Home / Browse projects / Mumbai Suburban, Maharashtra / MONTANA PHASE - 3

Registered No litigation declared Residential / Group Housing project

MONTANA PHASE - 3

By LOHITKA PROPERTIES LLP

RG-MH-43628 · RERA P51800017754 · Last updated on MahaRERA portal: 13 May 2026

Source: official MahaRERA filing

Red flags

  • 12 complaints at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 24 months from the original
11 of 11Construction stages doneevery applicable stage filed complete
3 of 332Units unsoldnot recorded sold or booked
12Complaints at MahaRERAon this registration
Jump to the 122 documents Report an error

MONTANA PHASE - 3 is a Residential / Group Housing project by LOHITKA PROPERTIES LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800017754 on 11 Sep 2018. Possession is promised by 29 Dec 2026. The completion date has moved by 24 months from the original filing. 329 of the 332 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete. 12 complaints are on record with the regulator.

At a glance

Project

  • NameMONTANA PHASE - 3
  • TypeResidential / Group Housing
  • Location
    • LBS ROAD
    • MULUND WEST
    • Kurla
    • Mumbai Suburban
    • 400080
  • Pincode400080
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800017754
  • ReraGenie IDRG-MH-43628

Builder

  • NameLOHITKA PROPERTIES LLP
  • Entity typePartnership
  • Other registrations3 more →
  • Completed1 of 4
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects10 →

Key dates

this monthRegisteredSep 2018First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Sep 2018
  • Promised completion29 Dec 2026
  • Revised completionRevised to 29 Dec 2026 (originally 30 Dec 2024)
  • Buildings1 building record
  • Documents filed122 files

Current status

99%329 of 332 units booked
100.0%Work done, per cost certificate

Figures as on 13 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GIONANA54433320332

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

GIONA: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 13 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes30%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed702

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots702
Closed/Covered702

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area9,102 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Sep 2024

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI33811.69
Proposed, not sanctioned10,706 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHIVDHAM COMPLEX DINDOSHI ONKAR CHS, GEN A K VAIDYA MARG, DINDOSHI MUMBAI - 97
Estimated costRs 181.76 cr
Cost incurredRs 181.72 cr
Work done99.98%
BuildingWingEstimatedIncurred
GIONANARs 169.14 crRs 169.14 cr
-NARs 12.62 crRs 12.58 cr

Certifying professionals and partners11

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAAKAR ARCHITECTS AND CONSULTANTS
ArchitectSANDEEP SHIKRE AND ASSOCIATES
ArchitectSandeep Shirke & Associates
EngineerSMARTY LACHHWANI
EngineerSterling engineering consultancy services pvt ltd
EngineerSHANKAR DALVI
EngineerMuhammad Shoeb Chouhan
EngineerGorakh N Patil
EngineerHameed Khalid Mirza
Chartered AccountantHaresh Bhanushali & Associates
Chartered AccountantM. B. Agrawal & Co.
PartnerRole in project
LOHITKA PROPERTIES LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800025742Dec 2024 → Dec 2026

Reason as filed by the promoter1. The applicant has completed super structure in respect of both wings being wing A and B of the said project till terrace floors and overhead tanks. Further the building has been roughly completed upto 40% and the applicant should be able to obtain OC for the said project within 1 year of the extension being sought. 2. In light of the factors mentioned above, the applicant is should be able to complete the construction of the said Project within the timeline as provided above i.e. by 29.12.2025. 3. The applicant however submits that it has bonafide intention and strong hope that the project

Complaints filed with MahaRERA12

Case no.ComplainantRespondentFiled
CC006000000057788CHARAN TRIMBAK PATILSHETH DEVLOPERS PRIVATE LIMITED24/01/2019
CC006000000194882Mangesh Krishna Zagadechintan sheth11/11/2020
CC006000000197492SRIKANT KRISHNAMOORTHYLOHITKA PROPERTIES LLP05/07/2021
CC12600790Pratap BhanushaliLOHITKA PROPERTIES LLP11/02/2026
CC12600841Pranav Prafull ChhedaLOHITKA PROPERTIES LLP14/02/2026
CC12600842shodan vitthal shettyLOHITKA PROPERTIES LLP14/02/2026
CC12600850Deepali nirav gajraLOHITKA PROPERTIES LLP15/02/2026
CC12600947Kapil DalviLOHITKA PROPERTIES LLP21/02/2026
CC12601221pramod waghamodeLOHITKA PROPERTIES LLP06/03/2026
CC12601239priyanka chandnaniLOHITKA PROPERTIES LLP07/03/2026
CC12602000Arun AdakLOHITKA PROPERTIES LLP04/04/2026
CC12604339Elton Christopher DsilvaLOHITKA PROPERTIES LLP11/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Sep 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Sep 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 May 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 May 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 29 Dec 2026

