Home / Browse projects / Pune, Maharashtra / MONTAGE

Registered No litigation declared Residential / Group Housing project

MONTAGE

By GOLDEN KALASH HOUSING LLP

RG-MH-98831 · RERA P52100052457 · Last updated on MahaRERA portal: 24 Apr 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 6 months
  • 1 extension taken
  • Rs 30.00 crore secured on the land, in favour of Bajaj Housing Finance Limited

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 6 months from the original
6 of 11Construction stages donefurthest along: Internal walls, 60%
31 of 120Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 80 documents Report an error

MONTAGE is a Residential / Group Housing project by GOLDEN KALASH HOUSING LLP in Pune, Maharashtra, registered with MahaRERA as P52100052457 on 8 Sep 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 6 months from the original filing. 89 of the 120 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameMONTAGE
  • TypeResidential / Group Housing
  • Location
    • Baner Pashan Link Road
    • Pashan
    • Haveli
    • Pune
    • 411021
  • Pincode411021
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100052457
  • ReraGenie IDRG-MH-98831

Builder

  • NameGOLDEN KALASH HOUSING LLP
  • Entity typePartnership
  • PartnersAKANKSHA VAIBHAV MITHARE, VISHAL VYAS, SUJIT ATMARAM KALE
  • Declared earlier projects1 →

Key dates

this monthRegisteredSep 2023First promiseJun 2026Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on8 Sep 2023
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2026)
  • Buildings1 building record
  • Documents filed80 files

Current status

74%89 of 120 units booked
47.0%Work done, per cost certificate

Figures as on 24 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1NA24231200120

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 60%.

1: 60% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed230

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots230
Closed/Covered230

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,981 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofBajaj Housing Finance Limited
Secured amountRs 30.00 crore
CERSAI search filedYes
Declared on3 Jun 2026

Approvals and building plan

Sanctioning authorityPMC
Permissible FSI19287.8
Proposed, not sanctioned8,534 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP 134/2/1/1, BANER LINK ROAD, PASHAN, PUNE 411021
Estimated costRs 112.88 cr
Cost incurredRs 53.07 cr
Work done47.01%
BuildingWingEstimatedIncurred
1NARs 107.88 crRs 50.87 cr
-NARs 5.00 crRs 2.20 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAR PRAKASH KANHEKAR
EngineerMR AVINASH CHANDRAKANT HARKAL
EngineerFidesto Projects Pvt Ltd
Chartered AccountantCA PRASAD RATHOD
Chartered AccountantPravin Pise
PartnerRole in project
GOLDEN KALASH HOUSING LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA23042620713Jun 2026 → Dec 2026

Reason as filed by the promoterThe project completion has been delayed due to circumstances beyond the control of the promoter. The project was adversely affected by delays in statutory approvals, disruption in availability of labor and construction materials, and interruptions caused by external factors. In addition, unforeseen administrative and operational challenges impacted the planned construction schedule. Despite these difficulties, the promoter has continued construction activities and remains fully committed to completing the project at the earliest. The extension is sought to ensure timely completion with require

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Aug 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Aug 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 2 Mar 2024

