ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / MONTANA PHASE - 2

Registration lapsed No litigation declared Residential / Group Housing project

MONTANA PHASE - 2

By LOHITKA PROPERTIES LLP

RG-MH-84973 · RERA P51800014539 · Last updated on MahaRERA portal: 20 Jan 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 2 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
6 of 11Construction stages donefurthest along: Staircases, 95%
2Complaints at MahaRERAon this registration
Jump to the 81 documents Report an error

MONTANA PHASE - 2 is a Residential / Group Housing project by LOHITKA PROPERTIES LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800014539 on 8 Dec 2017. Possession was promised by 30 Dec 2024 and is now 22 months past that date. 2 complaints are on record with the regulator.

At a glance

Project

  • NameMONTANA PHASE - 2
  • TypeResidential / Group Housing
  • Location
    • LBS ROAD
    • MULUND
    • Kurla
    • Mumbai Suburban
    • 400080
  • Pincode400080
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800014539
  • ReraGenie IDRG-MH-84973

Builder

  • NameLOHITKA PROPERTIES LLP
  • Entity typePartnership
  • Other registrations3 more →
  • Completed1 of 4
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects10 →

Key dates

22 months past promisethis monthRegisteredDec 2017PromisedDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on8 Dec 2017
  • Promised completion30 Dec 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed81 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SIERRANA450000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 95%.

SIERRA: 94% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%

Progress on shared amenities19

As on 20 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes60%
Water SupplyYes75%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes50%
Street LightingYes25%
Community BuildingsYes25%
Treatment And Disposal Of Sewage And Sullage WaterYes72%
Solid Waste Management And DisposalYes55%
Water conservation /Rain water harvestingYes60%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes75%
Electrical meter room, sub-station, receiving stationYes75%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable
TENNIS COURTYes0%
SWIMMING POOLYes0%
MULTI PURPOSE HALLYes0%
FITNESS CENTREYes0%

Parking filed378

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots378
Closed/Covered378

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,551 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI28691.0
Proposed, not sanctioned23,256 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDINDOSHI ONKAR BUILDING MUMBAI 97

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
LOHITKA PROPERTIES LLP-

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000078198Mr. Jimit B. Mehta & Mr. Bipinchandra S. MehtaLohitka Properties LLP21/02/2019
CC12400420Leena ThakkerLOHITKA PROPERTIES LLP16/10/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Oct 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Oct 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Jun 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Dec 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed81

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 81 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 with full OC.pdf20 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 1.pdf8 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2.pdf8 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 3.pdf8 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 4.pdf8 May 2024
Disclosure of sold/ booked inventoryFile: SIERRA.pdf4 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Sierra.pdf30 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 - Sierra of Sheth Montana.pdf22 Apr 2024
Certificates of CA (Form 3)File: FORM-3 - Montana Sierra C.pdf22 Apr 2024
Disclosure of sold/ booked inventoryFile: SIERRA.pdf2 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Sierra.pdf16 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Sieera.pdf16 Jan 2024
Certificates of CA (Form 3)File: Form 3 - Sierra.pdf16 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1) 1st quater.pdf7 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2) 2nd quater.pdf7 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 3) 3rd quater.pdf7 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 4) 4th quater.pdf7 Dec 2023
Disclosure of sold/ booked inventoryFile: SIERRA.pdf27 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 -Sierra.pdf18 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 - Sierra.pdf18 Oct 2023
Certificates of CA (Form 3)File: Form - 3 - Sierra.pdf18 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5 - MONTANA (SIERRA-WING C).pdf8 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Montana Ph 2.pdf7 Aug 2023
Certificates of CA (Form 3)File: Form 3 Montana Ph 2.pdf7 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Montana Phase 2.pdf17 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Sierra - Jan'23 - Mar'23.pdf24 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 -Sierra - Jan 23 to Mar 23.pdf24 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Montana Ph 2 Jan 23 to Mar 23.pdf24 Apr 2023
Disclosure of sold/ booked inventoryFile: Montana Phase 2 - Sierra.pdf24 Apr 2023
Certificates of CA (Form 3)File: Form 3 - Sierra - Jan 23 to Mar 23.pdf24 Apr 2023
Disclosure of sold/ booked inventoryFile: Montana Ph 2.pdf23 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM - 2 SIERRA.pdf18 Jan 2023
Certificates of CA (Form 3)File: FORM - 3 SIERRA.pdf18 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SIERA BUILDING.pdf9 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - Montana Ph 2.pdf16 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Montana Ph 2.pdf14 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Montana - Ph 2 Siearra.pdf5 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Montana Ph 2.pdf25 Oct 2022
Certificates of CA (Form 3)File: From - 3 Montana Ph 2 Sept 2022.pdf25 Oct 2022
Certificates of CA (Form 3)File: Montana - Sieara.pdf29 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MONTANA SIERRA.PDF21 Jul 2022
Certificates of CA (Form 3)File: Montana Ph 2 March 22.pdf21 Jul 2022
Disclosure of sold/ booked inventoryFile: MONTANA SIERRA.pdf19 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sierra.pdf13 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MONTANA SIERRA.PDF13 Jun 2022
Details of encumbrancesFile: Montan encumberence details- update_31032022.pdf26 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Montana Ph 2.pdf26 Apr 2022
Disclosure of sold/ booked inventoryFile: MONTANA -SIERRA.PDF20 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: MONTANA-2.pdf12 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SIERRA RERA FORM2 - DEC 21.pdf27 Jan 2022
Disclosure of sold/ booked inventoryFile: Montana - Sierra.pdf25 Jan 2022
CERSAI detailsFile: Montana Ph 1 to 4 CERSAI modified.pdf17 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form5 Montana Ph 2_compressed.pdf17 Jan 2022
Certificates of CA (Form 3)File: Sierra_Form_3.pdf12 Jan 2022
Certificates of CA (Form 3)File: Sierra_Form_3.pdf11 Jan 2022
Declaration about Commencement CertificateFile: FORM d mONTANA PH 2.pdf7 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM_1_Architect_Certificate_-_MONTANA_(Siera)_04012022 (1).pdf7 Jan 2022
Proforma of Allotment letterFile: MONTANA-SIEARA.pdf28 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Montana Phase - 2.pdf10 Jun 2021
Building plan approvalFile: ROSA1.pdf3 Jun 2021
Building plan approvalFile: ROSA2.pdf3 Jun 2021
Building Plan Approval (IOD)File: ROSA1.pdf3 Jun 2021
Building Plan Approval (IOD)File: ROSA2.pdf3 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: MONTANA-PHASE-1 AND 2CC.pdf15 Dec 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: form 5 18-19 - Siara.pdf5 Mar 2020
Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf30 Oct 2019
Commencement Certificates / NA Order for plotted developmentFile: Rosa CC 2019 (2)_compressed.pdf21 Oct 2019
Certificates of CA (Form 5)File: Montana Phase-2.pdf24 Oct 2018
Details of encumbrancesFile: encumberence detail - update 1.pdf18 May 2018
Commencement Certificates / NA Order for plotted developmentFile: MONTANA PH2 CC.pdf23 Mar 2018
Declaration in FORM BFile: Form-B.pdf17 Oct 2017
Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE.PDF16 Oct 2017
Layout approvalFile: LAYOUT APPROVAL.pdf13 Oct 2017
Building plan approvalFile: IOD.pdf13 Oct 2017
PAN CardFile: PAN Card - LOHITKA PROP LLP.PDF13 Oct 2017
Copy of the legal title reportFile: LEAGAL TITLE REPORT.pdf13 Oct 2017
Details of encumbrancesFile: encumberence detail FINAL.pdf13 Oct 2017
Copy of Layout Approval (in case of layout)File: LAYOUT APPROVAL.pdf13 Oct 2017
Building Plan Approval (IOD)File: IOD.pdf13 Oct 2017
Proforma of Allotment letterFile: AGREEMENT FOR SALE Montana Phase 2.pdf13 Oct 2017

Promoter's earlier projects10

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise7 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
MONTANA PHASE - 1P51800000735MULUND, Mumbai Suburban300Jul 2017CompletedDec 2023Feb 2023
SIGMAZANDU PHARMACTICAL GOKHALE ROAD SOUTH DADAR W MUMBAI - 25260-CompletedJul 2014Late, Dec 2014
VIVIANA MALLViviana Mall Voltas Compound Pokharan Rd No 2 Majiwade Thane w 400601240-CompletedMay 2013May 2013
Vasant LawnsVasant Lawns Voltas Compound Pokharan Rd No 2 Majiwade Thane w 400601465-CompletedMar 2012Late, Nov 2013
BEAUMONDEAPPASAHEB MARATHE MARG PRABHADEVI MUMBAI 25196-CompletedDec 2011Late, Jan 2012
VASANT MARVELWESTRN EXPRESS HIGHWAY BORIWALI EAST MUMBAI - 66641-CompletedOct 2011Late, Jul 2012
CYNERGYAPPASAHEB MARATHE MARG PRABHADEVI MUMBAI 2533-CompletedSep 2011Jul 2011
VASANT GALAXYJUNCTION OF MG ROAD AND LINK ROAD BANGUR NAGAR GOREGAON WEST MUMBAI803-CompletedOct 2010Late, Mar 2011
VASANT VALLEYMALAD EAST MUMBAI 96127-CompletedJun 2010Late, Dec 2010
VASANT GARDENSWAPNA NAGARI OFF LBS MARG MULUND WEST MUMBAI 801,825-CompletedMar 2007Late, Dec 2007

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MONTANA PHASE - 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MULUND6,700+ in Mumbai Suburban

2 kmMONTANA PHASE - 2Completed 92Lapsed / revoked 55Other 114Dot size: filed unitsN

Filed coordinates, straight-line distance. 261 registered projects within 2 km.

Builder: LOHITKA PROPERTIES LLP

LOHITKA PROPERTIES LLP has 4 registrations on MahaRERA, including MONTANA PHASE - 1 and MONTANA PHASE - 2. Its filings disclose 10 earlier MahaRERA projects: declares 3 of 10 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that MONTANA PHASE - 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MONTANA PHASE - 2 is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MONTANA PHASE - 2?

The registered promoter entity is LOHITKA PROPERTIES LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MONTANA PHASE - 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MONTANA PHASE - 2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MONTANA PHASE - 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in MONTANA PHASE - 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MONTANA PHASE - 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MONTANA PHASE - 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.