Documents filed122

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 122 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Building plan approvalFile: Amended Letter_signed dtd-20032023.pdf13 May 2026
Building plan approvalFile: Drawing20032023-1-1.pdf13 May 2026
Building plan approvalFile: Drawing20032023-1-2.pdf13 May 2026
Building plan approvalFile: Drawing20032023-2.pdf13 May 2026
Building plan approvalFile: Drawing20032023-3.pdf13 May 2026
Building plan approvalFile: Drawing20032023-4.pdf13 May 2026
Commencement certificateFile: 2493517_GIONAOC_signed.pdf13 May 2026
Withdrawal Update Form 1File: GionaForm-1.pdf13 May 2026
Withdrawal Update Form 2File: MONTANA PH 3.pdf13 May 2026
Withdrawal Update Form 3File: Form - 3_Giona_Mar 26.pdf13 May 2026
Withdrawal Update Form 1File: form 1 montana ph 3.pdf28 Jan 2026
Withdrawal Update Form 2File: MONTANA PHASE-3.pdf28 Jan 2026
Withdrawal Update Form 3File: Form-3_Giona_Dec 25_Signed.pdf28 Jan 2026
Withdrawal Update Form 1File: Rorm - A - Giona wing AB 27-10-25.pdf29 Nov 2025
Withdrawal Update Form 2File: FORM 2 - MONTANA PHASE-3.pdf29 Nov 2025
Withdrawal Update Form 3File: Form - 3_Giona_Sept 2025_Signed.pdf29 Nov 2025
Form 5 (FY 2024-2025)File: Form - 5_Giona_2024-25-Signed.pdf25 Nov 2025
Withdrawal Update Form 1File: Form 1 Giona.pdf10 Nov 2025
Withdrawal Update Form 2File: Form - 2 Giona.pdf10 Nov 2025
Withdrawal Update Form 3File: Form - 3 Giona.pdf10 Nov 2025
Form 2A (FY 2024-2025)File: FORM-2A - Montana Phase 3.pdf5 Nov 2025
Disclosure of sold/ booked inventoryFile: GIONA.pdf5 May 2025
Montana PH 3 - Gionna29 Apr 2025
Certificates of CA (Form 3)File: FORM 3 -Montana.pdf29 Apr 2025
FORM 2 - Sheth Montana Giona29 Apr 2025
Disclosure of sold/ booked inventoryFile: MONTANA-GIONA.pdf22 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Gionna.pdf18 Jan 2025
Certificates of CA (Form 3)File: FORM-3- Giona.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 - Giona.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: MONTANA Giona-FORM 1-Architect Certificate.pdf29 Oct 2024
Certificates of CA (Form 3)File: Form - 3 Giona.pdf29 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 Giona.pdf29 Oct 2024
Disclosure of sold/ booked inventoryFile: MONTANA - GIONA.pdf29 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5 - MONTANA Ph-3 GIONA A, B.pdf7 Oct 2024
Disclosure of sold/ booked inventoryFile: GIONA.pdf1 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Gionna.pdf26 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM -2 -GIONA.pdf26 Jul 2024
Certificates of CA (Form 3)File: FORM -3 -GIONA.pdf26 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 1.pdf8 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2.pdf8 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 3.pdf8 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 4.pdf8 May 2024
Disclosure of sold/ booked inventoryFile: GIONA.pdf4 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Gionna.pdf30 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 - Giona.pdf22 Apr 2024
Certificates of CA (Form 3)File: FORM-3 - Montana Giona A B.pdf22 Apr 2024
Disclosure of sold/ booked inventoryFile: GIONA.pdf2 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Giona Tower.pdf16 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 - Giona.pdf16 Jan 2024
Certificates of CA (Form 3)File: Form - 3 - Giona.pdf16 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1) 1st quater.pdf7 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2) 2nd quater.pdf7 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 3) 3rd quater.pdf7 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 4) 4t quater.pdf7 Dec 2023
Disclosure of sold/ booked inventoryFile: GIONA.pdf27 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - Gionna.pdf18 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 - Giona.pdf18 Oct 2023
Certificates of CA (Form 3)File: Form - 3 - Giona.pdf18 Oct 2023
Certificates of CA (Form 3)File: Form - 3 - Giona.pdf18 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5 - MONTANA (GIONA A AND B).pdf8 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Montana Ph 3.pdf7 Aug 2023
Certificates of CA (Form 3)File: Form 3 Montana Ph 3.pdf7 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Montana Phase 3.pdf17 Jul 2023
Commencement Certificates / NA Order for plotted developmentFile: Amended CC.pdf25 Apr 2023
Declaration about Commencement CertificateFile: Declaration About Commencment Certificate Montana Phase 3 BldgNo10 C.pdf25 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Giona - Jan'23 - Mar'23.pdf24 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Giona A and B - Jan 23 to Mar 23.pdf24 Apr 2023
Disclosure of sold/ booked inventoryFile: Montana Phase 3 - Giona.pdf24 Apr 2023
Certificates of CA (Form 3)File: Form 3 - Giona A and B - Jan 23 to Mar 23.pdf24 Apr 2023
Disclosure of sold/ booked inventoryFile: Montana Ph 3.pdf23 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM - 2 GIONA.pdf18 Jan 2023
Certificates of CA (Form 3)File: FORM - 3 GIONA.pdf18 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GIONA BUILDING.pdf9 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - Montana Ph 3.pdf16 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Montana Ph 3.pdf14 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Montana - Ph 3 Giona.pdf5 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Montana Ph 3.pdf25 Oct 2022
Certificates of CA (Form 3)File: From - 3 Montana Ph 3 Sept 2022.pdf25 Oct 2022
Disclosure of sold/ booked inventoryFile: Montana Giona.pdf19 Oct 2022
Certificates of CA (Form 3)File: Montana - Giona.pdf29 Sep 2022

