Home / Browse projects / NIRMITI 25 EAST

Registration lapsed No litigation declared Residential / Group Housing project

NIRMITI 25 EAST

By NIRMITI VASTU CREATION LLP

RG-MH-11907 · RERA P52100002410 · Last updated on MahaRERA portal: 19 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Mar 2026Possession promised7 months past this date
3 of 11Construction stages donefurthest along: Internal walls, 92%
0 of 142Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 196 documents Report an error

NIRMITI 25 EAST is a Residential / Group Housing project by NIRMITI VASTU CREATION LLP in PUNE, 411014, registered with MahaRERA as P52100002410 on 31 Jul 2017. Possession was promised by 28 Mar 2026 and is now 7 months past that date. The completion date has moved by 24 months from the original filing. 142 of the 142 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameNIRMITI 25 EAST
  • TypeResidential / Group Housing
  • Location
    • KHARADI
    • PUNE
    • 411014
  • Pincode411014
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100002410
  • ReraGenie IDRG-MH-11907

Builder

  • NameNIRMITI VASTU CREATION LLP
  • Entity typePartnership
  • PartnersSHARMILA NITIN PURANIK, SUJATA SUNIL PURANIK
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

7 months past promisethis monthRegisteredJul 2017First promiseMar 2024Revised toMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Jul 2017
  • Promised completion28 Mar 2026
  • Revised completionRevised to 28 Mar 2026 (originally 30 Mar 2024)
  • Buildings1 building record
  • Documents filed196 files

Current status

100%142 of 142 units booked
92.2%Work done, per cost certificate

Figures as on 19 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NIRMITI 25 EASTNA16121420142

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 92%.

NIRMITI 25 EAST: 50% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises92%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks88%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes75%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes75%
Energy managemcntYes50%
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed107

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots107
Closed/Covered93
Open Space14

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,467 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Sep 2025

Approvals and building plan

Sanctioning authorityPoona Municipal Corporation
Permissible FSI8947.0
Proposed, not sanctioned3,250 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHANDARKAR ROAD
Estimated costRs 34.60 cr
Cost incurredRs 31.89 cr
Work done92.15%
BuildingWingEstimatedIncurred
NIRMITI 25 EASTNARs 31.50 crRs 29.25 cr
-NARs 3.10 crRs 2.63 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJAGDISH DESHPANDE
ArchitectVishal J Deshpande
EngineerRAMESH CHINCHANI
Chartered AccountantCA PUSHPAK BOGATI
Chartered AccountantCA ABHIJIT MUNDADA
Chartered AccountantS P A K & Co
Chartered AccountantBogati & Co.
PartnerRole in project
NIRMITI VASTU CREATION LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100017401Mar 2024 → Mar 2025

Reason as filed by the promoterdue to covid 19 we were not able to construct anymore because of lack of labour contractors and poor market condition we were unable to complete the project within the due time

EXT52100027876Mar 2024 → Mar 2026

Reason as filed by the promoterThe project has two wings A wing consists of 71 units and B wing consistts of 71 units. A wing is complete in all respect and possession is given to 69 units alongwith Part OC dated 26/04/2024. B wing is 95% Completed. Detailed document and Format B is attached.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12400536Hemant Ashok GadeNIRMITI VASTU CREATION LLP23/10/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Jan 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Apr 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Apr 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 May 2024

