ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Nobles Heights Building A1 AND A2-Phase 1

Registered No litigation declared Residential / Group Housing project

Nobles Heights Building A1 AND A2-Phase 1

By Golden palm infrastructure

RG-MH-20704 · RERA P52100010046 · Last updated on MahaRERA portal: 3 May 2025

Source: official MahaRERA filing

Red flags

  • 6 complaints at MahaRERA
  • Completion date moved by 71 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedmoved 71 months from the original
6 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 90%
6Complaints at MahaRERAon this registration
Jump to the 133 documents Report an error

Nobles Heights Building A1 AND A2-Phase 1 is a Residential / Group Housing project by Golden palm infrastructure in Pune, Maharashtra, registered with MahaRERA as P52100010046 on 23 Aug 2017. Possession is promised by 31 Dec 2029. The completion date has moved by 71 months from the original filing. 6 complaints are on record with the regulator.

At a glance

Project

  • NameNobles Heights Building A1 AND A2-Phase 1
  • TypeResidential / Group Housing
  • Location
    • HADAPSAR TO KATRAJ ROAD
    • PISOLI
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411048
  • Pincode411048
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100010046
  • ReraGenie IDRG-MH-20704

Builder

  • NameGolden palm infrastructure
  • Entity typePartnership
  • PartnersAbdultaiyeb Kuresh Bahrainwala, Huzefa Kuresh Bahrainwala, Mustafa Kuresh Bahrainwala
  • Other registrations2 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2017First promiseJan 2024Revised toDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Aug 2017
  • Promised completion31 Dec 2029
  • Revised completionRevised to 31 Dec 2029 (originally 4 Jan 2024)
  • Buildings2 building records
  • Documents filed133 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1NA120000
A2NA120000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 3 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 90%.

A147%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A228%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor10%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities16

As on 3 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes20%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes5%
Covered ParkingYes0%

Parking filed158

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots158
Open Space158
BuildingOpen SpaceTotal
A17979
A27979

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,000 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Dattatreya Arjun DurePune (M Corp.)Pune
BHERU ARJUN DUREPune (M Corp.)Pune

Approvals and building plan

Permissible FSI6575.0
Proposed, not sanctioned6,575 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKP HOUSING SOC,GEN-THIMAYA ROAD, EAST STREET, CAMP, PUNE 411001

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJitendra Thackkar
EngineerVirendra Chavan
Chartered AccountantASBK & Associates
PartnerRole in project
Golden palm infrastructure-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024151Jan 2024 → Jan 2025

Reason as filed by the promoterInternal finishing work of building is in process along with common area and facilities.

EXT52100028398Jan 2024 → Dec 2029

Reason as filed by the promoterWe are writing to request an extension for the completion timeline of our project, which includes Buildings A1 and A2, registered under RERA in 2017. The COVID-19 pandemic severely impacted the project, causing several disruptions: • Customer Payment Deferrals: Many buyers in Building A1 deferred their payments due to financial uncertainty, which affected our cash flow and resulted in a shortage of working capital. • Construction Slowdown: Lockdowns and restrictions from 2020 to 2021 caused labour shortages, supply chain disruptions, and site closures, forcing a temporary halt in construction.

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC005000000471366Sanjeev Ramprasad TiwariGolden Palm Infrastructure Through its Partner Abdultaiyeb Kuresh Bahrainwala31/07/2024
CC12501563Aditya Sadashiv DomaneGolden palm infrastructure12/05/2025
CC12501679Paramjeet Singh AroraGolden palm infrastructure24/05/2025
CC12501681Paramjeet Singh AroraGolden palm infrastructure24/05/2025
CC12501818Ruchi Vyas BansalGolden palm infrastructure03/06/2025
CC12501935Christopher Valerian GnanamalaiGolden palm infrastructure12/06/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Apr 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed133

