (Form 5)File: FORM5.PDF1 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1 29-7-2019.PDF30 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITEC FORM 1.PDF25 Apr 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - ENGINEERS CERTICATE.PDF25 Apr 2019
Layout approvalFile: 1.pdf24 Apr 2019
Layout approvalFile: 2.pdf24 Apr 2019
Copy of Layout Approval (in case of layout)File: 1.pdf24 Apr 2019
Copy of Layout Approval (in case of layout)File: 2.pdf24 Apr 2019
Form 2AFile: FORM 2A- QUALITY ASSURANCE ENGINEER.PDF24 Apr 2019
Layout approvalFile: 1.pdf22 Apr 2019
Building plan approvalFile: 1.pdf22 Apr 2019
Building plan approvalFile: 2.pdf22 Apr 2019
Building plan approvalFile: 3.pdf22 Apr 2019
Building plan approvalFile: 4.pdf22 Apr 2019
Building plan approvalFile: 5.pdf22 Apr 2019
Building plan approvalFile: 6.pdf22 Apr 2019
Building plan approvalFile: 7.pdf22 Apr 2019
PAN CardFile: LJHC LLP PANCARD.PDF22 Apr 2019
Copy of Layout Approval (in case of layout)File: 1.pdf22 Apr 2019
Building Plan Approval (IOD)File: 1.pdf22 Apr 2019
Building Plan Approval (IOD)File: 2.pdf22 Apr 2019
Building Plan Approval (IOD)File: 3.pdf22 Apr 2019
Building Plan Approval (IOD)File: 4.pdf22 Apr 2019
Building Plan Approval (IOD)File: 5.pdf22 Apr 2019
Building Plan Approval (IOD)File: 6.pdf22 Apr 2019
Building Plan Approval (IOD)File: 7.pdf22 Apr 2019
Commencement Certificates / NA Order for plotted developmentFile: COMMECEMENT CERTIFICATE.PDF22 Apr 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE FORM 1 - 1-11-2018.PDF22 Apr 2019
OtherFile: Certification of Registration of Conversion LJHC to LLP.PDF22 Apr 2019
Form 2AFile: ENGINEER'S CERTIFICATE FOR QUALITY ASSURANCE.PDF26 Dec 2018
Certificates of CA (Form 5)File: Odela- Form 5 Annual -FY 17-18.PDF29 Sep 2018
OtherFile: ODELA- PLINTH CERTIFICATE- A WING PART A, B WING FULL.PDF6 Sep 2018
Proforma of Allotment letterFile: Odela Master Rera Flat Agreement revised dsp 16-12-2017.pdf18 Dec 2017
Copy of the legal title reportFile: Odela Title.PDF13 Dec 2017
Details of encumbrancesFile: Non Encumbrance Certificate.PDF13 Dec 2017
Building plan approvalFile: CC 3735 Sheet 1.pdf11 Dec 2017
Building plan approvalFile: CC 3735 Sheet 2.pdf11 Dec 2017
Building plan approvalFile: CC 3735 Sheet 3.pdf11 Dec 2017
Building plan approvalFile: CC 3735 Sheet 4.pdf11 Dec 2017
Building plan approvalFile: CC 3735 Sheet 5.pdf11 Dec 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
ValloniaS No 52 Hissa no 52 1B 1C 2P 3 4A and S No 53 Hissa No 1 2 4A 6P 9B 10 11 12 Plot No 3 of Village Bavdhan kh Pune Talula Mulshi Dist Pune 411021210CompletedJun 2015Late, Jan 2016
Riddhi SiddhiS No 54 Hissa No 1A-2 1B-9 S No 22 Hissa No 1 to 4-1 and 1 to 4-2 Village Bavdhan Kh Taluka Mulshi Dist Pune 41102197CompletedAug 2014Late, Mar 2015

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Odela on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR LMD CHOWK13,700+ in Pune

2 kmOdelaCompleted 73Lapsed / revoked 45Other 63Dot size: filed unitsN

Filed coordinates, straight-line distance. 181 registered projects within 2 km.

Builder: Lohia Jain Housing Company LLP

Lohia Jain Housing Company LLP has 1 registration on MahaRERA, including Odela. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Odela shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Odela is delayed beyond 30 Jan 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Odela?

The registered promoter entity is Lohia Jain Housing Company LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Odela?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Odela?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Odela?

The professionals named in the filing: Architect: SUBHASH SHAH & ASSOCIATES; Engineer: SHREE KAMAL DEVELOPERS; Chartered Accountant: CA YOGGETA R SHENVI; Chartered Accountant: CA VARDHAMAN JAIN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Odela?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Odela. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Odela to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.