Home / Browse projects / Pune, Maharashtra / NISHIGANDH 1

Registered No litigation declared Residential / Group Housing project

NISHIGANDH 1

By Vastushilp

RG-MH-25478 · RERA P52100013723 · Last updated on MahaRERA portal: 9 Oct 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 93 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 93 months from the original
11 of 11Construction stages doneevery applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 162 documents Report an error

NISHIGANDH 1 is a Residential / Group Housing project by Vastushilp in Pune, Maharashtra, registered with MahaRERA as P52100013723 on 23 Oct 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 93 months from the original filing.

At a glance

Project

  • NameNISHIGANDH 1
  • TypeResidential / Group Housing
  • Location
    • WAGHOLI
    • Haveli
    • Pune
    • 411014
  • Pincode411014
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100013723
  • ReraGenie IDRG-MH-25478

Builder

  • NameVastushilp
  • Entity typePartnership
  • PartnersJyoti Rahul Jagtap, Rajendra Hanumantrao Ghatge
  • Other registrations2 more →
  • Completed1 of 3

Key dates

this monthRegisteredOct 2017First promiseMar 2019Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Oct 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Mar 2019)
  • Buildings1 building record
  • Documents filed162 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NishigandhNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

Nishigandh: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 9 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area774 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
Declared on11 Sep 2024

Approvals and building plan

Sanctioning authorityPUNE METROPOLITAN REGION DEVELOPMENT AUTHORITY
Permissible FSI761.0
Proposed, not sanctioned761 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShristi chambers pune nagar road oune 411014

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Architectsandeep khatpe
EngineerRAJENDRA GHATAGE
Chartered AccountantANUPAMA SHETTY
Chartered AccountantA P SINGHI & CO
PartnerRole in project
Vastushilp-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100009445Mar 2019 → Dec 2021

Reason as filed by the promotercomplition ceritificate not received

EXT52100002445Mar 2019 → Mar 2020

Reason as filed by the promoterFourth Floor sanction was in process . we got sanctioned in sept 2019.

EXT52100006299Mar 2019 → Mar 2021

Reason as filed by the promoterwork is completed . occupancy certificate not received .

EXT52100024688Mar 2019 → Dec 2026

Reason as filed by the promotercompletion certificate not yet received. building work is completed.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Sep 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Sep 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Sep 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Dec 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed162

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 162 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT A.pdf9 Oct 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT A.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30092024.pdf7 Oct 2024
Disclosure of sold/ booked inventoryFile: 30092024.pdf7 Oct 2024
Certificates of CA (Form 3)File: 30092024.pdf7 Oct 2024
Certificates of CA (Form 3)File: 30092024.pdf7 Oct 2024
Declaration in FORM BFile: FORM B.pdf7 Oct 2024
Declaration in FORM BFile: FORM B.pdf7 Oct 2024
Certificates of CA (Form 3)File: 30092024.pdf7 Oct 2024
Certificates of CA (Form 3)File: 30092024.pdf7 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30092024.pdf7 Oct 2024
Disclosure of sold/ booked inventoryFile: 30092024.pdf7 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31032021.pdf6 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30062021.pdf6 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30092021.pdf6 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31122021.pdf6 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31032022.pdf6 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30062022.pdf6 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30092022.pdf6 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31122022.pdf6 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31032023.pdf6 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30062023.pdf6 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30092023.pdf6 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31122023.pdf6 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31032024.pdf6 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30062024.pdf6 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30092024.pdf6 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30032021.pdf6 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30062021.pdf6 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30092021.pdf6 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30122021.pdf6 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30032022.pdf6 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30062022.pdf6 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30092022.pdf6 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30122022.pdf6 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30032023.pdf6 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30062023.pdf6 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30092023.pdf6 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30122023.pdf6 Oct 2024
Certificates of CA (Form 3)File: 31032021.pdf6 Oct 2024
Certificates of CA (Form 3)File: 30062021.pdf6 Oct 2024
Certificates of CA (Form 3)File: 30092021.pdf6 Oct 2024
Certificates of CA (Form 3)File: 31122021.pdf6 Oct 2024
Certificates of CA (Form 3)File: 31032022.pdf6 Oct 2024
Certificates of CA (Form 3)File: 30062022.pdf6 Oct 2024
Certificates of CA (Form 3)File: 30092022.pdf6 Oct 2024
Certificates of CA (Form 3)File: 31122022.pdf6 Oct 2024
Certificates of CA (Form 3)File: 31032023.pdf6 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: nishigandh 1 form 5 2021-2022.pdf6 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: nishigandh 1 form 5 2022-2023.pdf6 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: nishigandh-1 form 5 2023-2024.pdf6 Oct 2024
Disclosure of sold/ booked inventoryFile: 31032021.pdf6 Oct 2024
Disclosure of sold/ booked inventoryFile: 30062021.pdf6 Oct 2024
Disclosure of sold/ booked inventoryFile: 30092021.pdf6 Oct 2024
Disclosure of sold/ booked inventoryFile: 31122021.pdf6 Oct 2024
Disclosure of sold/ booked inventoryFile: 30032022.pdf6 Oct 2024
Disclosure of sold/ booked inventoryFile: 30062022.pdf6 Oct 2024
Disclosure of sold/ booked inventoryFile: 30092022.pdf6 Oct 2024
Disclosure of sold/ booked inventoryFile: 31122022.pdf6 Oct 2024
Disclosure of sold/ booked inventoryFile: 31032023.pdf6 Oct 2024
Disclosure of sold/ booked inventoryFile: 30062023.pdf6 Oct 2024
Disclosure of sold/ booked inventoryFile: 30092023.pdf6 Oct 2024
Disclosure of sold/ booked inventoryFile: 31122023.pdf6 Oct 2024
Disclosure of sold/ booked inventoryFile: 31032024.pdf6 Oct 2024
Disclosure of sold/ booked inventoryFile: 30062024.pdf6 Oct 2024
Other - TechnicalFile: declaration cum undertaking nishigandh 1 project.pdf6 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of interest in other real estate organizations_page-0001.pdf6 Oct 2024
Certificates of CA (Form 3)File: 30062023.pdf6 Oct 2024
Certificates of CA (Form 3)File: 30092023.pdf6 Oct 2024
Certificates of CA (Form 3)File: 31122023.pdf6 Oct 2024
Certificates of CA (Form 3)File: 31032024.pdf6 Oct 2024
Certificates of CA (Form 3)File: 30062024.pdf6 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: nishigandh 1 form 5 2020-2021.pdf6 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30032024.pdf6 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30062024.pdf6 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2020-21.pdf6 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2021-22.pdf6 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2022-23.pdf6 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2023-24.pdf6 Oct 2024
CERSAI detailsFile: CERSAI declaration nishigandh 1.pdf6 Oct 2024

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 93 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NISHIGANDH 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WAGHOLI13,700+ in Pune

2 kmNISHIGANDH 1Completed 34Lapsed / revoked 15Other 22Dot size: filed unitsN

Filed coordinates, straight-line distance. 71 registered projects within 2 km.

Builder: Vastushilp

Vastushilp has 3 registrations on MahaRERA, including SONCHAFA and NISHIGANDH 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if NISHIGANDH 1 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NISHIGANDH 1?

The registered promoter entity is Vastushilp, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NISHIGANDH 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NISHIGANDH 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NISHIGANDH 1?

The professionals named in the filing: Architect: sandeep khatpe; Engineer: RAJENDRA GHATAGE; Chartered Accountant: ANUPAMA SHETTY; Chartered Accountant: A P SINGHI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NISHIGANDH 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NISHIGANDH 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NISHIGANDH 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.