Home / Browse projects / Palghar, Maharashtra / NAVKAR CITY PHASE I PART 14

Registered No litigation declared Residential / Group Housing project

NAVKAR CITY PHASE I PART 14

By NAVKAR DEVELOPERS

RG-MH-07155 · RERA P99000054543 · Last updated on MahaRERA portal: 22 Apr 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedno revision filed
1 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 92%
180 of 362Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

NAVKAR CITY PHASE I PART 14 is a Residential / Group Housing project by NAVKAR DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000054543 on 31 Jan 2024. Possession is promised by 31 Dec 2028. 182 of the 362 units on this registration are recorded sold or booked, and 1 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameNAVKAR CITY PHASE I PART 14
  • TypeResidential / Group Housing
  • Location
    • DON BOSCO HIGH SCHOOL
    • NAIGAON EAST
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401208
  • Pincode401208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000054543
  • ReraGenie IDRG-MH-07155

Builder

  • NameNAVKAR DEVELOPERS
  • Entity typePartnership
  • PartnersLAXMAN BHIKAJI KHEDKAR, SURESH BHAVARLAL JAIN, NARESH CHANDMAL JAIN, VINODKUMAR BHANWARLAL JAIN
  • Other registrations10 more →
  • Completed3 of 11
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

this monthRegisteredJan 2024PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Jan 2024
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings2 building records
  • Documents filed61 files

Current status

50%182 of 362 units booked
17.3%Work done, per cost certificate

Figures as on 22 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
R1NA24231810181
R2NA24231810181

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 22 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 92%.

R128%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure92%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
R20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 22 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed70

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots70
Closed/Covered70
BuildingClosed/CoveredTotal
R13535
R23535

