Home / Browse projects / Palghar, Maharashtra / Nakshatra Veda II

Registered No litigation declared Residential / Group Housing project

Nakshatra Veda II

By JSB HOMEMAKERS PVT LTD

RG-MH-34929 · RERA P99000048852 · Last updated on MahaRERA portal: 9 Jul 2026

Source: official MahaRERA filing

Red flags

  • Rs 75.00 crore secured on the land, in favour of Axis Bank Limited
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
30 of 44Construction stages doneacross 4 buildings; furthest along: Staircases, 90%
260 of 514Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 101 documents Report an error

Nakshatra Veda II is a Residential / Group Housing project by JSB HOMEMAKERS PVT LTD in Palghar, Maharashtra, registered with MahaRERA as P99000048852 on 24 Jan 2023. Possession is promised by 31 Dec 2026. 254 of the 514 units on this registration are recorded sold or booked, and 30 of 44 construction stages are filed complete.

At a glance

Project

  • NameNakshatra Veda II
  • TypeResidential / Group Housing
  • Location
    • Gokhivare
    • Virar
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401208
  • Pincode401208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000048852
  • ReraGenie IDRG-MH-34929

Builder

  • NameJSB HOMEMAKERS PVT LTD
  • Entity typeCompany
  • DirectorsSunil Devakinandan Seksaria, Divyesh Sunil Seksaria
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredJan 2023PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on24 Jan 2023
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings4 building records
  • Documents filed101 files

Current status

49%254 of 514 units booked
65.5%Work done, per cost certificate

Figures as on 9 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ENA2523928100
Wing FNA252315710167
Wing GNA252390696
Wing JNA262414110151

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 9 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

30 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 90%.

Wing E58%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing F100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing G100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing J42%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure67%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises23%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks67%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 9 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes68%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes50%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes50%
Energy managemcntYes50%
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed87

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots87
Closed/Covered87
BuildingClosed/CoveredTotal
Wing E1919
Wing F3333
Wing G22
Wing J3333

Land and ownership4

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area16,160 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
Encumbrance on the landDeclared present
Charge in favour ofAxis Bank Limited
Secured amountRs 75.00 crore
CERSAI search filedYes
Declared on27 May 2026
LandownerVillageDistrict
Rashmi Ameya Developers Housing & Estate RealtorsVasai-Virar City (M Corp)Palghar
Sai Rydam Realtors Private LimitedVasai-Virar City (M Corp)Palghar
Devendra Rajnikant LadhaniVasai-Virar City (M Corp)Palghar
Anil Ramchandra GuptaVasai-Virar City (M Corp)Palghar

Approvals and building plan

Sanctioning authorityVVCMC
Permissible FSI19179.0
Proposed, not sanctioned19,179 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch1574 - Malad West - Sunder Nagar
Estimated costRs 111.37 cr
Cost incurredRs 73.00 cr
Work done65.55%
BuildingWingEstimatedIncurred
Wing ENARs 25.00 crRs 16.00 cr
Wing FNARs 25.00 crRs 25.00 cr
Wing GNARs 25.00 crRs 25.00 cr
Wing JNARs 25.00 crRs 7.00 cr
-NARs 11.37 cr-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSanat Mehta & Associates
EngineerDeepak Kumar Singh
Chartered AccountantRitesh G Sharma & Co.
Chartered AccountantPARTHKUMAR DHIRAJLAL PATEL
Chartered AccountantPranav Patel & Associates
Chartered AccountantK.B. Mistry & Associates
PartnerRole in project
JSB HOMEMAKERS PVT LTD-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Dec 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Dec 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed101