Promoter's earlier projects10

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise7 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
MONTANA PHASE - 1P51800000735MULUND, Mumbai Suburban300Jul 2017CompletedDec 2023Feb 2023
SIGMAZANDU PHARMACTICAL GOKHALE ROAD SOUTH DADAR W MUMBAI - 25260-CompletedJul 2014Late, Dec 2014
VIVIANA MALLViviana Mall Voltas Compound Pokharan Rd No 2 Majiwade Thane w 400601240-CompletedMay 2013May 2013
Vasant LawnsVasant Lawns Voltas Compound Pokharan Rd No 2 Majiwade Thane w 400601465-CompletedMar 2012Late, Nov 2013
BEAUMONDEAPPASAHEB MARATHE MARG PRABHADEVI MUMBAI 25196-CompletedDec 2011Late, Jan 2012
VASANT MARVELWESTRN EXPRESS HIGHWAY BORIWALI EAST MUMBAI - 66641-CompletedOct 2011Late, Jul 2012
CYNERGYAPPASAHEB MARATHE MARG PRABHADEVI MUMBAI 2533-CompletedSep 2011Jul 2011
VASANT GALAXYJUNCTION OF MG ROAD AND LINK ROAD BANGUR NAGAR GOREGAON WEST MUMBAI803-CompletedOct 2010Late, Mar 2011
VASANT VALLEYMALAD EAST MUMBAI 96127-CompletedJun 2010Late, Dec 2010
VASANT GARDENSWAPNA NAGARI OFF LBS MARG MULUND WEST MUMBAI 801,825-CompletedMar 2007Late, Dec 2007

How this compares with Mumbai Suburban

99%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MONTANA PHASE - 3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MULUND WEST6,700+ in Mumbai Suburban

2 kmMONTANA PHASE - 3Completed 92Lapsed / revoked 56Other 113Dot size: filed unitsN

Filed coordinates, straight-line distance. 261 registered projects within 2 km.

Builder: LOHITKA PROPERTIES LLP

LOHITKA PROPERTIES LLP has 4 registrations on MahaRERA, including MONTANA PHASE - 1 and MONTANA PHASE - 2. Its filings disclose 10 earlier MahaRERA projects: declares 3 of 10 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if MONTANA PHASE - 3 is delayed beyond 29 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MONTANA PHASE - 3?

The registered promoter entity is LOHITKA PROPERTIES LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MONTANA PHASE - 3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MONTANA PHASE - 3?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MONTANA PHASE - 3?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MONTANA PHASE - 3?

The professionals named in the filing: Architect: AAKAR ARCHITECTS AND CONSULTANTS; Architect: SANDEEP SHIKRE AND ASSOCIATES; Architect: Sandeep Shirke & Associates; Engineer: SMARTY LACHHWANI; Engineer: Sterling engineering consultancy services pvt ltd; Engineer: SHANKAR DALVI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MONTANA PHASE - 3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MONTANA PHASE - 3. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MONTANA PHASE - 3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.