ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Montclaire

Registration lapsed No litigation declared Commercial project

Montclaire

By Niraj Kumar Associates Pvt Ltd

RG-MH-19810 · RERA P52100010610 · Last updated on MahaRERA portal: 28 Jul 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 3 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
8 of 11Construction stages donefurthest along: Basement (if any), 98%
3Complaints at MahaRERAon this registration
Jump to the 240 documents Report an error

Montclaire is a Commercial project by Niraj Kumar Associates Pvt Ltd in Pune, Maharashtra, registered with MahaRERA as P52100010610 on 31 Aug 2017. Possession was promised by 25 Dec 2024 and is now 22 months past that date. The completion date has moved by 12 months from the original filing. 3 complaints are on record with the regulator.

At a glance

Project

  • NameMontclaire
  • TypeCommercial
  • Location
    • Baner-Pashan Link Rd
    • Baner-Pashan
    • Pashan
    • Haveli
    • Pune
    • 411021
  • Pincode411021
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100010610
  • ReraGenie IDRG-MH-19810

Builder

  • NameNiraj Kumar Associates Pvt Ltd
  • Entity typeCompany
  • CINU45209MH1995PTC094283
  • Managing DirectorJayant Vallabhdas Kaneria
  • Other registrations6 more →
  • Completed5 of 7
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

22 months past promisethis monthRegisteredAug 2017First promiseDec 2023Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Aug 2017
  • Promised completion25 Dec 2024
  • Revised completionRevised to 25 Dec 2024 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed240 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MontclaireNA320000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 28 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 98%.

Montclaire: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)98%
Podiums (if any)100%
Plinth98%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 28 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes96%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes96%
Street LightingYes100%
Community BuildingsYes85%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceYes95%
Open ParkingNoNot applicable
No swimming poolNoNot applicable

Parking filed300

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots300
Closed/Covered300

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area13,750 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityPMC
Permissible FSI34545.0
Proposed, not sanctioned25,889 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchManekji wadia bldg ground floor nanik motwani marg fort Mumbai Maharashtra 400001

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVikas Achalkar
EngineerJW Consultant
PartnerRole in project
Niraj Kumar Associates Pvt Ltd-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100018179Dec 2023 → Dec 2024

Reason as filed by the promoterThe validity of current registration is up to 30/12/2023. However, due to prolonged monsoon and unseasonal rain showers the peripheral work including excavation for underground water tank, Sewage treatment plant (STP), drainage lines and foundation work for multi-level mechanical parking got delayed. For the same reason, the water proofing of top terrace, external façade installation got delayed by at least 4-5 months due to wet ground conditions. In addition, the approvals took longer than anticipated time. Also approval from MPCB and process of completion from corporation which used to run p

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC005000000095863Mr. Sandeep Subashchandra MehtaNiraj Kumar Associates Pvt Ltd07/08/2021
CC005000000441103Amit Ramesh ChavanNiraj Kumar Associates PVT LTD04/07/2024
CC12400092Niraj Kumar Associates Pvt LtdSandeep Subhashchandra Mehta13/09/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Sep 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 21 Oct 2024

Documents filed240

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 240 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Montclair June 2025.pdf28 Jul 2025
Certificates of CA (Form 3)File: Form 3 Mont Claire June 2025 sign_compressed.pdf28 Jul 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 MONTCLAIRE June 2025.pdf28 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 01 Montclaire March 2025.pdf11 Apr 2025
Certificates of CA (Form 3)File: FORM 3 NKAPL MONTCLAIRE MARCH 2025 (1).pdf11 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 MONTCLAIRE COMMER MARCH 2025.pdf11 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Claire March 2025.pdf11 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD MONTCLAIRE DEC 2024.pdf9 Jan 2025
Certificates of CA (Form 3)File: form 3 Montclaire Dec 2024.pdf8 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec 2024 Montclaire.pdf4 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 MONTCLAIRE DECEMBER 2024.pdf4 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Montclaire for Sept 2024 rectified.pdf4 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Montclaire RERA 2023-2024.pdf21 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Montclaire Dec 2023.pdf21 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Montclaire March 2024.pdf21 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Montclaire June 2024.pdf21 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Montclaire Sept 2024.pdf21 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Montclaire Dec 2023.pdf21 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Montclaire March 2024.pdf21 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Montclaire June 2024.pdf21 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Montclaire Sept 2024.pdf21 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Montclaire RERA 2023-2024.pdf21 Nov 2024
Certificates of CA (Form 3)File: form 3 Montclaire 30-09-2024_compressed.pdf22 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 MONTCLAIRE 30 sep 24.pdf22 Oct 2024
Disclosure of sold/ booked inventoryFile: Mont Clair Sold Unsold .pdf22 Oct 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: Montclaire society registration certificate.pdf21 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Ground and first Commercial Completion .pdf21 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Montclaire PART COMPLETION offices.pdf21 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Mont Claire Form 5 2023 2024.pdf7 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 MONTCLAIRE June 2024.pdf13 Aug 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold MONTCLAIREJune 2024.pdf13 Aug 2024
Certificates of CA (Form 3)File: Form 3 Montclaire June 2024.pdf13 Aug 2024
Certificates of CA (Form 3)File: form 3 Montclaire March 2024_compressed.pdf14 Jun 2024
Disclosure of sold/ booked inventoryFile: MONTCLAIRE.pdf30 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 MONTCLAIRE000.pdf15 May 2024
Disclosure of sold/ booked inventoryFile: NKAPL MONTCLAIRE.pdf8 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Montclaire Form 2 Dec 2023.pdf20 Jan 2024
Certificates of CA (Form 3)File: Montclaire Form 3 Dec 2023.pdf20 Jan 2024
Declaration in FORM BFile: Revised Form B Montclaire NKAPL Dec 12 2023.pdf12 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Montclaire Form 1 June 2023.pdf8 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Montclaire Form 1 Sept 2023.pdf8 Dec 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Montclaire declaration society formation.pdf8 Dec 2023
Details of encumbrances concerned to FinanceFile: Legal encumbrances.pdf6 Dec 2023
Details of encumbrances concerned to LegalFile: Legal encumbrances.pdf6 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Montclaire Form 2A FY 2022-2023.pdf6 Dec 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory 30-9-23 MONTCLAIRE.pdf6 Dec 2023
Certificates of CA (Form 3)File: MONTCLAIRE FORM 3 Sept 2023 signed.pdf6 Dec 2023
Proforma of Agreement for saleFile: Montclaire Agreement Draft.pdf6 Dec 2023
Proforma of Agreement for saleFile: Montclaire Agreement Draft part 2.pdf6 Dec 2023
Certificates of CA (Form 3)File: Form 3 Montclaire June 2023.pdf5 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 Montclaire.pdf28 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 MONTCLAIRE June 2023.pdf9 Nov 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory 30-6-23 KINGSTOWN RESI.pdf9 Nov 2023
Certificates of CA (Form 3)File: Form 3 MontClaire Mar 23.pdf25 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 MontClaire Mar 23 Qtr.pdf18 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 MontClaire Mar 23 Qtr.pdf8 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A MonClaire Mar 23.pdf8 Apr 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory MontClaire Mar 23.pdf8 Apr 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Montclaire Latest RERA certificate Match 2023 after cost update.pdf20 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A MontClaire Mar 20.pdf28 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A MontClaire Mar 21.pdf28 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A MontClaire 21 22.pdf28 Feb 2023
Certificates of CA (Form 3)File: Form 3 MontClaire Dec 22.pdf27 Feb 2023
Certificates of CA (Form 3)File: Form 3 MontClaire Mar 22.pdf22 Feb 2023
Building plan approvalFile: HPSCANNER4210_compressed.pdf20 Feb 2023
Building plan approvalFile: HPSCANNER4211_compressed.pdf20 Feb 2023
Building plan approvalFile: HPSCANNER4212_compressed.pdf20 Feb 2023
Building plan approvalFile: HPSCANNER4213_compressed.pdf20 Feb 2023
Building plan approvalFile: HPSCANNER4214_compressed.pdf20 Feb 2023
Building plan approvalFile: HPSCANNER4215_compressed.pdf20 Feb 2023
Building plan approvalFile: HPSCANNER4216_compressed.pdf20 Feb 2023
Building plan approvalFile: HPSCANNER4217_compressed.pdf20 Feb 2023
Building plan approvalFile: HPSCANNER4218_compressed.pdf20 Feb 2023
Building plan approvalFile: HPSCANNER4219_compressed.pdf20 Feb 2023
Building plan approvalFile: HPSCANNER4220_compressed.pdf20 Feb 2023
Building plan approvalFile: HPSCANNER4221_compressed.pdf20 Feb 2023
Building plan approvalFile: HPSCANNER4222_compressed.pdf20 Feb 2023
Building plan approvalFile: HPSCANNER4223_compressed.pdf20 Feb 2023
Building plan approvalFile: HPSCANNER4224_compressed.pdf20 Feb 2023
Building plan approvalFile: HPSCANNER4225_compressed.pdf20 Feb 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Avion1401A Pashan-Sus Rd Pashan93CompletedDec 2017Late, Jul 2018

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Montclaire on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Baner-Pashan13,700+ in Pune

2 kmMontclaireCompleted 105Lapsed / revoked 35Other 135Dot size: filed unitsN

Filed coordinates, straight-line distance. 275 registered projects within 2 km.

Builder: Niraj Kumar Associates Pvt Ltd

Niraj Kumar Associates Pvt Ltd has 7 registrations on MahaRERA, including Mont Vert Avion and Mont Vert Velocity. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Montclaire shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Montclaire is delayed beyond 25 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Montclaire?

The registered promoter entity is Niraj Kumar Associates Pvt Ltd, a company as per the filing. Its CIN U45209MH1995PTC094283 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Montclaire?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Montclaire?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Montclaire?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Montclaire?

The professionals named in the filing: Architect: Vikas Achalkar; Engineer: JW Consultant. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Montclaire?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Montclaire. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Montclaire to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.