Home / Browse projects / Palghar, Maharashtra / New Star Residency

Registered No litigation declared Residential / Group Housing project

New Star Residency

RG-MH-61121 · RERA PR1240002601690 · Last updated on MahaRERA portal: 16 Jul 2026

Source: official MahaRERA filing

Red flags

  • Allotment letter deviates from the model form

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
Jump to the 2 documents Report an error

New Star Residency is a Residential / Group Housing project by NEW STAR BUILDERS in Palghar, Maharashtra, registered with MahaRERA as PR1240002601690 on 27 Aug 2026. Possession is promised by 31 Dec 2030.

At a glance

Project

  • NameNew Star Residency
  • TypeResidential / Group Housing
  • Location
    • Waliv Road
    • Vasai East
    • Waliv
    • Vasai
    • Palghar
    • 401208
  • Pincode401208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR1240002601690
  • ReraGenie IDRG-MH-61121

Builder

  • NameNEW STAR BUILDERS
  • Entity typePartnership
  • GSTIN27AAIFN2903P3ZU

Key dates

todayRegisteredAug 2026PromisedDec 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Aug 2026
  • Promised completion31 Dec 2030
  • Revised completionNone
  • Buildings4 building records
  • Documents filed2 files

Current status

0%0 of 312 units booked

Figures as on 16 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO.01 WING A B C(Residential)Bldg 1 Wing A121185085
BUILDING NO.01 WING A B C(Residential)Bldg 1 Wing B121198098
BUILDING NO.01 WING A B C(Residential)Bldg 1 Wing C121187087
BUILDING NO.02(Residential)NA8742042

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 16 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing.

BUILDING NO.01 WING A B C(Residential) · wing Bldg 1 Wing A3%
ActivityProgress
Excavation30%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO.01 WING A B C(Residential) · wing Bldg 1 Wing B3%
ActivityProgress
Excavation30%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO.01 WING A B C(Residential) · wing Bldg 1 Wing C3%
ActivityProgress
Excavation30%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO.02(Residential)22%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 16 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing.

Common facilityProposedProgress
Internal Roads & FootpathsNo0%
Water SupplyNo0%
Sewerage (Chamber, Lines, Septic Tank , STP)No0%
Storm Water DrainsNo0%
Landscaping & Tree PlantingNo0%
Street LightingNo0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNo0%
Solid Waste Management And DisposalNo0%
Water conservation /Rain water harvestingNo0%
Energy managemcntNo0%
Fire protection and fire safety requirementsNo0%
Electrical meter room, sub-station, receiving stationNo0%
Aggregate area of recreational Open SpaceNo0%
Open ParkingNo0%

Parking filed208

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots208
Stilt / Ground208
BuildingStilt / GroundTotal
BUILDING NO.01 WING A B C(Residential) Bldg 1 Wing A5757
BUILDING NO.01 WING A B C(Residential) Bldg 1 Wing B6565
BUILDING NO.01 WING A B C(Residential) Bldg 1 Wing C6060
BUILDING NO.02(Residential)2626

Land and ownership1

MahaRERA does not publish landowner contact details.

Land area5,490 sq m
Promoter owns the landNo
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on10 Aug 2026
LandownerVillageDistrict
Santosh Sadanand ThodgeWalivPalghar

Approvals and building plan

Permissible FSI16507.6
Proposed, not sanctioned16,508 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA.

Separate project accountDeclared
Bank branchDOMS COMPLEX,GALA NO.10 23,RANGE OFFICE NAKA,VASAI EAST,THANE 401208

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMegha Kamothi Fernandes
EngineerStructbond Engneering
Chartered AccountantSunil Kumar Kothari
PartnerRole in project
NEW STAR BUILDERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

Documents filed2

As listed on the registration. The files themselves are on the MahaRERA portal.

DocumentUploaded
Declaration cum undertaking one plot16 Jul 2026
LAYOUT PLAN NEW STAR15 Jul 2026

How this compares with Palghar

0%of this project is bookeddistrict median 26%
31%of Palghar projects moved their completion datethis one has not
27%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,204 Palghar projects on ReraGenie, from their own filings.

Keep New Star Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vasai East3,204 in Palghar

Builder: NEW STAR BUILDERS

NEW STAR BUILDERS has 1 registration on MahaRERA, including New Star Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if New Star Residency is delayed beyond 31 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of New Star Residency?

The registered promoter entity is NEW STAR BUILDERS, a partnership as per the filing. Its GSTIN 27AAIFN2903P3ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in New Star Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for New Star Residency?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at New Star Residency?

The professionals named in the filing: Architect: Megha Kamothi Fernandes; Engineer: Structbond Engneering; Chartered Accountant: Sunil Kumar Kothari. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in New Star Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Planning to buy here? The Rs 499 buyer report adds red flags, the progress-versus-promise read, this promoter's other registrations and what the filed documents say, plus a ZIP of every document on the filing. It includes the Rs 299 project watch free for 90 days: an email in plain words every time this project's filing changes. See a real sample report before you buy. Get the buyer report · Rs 499
Studying this micro-market? The developer project analysis maps every registration within 5 km of this project from filed coordinates, reads what the market absorbs and what competes, prices the parcel, and takes the promoter's whole book apart, facts with their N, never a verdict. See a complete sample first. Get the developer analysis · Rs 2,999

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About New Star Residency. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TULJAI TOWER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.