Navkar City - Phase I - Part 8
RG-MH-99159 · RERA P99000033433 · Last updated on MahaRERA portal: 28 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Navkar City - Phase I - Part 8 is a Others project by NAVKAR HOMES TOWNSHIP LLP in Palghar, Maharashtra, registered with MahaRERA as P99000033433 on 22 Feb 2022. Possession is promised by 30 Jun 2027. The completion date has moved by 12 months from the original filing. 171 of the 269 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.
At a glance
Project
- NameNavkar City - Phase I - Part 8
- TypeOthers
- Location
- Don Bosco High School road
- Naigaon East
- Vasai-Virar City (M Corp)
- Vasai
- Palghar
- 401208
- Pincode401208
- RERA no.P99000033433
- ReraGenie IDRG-MH-99159
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on22 Feb 2022
- Promised completion30 Jun 2027
- Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2026)
- Buildings1 building record
- Documents filed66 files
Current status
Figures as on 28 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Navkar City Ph 1 Part 8 Building C3 and C4 | NA | 25 | 25 | 250 | 19 | 269 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 28 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
Navkar City Ph 1 Part 8 Building C3 and C4: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 28 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Navkar City Ph 1 Part 8 Building C3 and C4 | NA | Rs 40.00 cr | Rs 45.89 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RAJESH RC |
| Engineer | MADANJEET RAI |
| Chartered Accountant | RD LUKAD |
| Chartered Accountant | RD LUKAD CO. |
| Partner | Role in project |
|---|---|
| NAVKAR HOMES TOWNSHIP LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Promoter respectfully submits that although substantial progress has been achieved in the construction of the project, the project could not be completed within the originally stipulated timeline due to various practical and unforeseen circumstances encountered during the execution of the development. The construction activities were affected due to delays in procurement of construction materials, shortage of skilled labour, fluctuations in the availability and prices of essential building materials, and the extended time required for coordination of various statutory approvals and utility
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 15 Feb 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 18 Feb 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Feb 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 31 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jun 2027
Documents filed66
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Architect Certi Phase I Part 8.pdf | 28 Jul 2026 |
| Withdrawal Update Form 2File: Engineer certificate Ph 1 Part 8.pdf | 28 Jul 2026 |
| Withdrawal Update Form 3File: FORM 3 NAVKAR CITY PHASE 1 PART 8 _compressed.pdf | 28 Jul 2026 |
| Withdrawal Update Form 1File: Architect Navkar city Phase 1 Part 8.pdf | 21 Apr 2026 |
| Withdrawal Update Form 2File: Engineer certificate Ph 1 Part 8.pdf | 21 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 Phase 1 Part 8 1.pdf | 21 Apr 2026 |
| Form 2A (FY 2021-2022)File: FORM 2AA.pdf | 23 Jan 2026 |
| Form 2A (FY 2022-2023)File: FORM 2AA.pdf | 23 Jan 2026 |
| Form 2A (FY 2023-2024)File: FORM 2AA.pdf | 23 Jan 2026 |
| Form 2A (FY 2025-2026)File: Navkar Phase I Part 8_11zon.pdf | 23 Jan 2026 |
| Form 1File: FORM 1_11zon.pdf | 12 Jan 2026 |
| Form 2File: FORM 2_11zon.pdf | 12 Jan 2026 |
| Form 3File: FORM 3_11zon.pdf | 12 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory.pdf | 12 Jan 2026 |
| Form 5 (FY 2024-2025)File: phase 1 part 8.pdf | 10 Jan 2026 |
| Withdrawal Update Form 1File: C3 u0026 C4 Navkar Phase 1 Part 8_compressed.pdf | 16 Oct 2025 |
| Withdrawal Update Form 2File: Ph I P 8.pdf | 16 Oct 2025 |
| Withdrawal Update Form 3File: FORM 3PHASE-1 PART-8.pdf | 16 Oct 2025 |
| Withdrawal Update Form 1File: C3 u0026 C4 Navkar Phase 1 Part 8_compressed.pdf | 11 Sep 2025 |
| Withdrawal Update Form 2File: Ph I P 8.pdf | 11 Sep 2025 |
| Withdrawal Update Form 3File: FORM 3PHASE-1 PART-8.pdf | 11 Sep 2025 |
| Form 2A (FY 2024-2025)File: Navkar Phase I Part 8_compressed.pdf | 1 Sep 2025 |
