Home / Browse projects / Mumbai City, Maharashtra / NINE REFLEX

Registered No litigation declared Residential / Group Housing project

NINE REFLEX

By REFLEX PROJECTS LLP

RG-MH-63750 · RERA P51900034207 · Last updated on MahaRERA portal: 30 Mar 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 24 months from the original
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 95%
64 of 71Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

NINE REFLEX is a Residential / Group Housing project by REFLEX PROJECTS LLP in Mumbai City, Maharashtra, registered with MahaRERA as P51900034207 on 25 Mar 2022. Possession is promised by 30 Dec 2026. The completion date has moved by 24 months from the original filing. 7 of the 71 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameNINE REFLEX
  • TypeResidential / Group Housing
  • Location
    • B J DEVRUKHKAR ROAD
    • DADAR NAIGAON
    • Mumbai City
    • 400014
  • Pincode400014
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900034207
  • ReraGenie IDRG-MH-63750

Builder

  • NameREFLEX PROJECTS LLP
  • Entity typePartnership
  • GSTIN27ABAFR0040G1ZP
  • PartnersMANISH MAHIPATRAI SHAH, RAKESH MAHIPATRAI SHAH

Key dates

this monthRegisteredMar 2022First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Mar 2022
  • Promised completion30 Dec 2026
  • Revised completionRevised to 30 Dec 2026 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed56 files

Current status

10%7 of 71 units booked
84.2%Work done, per cost certificate

Figures as on 30 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NINE REFLEXNA2422591271

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 95%.

NINE REFLEX: 58% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises5%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 30 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes30%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed22

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots22
Closed/Covered22

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area605 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Mar 2026
LandownerVillageDistrict
SMT. R. M. SHAH FAMILY TRUSTABCD-400001Mumbai City

Approvals and building plan

Sanctioning authorityBRIHANMUMBAI MUNICIPAL CORPORATION
Permissible FSI3219.0
Proposed, not sanctioned2,682 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR JEHANGIR BUILDING M G ROAD FORT MUMBAI 400001
Estimated costRs 15.87 cr
Cost incurredRs 13.37 cr
Work done84.25%
BuildingWingEstimatedIncurred
NINE REFLEXNARs 13.37 crRs 13.37 cr
-NARs 2.50 cr-

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKALPESH L SHAH
ArchitectSKYLINE ARCHITECTS
ArchitectKEVIN SHAH
EngineerDHAVAL GANDHI
EngineerAAKASH RAJENDRA PATIL
Chartered AccountantDHAVAL THAKKAAR
Chartered AccountantSANKET SHAH
PartnerRole in project
REFLEX PROJECTS LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900025010Dec 2024 → Dec 2025

Reason as filed by the promoterThe promoters getting delayed in approvals and earlier fund issues, but now approval also available and fund also. As per the RERA Rules we have applied for extension and request you to approved as per MahaRERA Rules and Regulations.

EA30032620453Dec 2024 → Dec 2026

Reason as filed by the promoterTHE PROJECT DELAYED DUE TO SOME WORK IS PENDING AND TAKE SOME TIME APPROVAL FOR OCCUPANCY CERTIFICATE.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2026