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 133 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: 3 Declaration in FORM B 2025_compressed.pdf3 May 2025
Other - TechnicalFile: Self declaration letter.pdf3 May 2025
Declaration in FORM BFile: Form B.pdf9 Jul 2024
PAN CardFile: PAN Golden Palm Infra.pdf6 Jul 2024
Declaration about Commencement CertificateFile: Declaration CC.pdf6 Jul 2024
Declaration about Commencement CertificateFile: Plinth Certificate.pdf6 Jul 2024
Certificates of CA (Form 3)File: 01 CAC QPR PR-30-06-2017.pdf6 Jul 2024
Certificates of CA (Form 3)File: 02 CAC QPR PR-30-09-2017.pdf6 Jul 2024
Certificates of CA (Form 3)File: 03 CAC QPR PR-31-12-2017.pdf6 Jul 2024
Certificates of CA (Form 3)File: 04 CAC QPR PR-31-03-2018.pdf6 Jul 2024
Certificates of CA (Form 3)File: 05 CAC QPR PR-30-06-2018.pdf6 Jul 2024
Certificates of CA (Form 3)File: 06 CAC QPR PR-30-09-2018.pdf6 Jul 2024
Certificates of CA (Form 3)File: 07 CAC QPR PR-31-12-2018.pdf6 Jul 2024
Certificates of CA (Form 3)File: 08 CAC QPR PR-31-03-2019.pdf6 Jul 2024
Certificates of CA (Form 3)File: 09 CAC QPR PR-30-06-2019.pdf6 Jul 2024
Certificates of CA (Form 3)File: 10 CAC QPR PR-30-09-2019.pdf6 Jul 2024
Certificates of CA (Form 3)File: 11 CAC QPR PR-31-12-2019.pdf6 Jul 2024
Certificates of CA (Form 3)File: 12 CAC QPR PR-31-03-2020.pdf6 Jul 2024
Certificates of CA (Form 3)File: 13 CAC QPR PR-30-06-2020.pdf6 Jul 2024
Certificates of CA (Form 3)File: 14 CAC QPR PR-30-09-2020.pdf6 Jul 2024
Certificates of CA (Form 3)File: 15 CAC QPR PR-31-12-2020.pdf6 Jul 2024
Certificates of CA (Form 3)File: 16 CAC QPR PR-31-03-2021.pdf6 Jul 2024
Certificates of CA (Form 3)File: 17 CAC QPR PR-30-06-2021.pdf6 Jul 2024
Certificates of CA (Form 3)File: 18 CAC QPR PR-30-09-2021.pdf6 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM-5 CAC-2017-18.pdf6 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM-5 CAC-2018-19.pdf6 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM-5 CAC-2019-20.pdf6 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM-5 CAC-2020-21.pdf6 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM-5 CAC-2021-22.pdf6 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5 CAC-2022-23.pdf6 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 01 Engi Cert 30-06-2017.pdf5 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 02 Engi Cert 30-09-2017.pdf5 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 03 Engi Cert 31-12-2017.pdf5 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 04 Engi Cert 31-03-2018.pdf5 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 05 Engi Cert 30-06-2018.pdf5 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 06 Engi Cert 30-09-2018.pdf5 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 07 Engi Cert 31-12-2018.pdf5 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 08 Engi Cert 31-03-2019.pdf5 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 09 Engi Cert 30-06-2019.pdf5 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 10 Engi Cert 30-09-2019.pdf5 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 11 Engi Cert 31-12-2019.pdf5 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 12 Engi Cert 31-03-2020.pdf5 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 13 Engi Cert 30-06-2020.pdf5 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 14 Engi Cert 30-09-2020.pdf5 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 15 Engi Cert 31-12-2020.pdf5 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 16 Engi Cert 31-03-2021.pdf5 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 17 Engi Cert 30-06-2021.pdf5 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 18 Engi Cert 30-09-2021.pdf5 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 01 ARC_31-12-2021.pdf4 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 02 ARC_31-03-2022.pdf4 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 03 ARC_30-06-2022.pdf4 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 04 ARC_30-09-2022.pdf4 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 05 ARC_31-12-2022.pdf4 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 06 ARC_31-03-2023.pdf4 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 07 ARC_30-06-2023.pdf4 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 08 ARC_30-09-2023.pdf4 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 09 ARC_31-12-2023.pdf4 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 10 ARC_31-03-2024.pdf4 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QAC-31st March 2018.pdf4 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 01 Form 2A QAC -31st March 2019.pdf3 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 02 Form 2A QAC - 31st March 2020.pdf3 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 03 Form 2A QAC-31st March 2021.pdf3 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 04 Form 2A QSC-31st March 2022.pdf3 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 05 Form 2A QAC-31st March 2023.pdf3 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 06 Form 2A QAC-31st March 2024.pdf3 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5- FY 2023-24.pdf3 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 RERA Audit CA AR 2023-24_Signed.pdf3 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 00 Dec 21.pdf27 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 01 Mar 22.pdf27 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 02 June 22.pdf27 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 03 Sept 22.pdf27 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 04 Dec 22.pdf27 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 05 Mar 23.pdf27 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 06 June 23.pdf27 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 07 Sept 23.pdf27 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 08 Dec 23.pdf27 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 09 Mar 24.pdf27 Jun 2024
Disclosure of sold/ booked inventoryFile: 01 June 17.pdf27 Jun 2024
Disclosure of sold/ booked inventoryFile: 02 Sept 17.pdf27 Jun 2024
Disclosure of sold/ booked inventoryFile: 03 Dec 17.pdf27 Jun 2024

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 not delivered by the promised date
ProjectLocationRegisteredStatusPromisedDelivered
THE HERITAGEP52100024130NIBM, PuneJan 2020OngoingJul 2023Registered original: Dec 2022Not delivered
ONYX BIZMARK 52P52100020510KONDHWA BK, PuneApr 2019OngoingMar 2023Not delivered

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 71 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Nobles Heights Building A1 AND A2-Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PISOLI13,700+ in Pune

2 kmNobles Heights Building Completed 86Lapsed / revoked 35Other 57Dot size: filed unitsN

Filed coordinates, straight-line distance. 178 registered projects within 2 km.

Builder: Golden palm infrastructure

Golden palm infrastructure has 3 registrations on MahaRERA, including Nobles Heights Building A1 AND A2-Phase 1 and AVAUNCE BUILDING B AND C PHASE 2. Its filings disclose 2 earlier MahaRERA projects, none completed yet. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Nobles Heights Building A1 AND A2-Phase 1 is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Nobles Heights Building A1 AND A2-Phase 1?

The registered promoter entity is Golden palm infrastructure, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Nobles Heights Building A1 AND A2-Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Nobles Heights Building A1 AND A2-Phase 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Nobles Heights Building A1 AND A2-Phase 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Nobles Heights Building A1 AND A2-Phase 1?

The professionals named in the filing: Architect: Jitendra Thackkar; Engineer: Virendra Chavan; Chartered Accountant: ASBK & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Nobles Heights Building A1 AND A2-Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Nobles Heights Building A1 AND A2-Phase 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Nobles Heights Building A1 AND A2-Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.