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,860 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityवसई विरार शहर
Permissible FSI19208.87
Proposed, not sanctioned19,209 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPADMAVATI GRACE SHREE KRISHNA COMPLEX VASAI WEST
Estimated costRs 98.00 cr
Cost incurredRs 16.96 cr
Work done17.31%
BuildingWingEstimatedIncurred
R1NARs 78.40 crRs 13.57 cr
R2NARs 19.60 crRs 3.39 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Architects.Arch Designs
EngineerMADANJEET RAI
Chartered AccountantRDLUKLAD
PartnerRole in project
NAVKAR DEVELOPERS-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
SM12600399Bhakti AchrekarNAVKAR DEVELOPERS12/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Jan 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Jan 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Jan 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Navkar City Phase I Part 14.pdf22 Apr 2026
Withdrawal Update Form 2File: Engineer certificate Ph 1 Part 14.pdf22 Apr 2026
Withdrawal Update Form 3File: Form 3 Ph 1 part 14 1.pdf22 Apr 2026
Form 2A (FY 2023-2024)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24).pdf23 Jan 2026
Form 2A (FY 2025-2026)File: Navkar Phase I Part 14 _11zon.pdf23 Jan 2026
Withdrawal Update Form 1File: FORM 1_11zon.pdf16 Jan 2026
Withdrawal Update Form 2File: FORM2_11zon.pdf16 Jan 2026
Withdrawal Update Form 3File: FORM 3_11zon.pdf16 Jan 2026
Form 5 (FY 2024-2025)File: phase 1 part 14.pdf10 Jan 2026
Withdrawal Update Form 1File: Ph I P 14 F.pdf16 Oct 2025
Withdrawal Update Form 2File: Ph I P 14.pdf16 Oct 2025
Withdrawal Update Form 3File: Navkar Developers - CA certificate_compressed.pdf16 Oct 2025
Form 2A (FY 2024-2025)File: Navkar Phase I Part 14 _compressed.pdf1 Sep 2025
Withdrawal Update Form 1File: Ph I P 14 F.pdf25 Aug 2025
Withdrawal Update Form 2File: Ph I P 14.pdf25 Aug 2025
Withdrawal Update Form 3File: Navkar Developers - CA certificate_compressed.pdf25 Aug 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Navkar Phase 1 Part 14_compressed.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R1 R2 Navkar Phase 1 Part 14 _compressed.pdf18 Apr 2025
Disclosure of sold/ booked inventoryFile: R1 R2.pdf10 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ph I P 14.pdf24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ph I P 14.pdf24 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: E - Ph I P 14.pdf24 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ph I P 14.pdf11 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ph I P 14.pdf11 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ph I P 14.pdf11 Dec 2024
Other - TechnicalFile: Ph I P 14.pdf15 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Ph I P 14.pdf13 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ph I P 14.pdf28 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ph I P 14 F.pdf9 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ph I P 14.pdf9 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2TOWER PART-2.pdf24 May 2024
Layout approvalFile: Layout - 01_11zon.pdf23 Jan 2024
Details of encumbrances concerned to FinanceFile: Self Declaration.pdf23 Jan 2024
Details of encumbrances concerned to LegalFile: Self Declaration.pdf23 Jan 2024
Copy of Layout Approval (in case of layout)File: Layout - 01_11zon.pdf23 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Navkar Developers - CA certificate_compressed.pdf23 Jan 2024
Proforma of Agreement for saleFile: AGREEMENT FOR SALE Navkar City Phase I Part - 14 - fnl- 23-01-2024.pdf23 Jan 2024
Other - LegalFile: Conveyance Deed, Navkar Developers(2)_11zon.pdf23 Jan 2024
Other - TechnicalFile: Clarification against scrutiny.pdf23 Jan 2024
Building plan approvalFile: 1 Building Plan Approval _ NA Order for plotted development.pdf8 Jan 2024
Building plan approvalFile: R1 R2 - 24_11zon.pdf8 Jan 2024
Copy of the legal title reportFile: tITLE cERTIFICATE.pdf8 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 1 Building Plan Approval _ NA Order for plotted development.pdf8 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: R1 R2 - 24_11zon.pdf8 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: 1 Commencement Certificates _ NA Order for plotted development.pdf8 Jan 2024
Declaration about Commencement CertificateFile: DECLARATION CC.pdf8 Jan 2024
CERSAI detailsFile: SELF DECLARATION CERSAI.pdf8 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A NARESH JAIN.pdf8 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A VINOD JAIN.pdf8 Jan 2024
Proforma of Allotment letterFile: ANNEXURE A-Allotment Letter.pdf8 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A-Bank Declaration.pdf8 Jan 2024
Other - LegalFile: CLARIFICATION.pdf8 Jan 2024
PAN CardFile: Navkar Developers Pan Card.pdf25 Nov 2023
Details of encumbrances concerned to FinanceFile: Concerned To Legal.pdf25 Nov 2023
Details of encumbrances concerned to LegalFile: Concerned To Legal.pdf25 Nov 2023
Declaration in FORM BFile: Affedivit - Form B.pdf25 Nov 2023
CERSAI detailsFile: CERSAI_Navkar Developers.pdf25 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure LK.pdf25 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure SJ.pdf25 Nov 2023
Deviation Report with respect to Allotment letterFile: Allotment Letter.pdf25 Nov 2023
Deviation Report with respect to model copy of AgreementFile: Agreement Letter.pdf25 Nov 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
NAVKAR CITY PHASE I PART 3SURVEY NO. 332 1 2 3 4 7 884CompletedDec 2021Jun 2021

How this compares with Palghar

50%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NAVKAR CITY PHASE I PART 14 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NAIGAON EAST3,200+ in Palghar

2 kmNAVKAR CITY PHASE I PARTCompleted 25Lapsed / revoked 8Other 31Dot size: filed unitsN

Filed coordinates, straight-line distance. 64 registered projects within 2 km.

Builder: NAVKAR DEVELOPERS

Navkar developers has 11 registrations on MahaRERA, including Tulsi Centre Point and NAVKAR CITY. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if NAVKAR CITY PHASE I PART 14 is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NAVKAR CITY PHASE I PART 14?

The registered promoter entity is NAVKAR DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NAVKAR CITY PHASE I PART 14?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against NAVKAR CITY PHASE I PART 14?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for NAVKAR CITY PHASE I PART 14?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NAVKAR CITY PHASE I PART 14?

The professionals named in the filing: Architect: s.Arch Designs; Engineer: MADANJEET RAI; Chartered Accountant: RDLUKLAD. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NAVKAR CITY PHASE I PART 14?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NAVKAR CITY PHASE I PART 14. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NAVKAR CITY PHASE I PART 14 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.