| Disclosure of sold/ booked inventoryFile: C3 C4.pdf | 10 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PH-I,PART-8.pdf | 24 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ph I P 8.pdf | 24 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Part 8.pdf | 24 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PH-I,PART-8.pdf | 24 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ph I P 8.pdf | 11 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ph I P 8.pdf | 11 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ph I P 8.pdf | 11 Dec 2024 |
| Other - TechnicalFile: Ph I P 8.pdf | 15 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Ph I P 8.pdf | 13 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ph I P 8.pdf | 28 Oct 2024 |
| Other - FinanceFile: 3416968645.pdf | 19 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ph I P 8 F.pdf | 9 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ph I P 8.pdf | 9 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3PHASE-1 PART-8.pdf | 10 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 3 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 3 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 18 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 18 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 18 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form3.pdf | 18 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form5.pdf | 18 Mar 2024 |
| Proforma of Allotment letterFile: Allotment Letter Phase I Part -8.pdf | 23 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ph I P 8.pdf | 1 Jul 2023 |
| Layout approvalFile: LAYOUT PLAN.pdf | 18 Feb 2022 |
| Building plan approvalFile: C3 C4 - 2.pdf | 18 Feb 2022 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf | 18 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: C3 C4 - 2.pdf | 18 Feb 2022 |
| Building plan approvalFile: C3 C4 - 1.pdf | 16 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: C3 C4 - 1.pdf | 16 Feb 2022 |
| Copy of the legal title reportFile: Flow of the title.pdf | 15 Feb 2022 |
| Proforma of Allotment letterFile: Agreement for sale.pdf | 12 Feb 2022 |
| Proforma of Allotment letterFile: Provisional Booking Letter.pdf | 11 Feb 2022 |
| CERSAI detailsFile: CERSAI_Search_Report.pdf | 9 Feb 2022 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf | 2 Feb 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate form 3.pdf | 2 Feb 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 1 Feb 2022 |
| PAN CardFile: PAN CARD.pdf | 31 Jan 2022 |
| Copy of the legal title reportFile: Legal Title Report.pdf | 31 Jan 2022 |
| Details of encumbrancesFile: Concern Letter.pdf | 31 Jan 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: NA Order.pdf | 31 Jan 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: CC Copy.pdf | 31 Jan 2022 |
| Declaration in FORM BFile: Affidavit.pdf | 31 Jan 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate.pdf | 31 Jan 2022 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| NAVKAR CITY PHASE I PART-1 | Survey no. 332 H No 1 3 4 Near Don Bosco High School Juchandra Naigaon E Tal Vasai Dist Palghar | 131 | Completed | Jun 2021 | Jun 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 66 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Navkar City - Phase I - Part 8 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Naigaon East3,200+ in Palghar
Suraksha Smart City - Phase I
Conceptual Advisory Services LLP
The Great Western Mumbai
HOABL Impactum Land Private Limited
Suraksha Smart City - Phase II
Conceptual Advisory Services LLP
Suraksha Smart City - Phase III
Conceptual Advisory Services LLP
Rashmi Star City Phase 2
Rashmi Realty Builders Pvt Ltd
Agarwal Sky Heights
Shreenath Realtors
See every Palghar project, with the district possession charts
Builder: NAVKAR HOMES TOWNSHIP LLP
NAVKAR HOMES TOWNSHIP LLP has 2 registrations on MahaRERA, including Navkar City - Phase I - Part 8 and NAVKAR CITY PHASE I PART 9. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if Navkar City - Phase I - Part 8 is delayed beyond 30 Jun 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Navkar City - Phase I - Part 8?
The registered promoter entity is NAVKAR HOMES TOWNSHIP LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Navkar City - Phase I - Part 8?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Navkar City - Phase I - Part 8?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Navkar City - Phase I - Part 8?
The professionals named in the filing: Architect: RAJESH RC; Engineer: MADANJEET RAI; Chartered Accountant: RD LUKAD; Chartered Accountant: RD LUKAD CO.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Navkar City - Phase I - Part 8?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback