Home / Browse projects / Thane, Maharashtra / Mukta Residency Phase 2

Registration lapsed No litigation declared Residential / Group Housing project

Mukta Residency Phase 2

By MUKTA DEVELOPERS

RG-MH-21147 · RERA P51700005154 · Last updated on MahaRERA portal: 15 Apr 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 2 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
43 of 55Construction stages doneacross 5 buildings; furthest along: Internal walls, 40%
0Complaints at MahaRERAon this registration
Jump to the 74 documents Report an error

Mukta Residency Phase 2 is a Residential / Group Housing project by MUKTA DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700005154 on 10 Aug 2017. Possession was promised by 30 Dec 2023 and is now 34 months past that date.

At a glance

Project

  • NameMukta Residency Phase 2
  • TypeResidential / Group Housing
  • Location
    • Kalyan Shill Road
    • Khidkali
    • Thane (M Corp.)
    • Thane
    • 421204
  • Pincode421204
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700005154
  • ReraGenie IDRG-MH-21147

Builder

  • NameMUKTA DEVELOPERS
  • Entity typePartnership
  • PartnersPRAVIN SAKHARAM PATIL, KISHORE SAKHARAM PATIL
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

34 months past promisethis monthRegisteredAug 2017PromisedDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on10 Aug 2017
  • Promised completion30 Dec 2023
  • Revised completionNone
  • Buildings5 building records
  • Documents filed74 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B-1 ZINIANA260000
B-2 FRESSIANA260000
C-1 POLICE STATIONNA80000
C-2 MUKTA HOUSENA70000
A1 BunglowNA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 15 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

43 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Internal walls, at 40%.

B-1 ZINIA91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B-2 FRESSIA91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C-1 POLICE STATION91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C-2 MUKTA HOUSE82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A1 Bunglow42%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 15 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed157

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots157
Closed/Covered130
Open Space27
BuildingClosed/CoveredOpen SpaceTotal
B-1 ZINIA55358
B-2 FRESSIA55358
C-1 POLICE STATION101323
C-2 MUKTA HOUSE10818

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,615 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI11685.29
Proposed, not sanctioned10,617 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMG ROAD THANE WEST

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr. Sameer S. Lotke
EngineerMr.Rajesh Patil
PartnerRole in project
MUKTA DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed74