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: 1 Form 1 Architect Jun 25.pdf30 Mar 2026
Withdrawal Update Form 1File: 1 Form 1 Architect Sep 25.pdf30 Mar 2026
Withdrawal Update Form 1File: ARCHITECTS CERTIFICATE DEC 25.pdf30 Mar 2026
Withdrawal Update Form 2File: 2 ENGINEER CERTIFICATE JUN 25.pdf30 Mar 2026
Withdrawal Update Form 2File: 2 Form 2 Enginner Certificate Sep 25.pdf30 Mar 2026
Withdrawal Update Form 2File: ENGINEER CERTIFICATE DEC 25.pdf30 Mar 2026
Withdrawal Update Form 3File: C A CERTIFICATE 30TH JUN 2022.pdf30 Mar 2026
Withdrawal Update Form 3File: C A CERTIFICATE 30TH JUN 2022.pdf30 Mar 2026
Withdrawal Update Form 3File: CA CERTIFICATE DEC 25.pdf30 Mar 2026
Withdrawal Update Form 1File: Architect Certificate Nine Reflex.pdf25 Mar 2026
Withdrawal Update Form 2File: Nitesh Engineer's Certificate - Jun 24.pdf25 Mar 2026
Withdrawal Update Form 3File: C A CERTIFICATE 30TH JUN 2022.pdf25 Mar 2026
Form 5 (FY 2024-2025)File: FORM 5 TILL 31ST MARCH 2025.pdf17 Mar 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE TILL DECEMBER 2024.pdf27 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE TILL DECEMBER 2024.pdf27 Mar 2025
Declaration in FORM BFile: FORM B Affidavit Cum Declaration Nine Reflex.pdf24 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE TILL SPTEMBER 2024.pdf24 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE TILL DECEMBER 2024.pdf24 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM III TILL 30 SPTEMBER 2024.pdf19 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM III TILL 31 DECEMBER 2024.pdf19 Mar 2025
Details of encumbrances concerned to FinanceFile: Encumbrances Legal - Nine Reflex.pdf3 Feb 2025
Disclosure of sold/ booked inventoryFile: SOLD AND UNSOLD NINE REFLEX.pdf3 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT A NINE REFLEX.pdf3 Feb 2025
Deviation Report with respect to Allotment letterFile: No Deviation in AL - Nine Reflex.pdf3 Feb 2025
Details of encumbrances concerned to LegalFile: Encumbrances Legal - Nine Reflex.pdf3 Feb 2025
Deviation Report with respect to model copy of AgreementFile: No Deviation in AFS - Nine Reflex.pdf3 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Certificate of Architect - Form 1 10 July 2024 (2).pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate (2).pdf19 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A- QUALITY ASSURANCE 21-22.pdf19 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Declaration of No Interest In other Project.pdf19 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A-QUALITY ASSURANCE 22-23.pdf19 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A-QUALITY ASSURANCE 23-24.pdf19 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 (Mar 23) - Reflex Project LLP.pdf11 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Reflex Project LLP.pdf11 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Certificate of Architect - Form 1 - Jun 24.pdf12 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nitesh Engineer's Certificate - Jun 24.pdf12 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf17 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERTIFICATE 31 MARCH 2022.pdf8 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERTIFICATE 30TH JUN 2022.pdf8 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Certificate of Architect - Form 1 dated 12-07-2022.pdf7 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE FORM 3.pdf19 Mar 2022
OtherFile: 14TH ,15TH 18TH TO 22ND PROPOSED PLAN.pdf19 Mar 2022
Copy of the legal title reportFile: RERA Title Report_Reflex Project LLP.pdf10 Mar 2022
Layout approvalFile: Declration no layout.pdf9 Mar 2022
Building plan approvalFile: BUILDING SANTION PLAN.pdf9 Mar 2022
Details of encumbrancesFile: Encumbrances Declaration.pdf9 Mar 2022
Copy of Layout Approval (in case of layout)File: Declration no layout.pdf9 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: BUILDING SANTION PLAN.pdf9 Mar 2022
Declaration about Commencement CertificateFile: Declaration About CC Form D.pdf9 Mar 2022
Declaration in FORM BFile: FORM B.pdf9 Mar 2022
CERSAI detailsFile: Encumbrances Declaration.pdf9 Mar 2022
PAN CardFile: REFLEX PROJECTS LLP PAN CARD.pdf5 Mar 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate dated 05-03-2022.pdf5 Mar 2022
Proforma of Allotment letterFile: RERA Agreement- Daya Manzil 5322 Clean PDF.pdf5 Mar 2022
Proforma of Allotment letterFile: ALLOTMENT DRAFT NINE REFLEX 5322 Clean PDF.pdf5 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: FirstCC_signed.pdf17 Dec 2021

How this compares with Mumbai City

10%of this project is bookeddistrict median 17%
33%of Mumbai City projects moved their completion datethis one moved by 24 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is on the register

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NINE REFLEX on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DADAR NAIGAON780+ in Mumbai City

2 kmNINE REFLEXCompleted 77Lapsed / revoked 55Other 94Dot size: filed unitsN

Filed coordinates, straight-line distance. 226 registered projects within 2 km.

Builder: REFLEX PROJECTS LLP

REFLEX PROJECTS LLP has 1 registration on MahaRERA, including NINE REFLEX. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What are my rights if NINE REFLEX is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NINE REFLEX?

The registered promoter entity is REFLEX PROJECTS LLP, a partnership as per the filing. Its GSTIN 27ABAFR0040G1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NINE REFLEX?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NINE REFLEX?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NINE REFLEX?

The professionals named in the filing: Architect: KALPESH L SHAH; Architect: SKYLINE ARCHITECTS; Architect: KEVIN SHAH; Engineer: DHAVAL GANDHI; Engineer: AAKASH RAJENDRA PATIL; Chartered Accountant: DHAVAL THAKKAAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NINE REFLEX?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NINE REFLEX. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NINE REFLEX to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.