Documents filed196

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 196 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Dec 24.pdf19 May 2026
Form 2File: F2 Dec 24.pdf19 May 2026
Form 3File: F3 Dec 24.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: Disclsoure of Sold Dec 2024.pdf19 May 2026
Withdrawal Update Form 1File: Dec 25.pdf25 Feb 2026
Withdrawal Update Form 1File: Dec 25.pdf25 Feb 2026
Withdrawal Update Form 1File: Dec 25.pdf25 Feb 2026
Withdrawal Update Form 2File: Nirmiti 25 east Form 2 Dec 2025 Qtr.pdf25 Feb 2026
Withdrawal Update Form 2File: Nirmiti 25 east Form 2 Dec 2025 Qtr.pdf25 Feb 2026
Withdrawal Update Form 2File: Nirmiti 25 east Form 2 Dec 2025 Qtr.pdf25 Feb 2026
Withdrawal Update Form 3File: Nirmiti 25 East Form 3 Dec 25 (Revised Estimate) Final.pdf25 Feb 2026
Withdrawal Update Form 3File: Nirmiti Dec 25 Form 3.pdf25 Feb 2026
Withdrawal Update Form 3File: Nirmiti Dec 25 Form 3.pdf25 Feb 2026
Withdrawal Update Form 1File: Form 1 Nirmiti 25 East_June_2025.pdf18 Feb 2026
Withdrawal Update Form 1File: Sept 25.pdf18 Feb 2026
Withdrawal Update Form 2File: Form 2 Nirmiti 25 East for June_2025.pdf18 Feb 2026
Withdrawal Update Form 2File: Nirmiti 25 East Form 2 Sept_2025.pdf18 Feb 2026
Withdrawal Update Form 3File: Form 3 Nirmiti 25 East June_2025 Qtr.pdf18 Feb 2026
Withdrawal Update Form 3File: Form 3 Nirmiti 25 East Sept 2025 (Revised Estimate).pdf18 Feb 2026
Form 5 (FY 2024-2025)File: Form 5 Nirmiti 25 East 31-03-2025.pdf31 Oct 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec 24.pdf24 Mar 2025
CERSAI detailsFile: Declairation for Cersai for Nirmiti 25 East.pdf24 Mar 2025
Declaration in FORM BFile: FORM B 28-03-2026.pdf17 Mar 2025
Disclosure of sold/ booked inventoryFile: Nirmiti 25 East Disclosure of Sold Unsold Inventory 31-12-2024.pdf17 Mar 2025
Details of encumbrances concerned to FinanceFile: Declaration of no encumbrances- legal.pdf15 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration for Separarte bank account.pdf15 Mar 2025
Details of encumbrances concerned to LegalFile: Declaration of no encumbrances- legal.pdf15 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other real estate organisations.pdf15 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Nirmiti 23 to 24.pdf10 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec 2018.pdf8 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Jun 2019.pdf8 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Jun 2021.pdf8 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Jun 2023.pdf8 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mar 18.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Jun 18.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sep 18.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mar 18.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Jun 18.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sep 18.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sep 20.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mar 22.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dec 22.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mar 23.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dec 23.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Jun 24 (1).pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dec 24 (1).pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mar 19.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec 24.pdf3 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 Dec 24.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Dec 24.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Sep 24.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Jun 24.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Mar 24.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Dec 23.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Sep 23.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Jun 23.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Mar 23.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Dec 22.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Sep 22.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Jun 22.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Mar 22.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Dec 21.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Sep 21.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Jun 21.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Mar 21.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Dec 20.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Sep 20.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Jun 20.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Mar 20.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Dec 19.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Sep 19.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Jun 19.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Mar 19.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Dec 18.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Sep 18.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Jun 18.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Mar 18.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Dec 17.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Sep 17.pdf3 Mar 2025
Certificates of CA (Form 3)File: F3 Mar 21.pdf25 Feb 2025

Keep NIRMITI 25 EAST on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUNE

2 kmNIRMITI 25 EASTCompleted 50Lapsed / revoked 23Other 48Dot size: filed unitsN

Filed coordinates, straight-line distance. 121 registered projects within 2 km.

Builder: NIRMITI VASTU CREATION LLP

NIRMITI VASTU CREATION LLP has 2 registrations on MahaRERA, including NIRMITI 25 EAST and NIRMITI ELITE. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What does it mean that NIRMITI 25 EAST shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if NIRMITI 25 EAST is delayed beyond 28 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NIRMITI 25 EAST?

The registered promoter entity is NIRMITI VASTU CREATION LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NIRMITI 25 EAST?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against NIRMITI 25 EAST?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for NIRMITI 25 EAST?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NIRMITI 25 EAST?

The professionals named in the filing: Architect: JAGDISH DESHPANDE; Architect: Vishal J Deshpande; Engineer: RAMESH CHINCHANI; Chartered Accountant: CA PUSHPAK BOGATI; Chartered Accountant: CA ABHIJIT MUNDADA; Chartered Accountant: S P A K & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NIRMITI 25 EAST?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NIRMITI 25 EAST. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NIRMITI 25 EAST to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.