ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / NIRVANA BEYOND WING E

Completed No litigation declared Residential / Group Housing project

NIRVANA BEYOND WING E

By DIAMOND NEXUS PROPERTIES

RG-MH-55412 · RERA P52100049505 · Last updated on MahaRERA portal: 26 Nov 2024

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 3 other registrations.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2024Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

NIRVANA BEYOND WING E is a Residential / Group Housing project by DIAMOND NEXUS PROPERTIES in Pune, Maharashtra, registered with MahaRERA as P52100049505 on 15 Feb 2023. The registration is recorded completed; possession was promised by 31 Dec 2024.

At a glance

Project

  • NameNIRVANA BEYOND WING E
  • TypeResidential / Group Housing
  • Location
    • RAVET KIVALE ROAD
    • KATALE VASTI
    • Kivale
    • Mawal
    • Pune
    • 412101
  • Pincode412101
  • RERA no.P52100049505
  • ReraGenie IDRG-MH-55412

Builder

  • NameDIAMOND NEXUS PROPERTIES
  • Entity typePartnership
  • PartnersSATISHKUMAR RAVJIBHAI PATEL, BHAVESH HARIBHAI PATEL, RASIK NARSINF CHAUHAN, BHARAT NARSINGH PATEL, MAHESH LALJIBHAI PATEL, RUPALI VISHWAS DARADE, HARDIK RASIKBHAI PATEL
  • Other registrations3 more →
  • Completed4 of 4

Key dates

this monthRegisteredFeb 2023PromisedDec 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on15 Feb 2023
  • Promised completion31 Dec 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed54 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ENA170000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 26 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

WING E: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 26 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed115

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots115
Closed/Covered115

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,498 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
SADASHIV BHIKHOBHA KATALEKiwalePune

Approvals and building plan

Permissible FSI8735.0
Proposed, not sanctioned8,735 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNIGADI PUNE

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDream Space Architects
EngineerAADHAR ENGENDERS
Chartered AccountantVinit D Achha And Associates Chartered Accountants
PartnerRole in project
DIAMOND NEXUS PROPERTIES-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Sep 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Jan 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Dec 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 26 Nov 2024

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: ARCHITECT CERTIFICATE DATE 18-11-2024_0001.pdf26 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COMPLITION CERTIFICATE (D WING E) Date- 30-10-2024.pdf26 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 08) AECHITECTS CERTIFICATE DATE - 14-11-2024.pdf18 Nov 2024
Architect’s Certificate on Completion of Project (Form 4)File: ARCHITECT CERTIFICATE DATE 18-11-2024_0001.pdf18 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Annual Repots Date- 09-07-2024_0001.pdf5 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5) CA CERTIFICATE DATE 25-12-2023 (30-09-23)_comp.pdf26 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 6) CA CERTIFICATE DATE - 13-04-2024 (30-03-24)_comp.pdf26 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4ENG CERTIFICATE DATE 30122023.pdf19 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 07) AECHITECTS CERTIFICATE DATE - 01-07-2024.pdf17 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 06) AECHITECTS CERTIFICATE DATE - 01-04-2024.pdf9 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5ENG CERTIFICATE DATE 08042024.pdf9 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 05)ARCHITECTS CERTIFICATE DATE 30-12-2023_0001.pdf2 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 Form 3 30062023.pdf25 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Form 3 30092023.pdf25 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 01)ARCHITECTS CERTIFICATE DATE 31-03-2023_0001.pdf19 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 03)ARCHITECTS CERTIFICATE DATE 30-06-2023_0001.pdf19 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 04)ARCHITECTS CERTIFICATE DATE 27-09-2023_0001.pdf19 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 ENG CERTIFICATE DATED 31032023.pdf19 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 ENG CERTIFICATE DATED 30062023.pdf19 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 ENG CERTIFICATE DATED 30092023.pdf19 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 Form 3 31032023.pdf19 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annual Repots Date-20-09-2023_0001.pdf19 Dec 2023
Proforma of Agreement for saleFile: 1 Proforma of Agreement for sale.pdf11 Feb 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to model copy of Agreement.pdf10 Feb 2023
Declaration in FORM BFile: FORM B Pramoter DATE 20-01-2023_0001_compressed.pdf24 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration About Separate Bank Account.pdf24 Jan 2023
Layout approvalFile: layout (2).pdf17 Jan 2023
Copy of Layout Approval (in case of layout)File: layout (2).pdf17 Jan 2023
Declaration about Commencement CertificateFile: Declaration CC.pdf17 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: SRP Discloser of Interest in other real Estate.pdf11 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: HPP Discloser of Interest in other real Estate.pdf11 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: BHP Discloser of Interest in other real Estate.pdf11 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: HRP Discloser of Interest in other real Estate.pdf11 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: RNC Discloser of Interest in other real Estate.pdf11 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: BNP Discloser of Interest in other real Estate.pdf11 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: MLP Discloser of Interest in other real Estate.pdf11 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: RVD Discloser of Interest in other real Estate.pdf11 Jan 2023
Building plan approvalFile: 3.pdf19 Dec 2022
Building plan approvalFile: 4.pdf19 Dec 2022
Building plan approvalFile: 5.pdf19 Dec 2022
Details of encumbrances concerned to FinanceFile: NoEncLegal.pdf19 Dec 2022
Details of encumbrances concerned to LegalFile: NoEncLegal.pdf19 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: 3.pdf19 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: 4.pdf19 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: 5.pdf19 Dec 2022
CERSAI detailsFile: CERSAI.pdf19 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_CERTIFICATE_FORM-3.pdf19 Dec 2022
Copy of the legal title reportFile: 1 SEARACH REPORT DATE 07-06-2022_compressed.pdf7 Sep 2022
Proforma of Allotment letterFile: Wing E Allotment Letter .pdf7 Sep 2022
Deviation Report with respect to Allotment letterFile: DEVIATIONS REPORT ALLOTMENT LETTER_0001.pdf7 Sep 2022
Details of encumbrances concerned to LegalFile: 1 SEARACH REPORT DATE 07-06-2022_compressed.pdf24 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: 20220315040825_Compressed.pdf24 Aug 2022
PAN CardFile: PAN CARD.pdf20 Jul 2022
Details of encumbrances concerned to FinanceFile: NO ENCUMBRAMCE DECLARATION.pdf20 Jul 2022

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NIRVANA BEYOND WING E on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KATALE VASTI13,700+ in Pune

Builder: DIAMOND NEXUS PROPERTIES

Diamond Nexus Properties has 4 registrations on MahaRERA, including NIRVANA BEYOND A WING and NIRVANA BEYOND B WING. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if NIRVANA BEYOND WING E is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NIRVANA BEYOND WING E?

The registered promoter entity is DIAMOND NEXUS PROPERTIES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NIRVANA BEYOND WING E?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NIRVANA BEYOND WING E?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NIRVANA BEYOND WING E?

The professionals named in the filing: Architect: Dream Space Architects; Engineer: AADHAR ENGENDERS; Chartered Accountant: Vinit D Achha And Associates Chartered Accountants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NIRVANA BEYOND WING E?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NIRVANA BEYOND WING E. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NIRVANA BEYOND WING E to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.