ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Nilharsh DWARKA

Registration lapsed No litigation declared Residential / Group Housing project

Nilharsh DWARKA

By Nilharsh Projects

RG-MH-24714 · RERA P52100010815 · Last updated on MahaRERA portal: 24 Jan 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 18 months past the filed date
  • Completion date moved by 58 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Apr 2025Possession promised18 months past this date
8 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 95%
0Complaints at MahaRERAon this registration
Jump to the 69 documents Report an error

Nilharsh DWARKA is a Residential / Group Housing project by Nilharsh Projects in Pune, Maharashtra, registered with MahaRERA as P52100010815 on 31 Aug 2017. Possession was promised by 30 Apr 2025 and is now 18 months past that date. The completion date has moved by 58 months from the original filing.

At a glance

Project

  • NameNilharsh DWARKA
  • TypeResidential / Group Housing
  • Location
    • Bhakti Vedanta Sawami Marg
    • ISKCON temple Ravet Pradhikaran
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100010815
  • ReraGenie IDRG-MH-24714

Builder

  • NameNilharsh Projects
  • Entity typePartnership
  • GSTIN27AAGFN7949H2ZQ
  • PartnerBhagwan Pandurang Sonar

Key dates

18 months past promisethis monthRegisteredAug 2017First promiseJun 2020Revised toApr 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Aug 2017
  • Promised completion30 Apr 2025
  • Revised completionRevised to 30 Apr 2025 (originally 30 Jun 2020)
  • Buildings1 building record
  • Documents filed69 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DwarkaNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

Dwarka: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities20

As on 24 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes85%
Street LightingYes80%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes80%
Solid Waste Management And DisposalYes80%
Water conservation /Rain water harvestingYes80%
Energy managemcntYes85%
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes80%
Open ParkingYes85%
Vertical green wall at south elevation faceYes95%
solar water heaterYes85%
Rooftop solar power plantYes80%
Open Kitchen Area Or Community KitchenYes80%
Drinking Water WellYes90%

Parking filed62

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots62
Closed/Covered49
Open Space13

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,000 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2728.56
Proposed, not sanctioned1,999 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTJSB Sahkari Bank Ltd Plot No 449 Sector 27 A Nigdi Pradhikaran Pune 411044

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerSarvasidhant Structural engineers pvt ltd
Chartered AccountantS G Somwanshi
Chartered AccountantSuresh Somvanshi
PartnerRole in project
Nilharsh Projects-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100002041Jun 2020 → Jun 2020

Reason as filed by the promoterRespected Sir, Nilharsh projects is committed to promoting green building and Nilharsh DWARKA is our very first project, We are fully committed to Nilharsh DWARKA but the ground reality remains that we have been unable to generate any sort of sales figures since the introduction of the RERA. We even have not been able to purchase any new materials and also the work on Nilharsh DWARKA site has been stopped due to same reasons. We have not done any financial transactions and have attached following documents supporting our claim. 1. Bank statement 2. C. A certificate Due to misinformation regard

EXT52100009330Jun 2020 → Dec 2022

Reason as filed by the promoterNilharsh DWARKA is a one of it's kind project based on the concepts of innovation in design and eco friendly living aimed towards creating a healthy lifestyle for the residents. Sir/ma'am, The real estate sector had been facing some problems and we couldn't generate bookings due to various factors like slack in the housing sector, uncertainty in minds of home buyers and the biggest sole reason of the Pandemic i.e., COVID 19. The subsequent lockdown which was imposed for the safety of Citizens had a very negative impact on the economy worldwide and had impacted the supply chain all over the wor

EXT52100018771Jun 2020 → Aug 2024

Reason as filed by the promoterWe, Nilharsh Projects, are the promoters of the residential project named Nilharsh Projects Dwarka, located at Ravet, Pune, Maharashtra. We have already completed 4 floors of the project and have obtained the part completion certificate for the same on12/12/2022 and uploaded the document along with form 4 to RERA portal, We have also handed over the possession of the units on these floors to the respective allottees. The work on the remaining 3 floors is more than 80% complete and is slated to finish by 31 July 2024. We are confident that we will be able to complete the project within the exte

EXT52100024634Jun 2020 → Apr 2025

Reason as filed by the promoterHave marked noc obtained from Allotees with O.C NOT RECIEVED. Have revised form 3 as discussed