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 - Mukta Residency Phase 2 - Q1 22-23.pdf15 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 - Mukta Residency Phase 2 - Q2 22-23.pdf15 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 - Mukta Residency Phase 3 - Q1 22-23.pdf15 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 - Mukta Residency Phase 4 - Q1 22-23.pdf15 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 - Mukta Residency Phase 2 - Q3 23-24.pdf15 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 - Mukta Residency Phase 2 - Q4 23-24.pdf15 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Mukta Residency Phase 2 Form 2 Q2 22-23.pdf15 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Mukta Residency Phase 2 Form 2 Q3 22-23.pdf15 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate Mukta Residency Phase 2 Form 2A FY 22-23.pdf15 Apr 2024
Disclosure of sold/ booked inventoryFile: Mukta Residency Ph 2 Disclosure of Sold-Unsold Inventory Q2 23-24.pdf15 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate Mukta Residency Phase 2 Form 2A FY 23-24.pdf1 Apr 2024
Disclosure of sold/ booked inventoryFile: Mukta Residency Phase 2 Disclosure of Sold-Unsold Inventory Q3 23-24.pdf1 Apr 2024
Certificates of CA (Form 3)File: 1 MD - Form-3 as on 30 Jun 21.pdf30 Mar 2024
Certificates of CA (Form 3)File: 2 MD - Form-3 as on 30 Sept 21.pdf30 Mar 2024
Certificates of CA (Form 3)File: 3 MD - Form-3 as on 31 Dec 21.pdf30 Mar 2024
Certificates of CA (Form 3)File: 4 MD - Form-3 as on 31 Mar 22.pdf30 Mar 2024
Certificates of CA (Form 3)File: 5 MD - Form-3 as on 30 Jun 22.pdf30 Mar 2024
Certificates of CA (Form 3)File: 6 MD - Form-3 as on 30 Sept 22.pdf30 Mar 2024
Certificates of CA (Form 3)File: 7 MD - Form-3 as on 31 Dec 22.pdf30 Mar 2024
Certificates of CA (Form 3)File: 8 MD - Form-3 as on 31 Mar 23.pdf30 Mar 2024
Certificates of CA (Form 3)File: 9 MD - Form-3 as on 30 Jun 23.pdf30 Mar 2024
Certificates of CA (Form 3)File: 10 MD - Form-3 as on 30 Sept 23.pdf30 Mar 2024
Certificates of CA (Form 3)File: 11 MD - Form-3 as on 31 Dec 23.pdf30 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: MD - Form 5 - F Y 21-22.pdf30 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: MD - Form 5 - F Y 22-23.pdf30 Mar 2024
Certificates of CA (Form 3)File: CA Certificate Form-3 FY 17-18.pdf25 May 2023
Certificates of CA (Form 3)File: CA Certificate Form-3 FY 18-19.pdf25 May 2023
Certificates of CA (Form 3)File: CA Certificate Form-3 FY 19-20.pdf25 May 2023
Certificates of CA (Form 3)File: CA Certificate Form-3 FY 20-21.pdf25 May 2023
Certificates of CA (Form 5)File: CA Certificate Form-3 FY 17-18.pdf25 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 - Mukta Residency Phase 2 - FY 17-18.pdf19 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 - Mukta Residency Phase 2 - FY 18-19.pdf19 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 - Mukta Residency Phase 2 - FY 19-20.pdf19 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 - Mukta Residency Phase 2 - FY 20-21.pdf19 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 - Mukta Residency Phase 2 - Q1 21-22.pdf19 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 - Mukta Residency Phase 2 - Q2 21-22.pdf19 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 - Mukta Residency Phase 2 - Q3 21-22.pdf19 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 - Mukta Residency Phase 2 - Q4 21-22.pdf19 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Form 2 FY 31-03-2018.pdf9 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Form 2 FY 31-03-2019.pdf9 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Form 2 FY 31-03-2020.pdf9 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Form 2 FY 31-03-2021.pdf9 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Form 2 Q1 21-22.pdf9 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Form 2 Q2 21-22.pdf9 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Form 2 Q3 21-22.pdf9 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Form 2 Q4 21-22.pdf9 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate Mukta Residency Phase 2 Form 2A FY 21-22.pdf9 May 2023
Declaration about Commencement CertificateFile: Format D Declaration about Commencement Certificate.pdf7 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A - Quality Assurance Certificate.pdf7 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - Quality Assurance Certificate.pdf7 Jun 2022
Disclosure of sold/ booked inventoryFile: Mukta Residency Phase II Disclosure of Sold-Unsold Inventory.pdf7 Jun 2022
CERSAI detailsFile: CERSAI Search Report - Asset Based.pdf7 Jun 2022
CERSAI detailsFile: CERSAI Search Report - Debtors Based.pdf7 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - Phase II.pdf3 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Mukta.pdf19 Feb 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Mukta Developers Form 5.pdf18 Dec 2019
Certificates of CA (Form 5)File: Form 5 - Phase II.pdf15 Oct 2018
Proforma of Allotment letterFile: MZ RERA Draft Agreement.pdf7 May 2018
Declaration in FORM BFile: Mukta Residency Phase II.pdf1 Mar 2018
Building plan approvalFile: Building Plan Approval- Final.pdf30 Jul 2017
Building Plan Approval (IOD)File: Building Plan Approval- Final.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Mukta Phese 2.pdf30 Jul 2017
Proforma of Allotment letterFile: Mukta Agreement to sell.pdf30 Jul 2017
OtherFile: Mukta Residency Phase II Project Note.pdf30 Jul 2017
Declaration in FORM BFile: Mukta Residency Phase II.pdf29 Jul 2017
Certificates of CA (Form 3)File: CA Certificate-Mukta Phase 2.pdf29 Jul 2017
Layout approvalFile: Sanction Layout Plan B-1 B-2 C-1 C-2.pdf28 Jul 2017
PAN CardFile: Mukta Developers Pan Card.pdf28 Jul 2017
Copy of the legal title reportFile: TITLE CERTI 112-2A_0001(1).pdf28 Jul 2017
Details of encumbrancesFile: Declaration cum no Encumbrances Mukta Residency Phase II B-1 B-2 C-1 C-2.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: Sanction Layout Plan B-1 B-2 C-1 C-2.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC COPY.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate B-1 B-2 C-1 C-2.pdf28 Jul 2017
Proforma of Allotment letterFile: Allotment Letter B-1 B-2 C-1 C-2.pdf28 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
MUKTA RESIDENCY ASTER A-1Mukta Residency Next To Regent Honda Showroom Near Lodha Palava Kalyan Shill Road Khidkali Thane West 42120424CompletedMay 2016May 2016
MUKTA RESIDENCY LILAC B-4Mukta Residency Next To Regent Honda Showroom Near Lodha Palava Kalyan Shill Road Khidkali Thane w 421 20428CompletedJun 2015Jun 2015

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Mukta Residency Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Khidkali7,600+ in Thane

2 kmMukta Residency Phase 2Completed 44Lapsed / revoked 10Other 44Dot size: filed unitsN

Filed coordinates, straight-line distance. 98 registered projects within 2 km.

Builder: MUKTA DEVELOPERS

MUKTA DEVELOPERS has 3 registrations on MahaRERA, including A-2 MARIGOLD and Mukta Residency Phase 2. Its filings disclose 4 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that Mukta Residency Phase 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Mukta Residency Phase 2 is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Mukta Residency Phase 2?

The registered promoter entity is MUKTA DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Mukta Residency Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Mukta Residency Phase 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Mukta Residency Phase 2?

The professionals named in the filing: Architect: Mr. Sameer S. Lotke; Engineer: Mr.Rajesh Patil. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mukta Residency Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mukta Residency Phase 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mukta Residency Phase 2 to a free account