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 101 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Veda II Form 1 March 26.pdf9 Jul 2026
Withdrawal Update Form 2File: Form 2 Veda II March 26.pdf9 Jul 2026
Withdrawal Update Form 3File: FORM-3_Nakshatra_Veda_II_Signed_c.pdf9 Jul 2026
Withdrawal Update Form 1File: Veda II Form 1 Dec 25.pdf12 Mar 2026
Withdrawal Update Form 2File: Veda II Form 2 Dec 25.pdf12 Mar 2026
Withdrawal Update Form 3File: Form 3 Veda II Dec 2025.pdf12 Mar 2026
Withdrawal Update Form 1File: Form 1 Veda II Sept 25.pdf20 Nov 2025
Withdrawal Update Form 2File: FORM 2-DEEPAK KUMAR SINGH - Sept 25.pdf20 Nov 2025
Withdrawal Update Form 3File: NAKSHATRA VEDA-II Form 3 Sept25.pdf20 Nov 2025
Withdrawal Update Form 1File: VEDA II FORM 1 JUNE 2025.pdf15 Nov 2025
Withdrawal Update Form 2File: Form 2 Nakshatra Veda II Jun 25.pdf15 Nov 2025
Withdrawal Update Form 3File: Form 3 Nakshatra Veda Jun 25.pdf15 Nov 2025
Form 5 (FY 2024-2025)File: Form 5 Nakshatra Veda II.pdf11 Oct 2025
Form 1File: VEDA II FORM 1 JUNE 2025.pdf31 Jul 2025
Form 2File: Form 2 Nakshatra Veda II Jun 25.pdf31 Jul 2025
Form 3File: Form 3 Nakshatra Veda Jun 25.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of inventory Jun 25.pdf31 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Nakshatra Veda II March 2025.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Nakshatra Veda II March 25.pdf3 May 2025
Disclosure of sold/ booked inventoryFile: Disclosure of inventory March 25.pdf19 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Nakshatra Veda II.pdf17 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VEDA 2 FORM 1 MAR 2025.pdf11 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 Form 3_Nakshatra Veda II_Decmber 2024.pdf29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Nakshatra Veda II Dec 24.pdf29 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of inventory Dec 24.pdf25 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VEDA 2 FORM 1 DEC 2024.pdf11 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3_Veda II Sept 24_c.pdf26 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Nakshatra Veda II Sept 24.pdf26 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Nakshatra Veda II Sept 24.pdf15 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: VEDA_II_FORM5_2023_2024.pdf14 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of inventory Sept 24.pdf8 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Veda II Form 3 June 2024.pdf15 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Nakshatra Veda II Jun 24.pdf15 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of inventory Jun 24.pdf15 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Veda II June 24.pdf10 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Nakshatra Veda II March 24.pdf17 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3-Veda II March 24.pdf17 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Nakshatra Veda II March 24.pdf10 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of inventory March 24.pdf27 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Nakshatra Veda II.pdf21 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VEDA II FORM 1 MAR 2024.pdf4 May 2024
Details of encumbrances concerned to FinanceFile: VEDA II BHFL 45CR ENCUMBRANCE.pdf19 Apr 2024
Details of encumbrances concerned to LegalFile: VEDA II BHFL 45CR ENCUMBRANCE.pdf19 Apr 2024
Other - FinanceFile: VEDA II BHFL 45CR ENCUMBRANCE.pdf19 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Nakshatra Veda II.pdf17 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nakshatra Veda II form 3.pdf13 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Veda II Form 5.pdf2 Mar 2024
Disclosure of sold/ booked inventoryFile: Disclosure of inventory Dec 23.pdf10 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VEDA II FORM 1 DEC 2023.pdf6 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: VEDA II FORM 1 DEC 2023.pdf6 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Veda II.pdf10 Nov 2023
Disclosure of sold/ booked inventoryFile: Disclosure of inventory Jun 2023-.pdf10 Nov 2023
Disclosure of sold/ booked inventoryFile: Disclosure of inventory Sept 23.pdf10 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Nakshatra Veda II Sept 23.pdf10 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SEP 2023 VEDA II_11zon.pdf4 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Nakshatra Veda June 23.pdf18 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of inventory Jun 2023.pdf18 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Nakshatra Veda II 30-06-23.pdf18 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of inventory March 2023.pdf2 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 2023.pdf2 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 DEC 22.pdf29 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 March 23 NEW.pdf29 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A March 23.pdf29 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 JUNE 2023.pdf26 Jul 2023
Copy of the legal title reportFile: Form B-Co-Promoter.pdf13 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A-Sunil Seksaria.pdf13 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A-Divyesh Seksaria.pdf2 Jan 2023
Copy of the legal title reportFile: Legal Title Report New.pdf28 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Veda II Final New.pdf26 Dec 2022
Layout approvalFile: Gokhiware Layout Highlighted.pdf13 Dec 2022
Building plan approvalFile: E Wing Sheet 1_compressed_organized_compressed_compressed.pdf13 Dec 2022
Building plan approvalFile: E Wing Sheet 2_compressed_organized.pdf13 Dec 2022
Building plan approvalFile: organized.pdf13 Dec 2022
Building plan approvalFile: G Wing organized.pdf13 Dec 2022
Building plan approvalFile: J wing organized.pdf13 Dec 2022
PAN CardFile: JSB Home Makers PAN Card.pdf13 Dec 2022
Details of encumbrances concerned to FinanceFile: Encumbrance Certificate.pdf13 Dec 2022
Details of encumbrances concerned to LegalFile: Encumbrance Certificate.pdf13 Dec 2022
Copy of Layout Approval (in case of layout)File: Gokhiware Layout Highlighted.pdf13 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: E Wing Sheet 1_compressed_organized_compressed_compressed.pdf13 Dec 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Sai Nakshatra TrridentSurvey No. 212 Hissa No. 1 at Vasai Virar City M Corp. Vasai Palghar 4013031OngoingDec 2024Dec 2024

How this compares with Palghar

49%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Nakshatra Veda II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Virar3,200+ in Palghar

2 kmNakshatra Veda IICompleted 20Lapsed / revoked 17Other 52Dot size: filed unitsN

Filed coordinates, straight-line distance. 89 registered projects within 2 km.

Builder: JSB HOMEMAKERS PVT LTD

JSB HOMEMAKERS PVT LTD has 2 registrations on MahaRERA, including Nakshatra Veda and Nakshatra Veda II. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if Nakshatra Veda II is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Nakshatra Veda II?

The registered promoter entity is JSB HOMEMAKERS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Nakshatra Veda II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Nakshatra Veda II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Nakshatra Veda II?

The professionals named in the filing: Architect: Sanat Mehta & Associates; Engineer: Deepak Kumar Singh; Chartered Accountant: Ritesh G Sharma & Co.; Chartered Accountant: PARTHKUMAR DHIRAJLAL PATEL; Chartered Accountant: Pranav Patel & Associates; Chartered Accountant: K.B. Mistry & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Nakshatra Veda II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Nakshatra Veda II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Nakshatra Veda II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.