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 29 Jun 2023

Documents filed69

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: form.pdf24 Jan 2025
Declaration in FORM BFile: Affadavit.pdf13 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA FORM 1.pdf13 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA FORM 2 24.pdf13 Dec 2024
Declaration about Commencement CertificateFile: commencement declaration.pdf13 Dec 2024
CERSAI detailsFile: CERSAI REPORT.pdf13 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: interst in other organizations.pdf13 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: RERA FORM 2A 24.pdf13 Dec 2024
Certificates of CA (Form 3)File: form 3 (2).pdf27 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form5.pdf27 Nov 2024
Building plan approvalFile: sanction plan 1.pdf19 Mar 2024
Building plan approvalFile: sanction plan 2 .pdf19 Mar 2024
Building plan approvalFile: sanction plan 3 .pdf19 Mar 2024
Building plan approvalFile: sanction plan 4.pdf19 Mar 2024
Building plan approvalFile: sanction plan 5.pdf19 Mar 2024
Building Plan Approval (IOD)File: sanction plan 1.pdf19 Mar 2024
Building Plan Approval (IOD)File: sanction plan 2 .pdf19 Mar 2024
Building Plan Approval (IOD)File: sanction plan 3 .pdf19 Mar 2024
Building Plan Approval (IOD)File: sanction plan 4.pdf19 Mar 2024
Building Plan Approval (IOD)File: sanction plan 5.pdf19 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement 24.pdf19 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: RERA FORM 2A.pdf17 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: RERA FORM 2A.pdf17 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: RERA FORM 2A.pdf17 Jan 2024
Disclosure of sold/ booked inventoryFile: letter head (1).pdf17 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: RERA AC.pdf17 Jan 2024
Details of encumbrances concerned to FinanceFile: ALLOTMENT LETTER (1).pdf14 Jan 2024
Details of encumbrances concerned to LegalFile: ALLOTMENT LETTER (1).pdf14 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 22 23.pdf14 Jan 2024
Proforma of Agreement for saleFile: DRAFT AGREEMENT (1).pdf14 Jan 2024
Deviation Report with respect to Allotment letterFile: ALLOTMENT LETTER.pdf14 Jan 2024
Deviation Report with respect to model copy of AgreementFile: ALLOTMENT LETTER.pdf14 Jan 2024
Home Buyer /Allottee Grievance Redressal CellFile: ALLOTMENT LETTER (2).pdf14 Jan 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: pdf_20230629_215552_0000.pdf29 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21 22.pdf3 May 2023
Building plan approvalFile: 1_compressed.pdf25 Nov 2021
Building plan approvalFile: 2_compressed.pdf25 Nov 2021
Building plan approvalFile: 3_compressed.pdf25 Nov 2021
Building Plan Approval (IOD)File: 1_compressed.pdf25 Nov 2021
Building Plan Approval (IOD)File: 2_compressed.pdf25 Nov 2021
Building Plan Approval (IOD)File: 3_compressed.pdf25 Nov 2021
Commencement Certificates / NA Order for plotted developmentFile: New commencement Nilharsh Dwarka_compressed.pdf25 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: CA certificate, 2018-19.pdf17 Mar 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA certificate, 2018-19.pdf17 Mar 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CA certificate 2019 20.pdf17 Mar 2021
Certificates of CA (Form 5)File: FORM NO 5 DEC2018.pdf21 Dec 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Not Applicable.pdf10 Apr 2018
Status of ConveyanceFile: Not Applicable.pdf10 Apr 2018
OtherFile: certificate of commitment.pdf10 Apr 2018
Layout approvalFile: HPSC0372.pdf3 Aug 2017
Copy of Layout Approval (in case of layout)File: HPSC0372.pdf3 Aug 2017
Certificates of CA (Form 3)File: RERA Form 3 Certificate-compressed.pdf3 Aug 2017
Proforma of Allotment letterFile: Draft Dwarka Rera 2017.pdf2 Aug 2017
Building plan approvalFile: HPSC0372.pdf1 Aug 2017
Building plan approvalFile: HPSC0373.pdf1 Aug 2017
Building plan approvalFile: HPSC0375.pdf1 Aug 2017
Building plan approvalFile: HPSC0376-compressed.pdf1 Aug 2017
PAN CardFile: Pan Card.pdf1 Aug 2017
Copy of the legal title reportFile: Search title 1.pdf1 Aug 2017
Copy of the legal title reportFile: search title 2.pdf1 Aug 2017
Details of encumbrancesFile: Details of Encumbrances.pdf1 Aug 2017
Building Plan Approval (IOD)File: HPSC0372.pdf1 Aug 2017
Building Plan Approval (IOD)File: HPSC0373.pdf1 Aug 2017
Building Plan Approval (IOD)File: HPSC0375.pdf1 Aug 2017
Building Plan Approval (IOD)File: HPSC0376-compressed.pdf1 Aug 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement.pdf1 Aug 2017
Declaration in FORM BFile: Form B.pdf1 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects certificate.pdf1 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 Engineers cirtificate.pdf1 Aug 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 58 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Nilharsh DWARKA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ISKCON temple Ravet Pradhikaran13,700+ in Pune

2 kmNilharsh DWARKACompleted 81Lapsed / revoked 37Other 69Dot size: filed unitsN

Filed coordinates, straight-line distance. 187 registered projects within 2 km.

Builder: Nilharsh Projects

Nilharsh Projects has 1 registration on MahaRERA, including Nilharsh DWARKA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Nilharsh DWARKA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Nilharsh DWARKA is delayed beyond 30 Apr 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Nilharsh DWARKA?

The registered promoter entity is Nilharsh Projects, a partnership as per the filing. Its GSTIN 27AAGFN7949H2ZQ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Nilharsh DWARKA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Nilharsh DWARKA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Nilharsh DWARKA?

The professionals named in the filing: Engineer: Sarvasidhant Structural engineers pvt ltd; Chartered Accountant: S G Somwanshi; Chartered Accountant: Suresh Somvanshi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Nilharsh DWARKA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Nilharsh DWARKA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Nilharsh DWARKA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.