Documents filed80

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: Form 5 - FY 24-25.pdf24 Apr 2026
Withdrawal Update Form 1File: Form 1 - Mar 26.pdf23 Apr 2026
Withdrawal Update Form 2File: Form 2 - Mar 26.pdf23 Apr 2026
Withdrawal Update Form 3File: Form 3 - Mar 26.pdf23 Apr 2026
Withdrawal Update Form 1File: Form 1.pdf8 Apr 2026
Withdrawal Update Form 1File: Form 1.pdf8 Apr 2026
Withdrawal Update Form 1File: Form 1.pdf8 Apr 2026
Withdrawal Update Form 2File: Form 2 (2).pdf8 Apr 2026
Withdrawal Update Form 2File: Form 2 (2).pdf8 Apr 2026
Withdrawal Update Form 2File: Form 2 (2).pdf8 Apr 2026
Withdrawal Update Form 3File: Form 3 revised (1).pdf8 Apr 2026
Withdrawal Update Form 3File: Form 3 revised (1).pdf8 Apr 2026
Withdrawal Update Form 3File: Form 3 revised (1).pdf8 Apr 2026
Disclosure of Sold and Booked InventoryFile: Sold Inventory.pdf20 Oct 2025
Form 2File: QA Certificate.pdf20 Oct 2025
Form 1File: Arch Cert 12 th slab.pdf20 Oct 2025
Form 3File: Sold Inventory.pdf20 Oct 2025
Form 1File: Arch Cert 22 Slab and Tiling (1).pdf20 Oct 2025
Form 2File: QA Certificate.pdf20 Oct 2025
Form 3File: Form 3 Scan(1).pdf20 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Inventory.pdf20 Oct 2025
Disclosure of sold/ booked inventoryFile: Booking details of RERA.pdf2 Apr 2025
Building plan approvalFile: New Sanction Plan 1_compressed.pdf29 Mar 2025
Building plan approvalFile: New Sanction Plan 1_compressed.pdf29 Mar 2025
Building plan approvalFile: New Sanction Plan 2_compressed.pdf29 Mar 2025
Building plan approvalFile: New Sanction Plan 3_compressed.pdf29 Mar 2025
Building plan approvalFile: New Sanction Plan 4_compressed.pdf29 Mar 2025
Building plan approvalFile: New Sanction Plan 5_compressed.pdf29 Mar 2025
Building plan approvalFile: New Sanction Plan 6_compressed.pdf29 Mar 2025
Building plan approvalFile: New Sanction Plan_compressed.pdf29 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: New Sanction CC.pdf29 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: New Sanction Plan 1_compressed.pdf29 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: New Sanction Plan 1_compressed.pdf29 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: New Sanction Plan 2_compressed.pdf29 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: New Sanction Plan 3_compressed.pdf29 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: New Sanction Plan 4_compressed.pdf29 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: New Sanction Plan 5_compressed.pdf29 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: New Sanction Plan 6_compressed.pdf29 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: New Sanction Plan_compressed.pdf29 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate.pdf17 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate.pdf14 Aug 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory Disclosure.pdf14 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE RERA.pdf14 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2nd Slab Arch Cert-compressed.pdf1 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Details Certificate .pdf1 May 2024
Disclosure of sold/ booked inventoryFile: Apartments Booked RERA.pdf2 Mar 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 1st Slab Arch Cert.pdf2 Mar 2024
Proforma of Agreement for saleFile: Draft Agreement copy Montage.pdf30 Jan 2024
Other - LegalFile: Sale Deed Part 1.pdf29 Aug 2023
Other - LegalFile: Sale Deed Part 2.pdf29 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf28 Aug 2023
Copy of the legal title reportFile: final title for rera upload_compressed.pdf19 Aug 2023
Layout approvalFile: 5_6_7_merged.pdf17 Aug 2023
Copy of Layout Approval (in case of layout)File: 5_6_7_merged.pdf17 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect’s Certificate of Percentage of Completion of Work.pdf17 Aug 2023
CERSAI detailsFile: DELCARATION CERSAI.pdf17 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf16 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf16 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf16 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf16 Aug 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account details including no encumbrances on the Bank Account or no escrow o16 Aug 2023
Building plan approvalFile: 1.pdf11 Aug 2023
Building plan approvalFile: 2.pdf11 Aug 2023
Building plan approvalFile: 3.pdf11 Aug 2023
Building plan approvalFile: 4.pdf11 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: 1.pdf11 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: 2.pdf11 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: 3.pdf11 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: 4.pdf11 Aug 2023
Commencement Certificates / NA Order for plotted developmentFile: SKM_36723081112090.pdf11 Aug 2023
Declaration about Commencement CertificateFile: CC DELCARATION 1.pdf11 Aug 2023
Proforma of Agreement for saleFile: Final Model Agreement.pdf30 Jun 2023
PAN CardFile: Pan of Golden Kalash LLP.pdf16 Jun 2023
Details of encumbrances concerned to FinanceFile: DELCARATION OF ENCUMBRANCES.pdf16 Jun 2023
Details of encumbrances concerned to LegalFile: DELCARATION OF ENCUMBRANCES.pdf16 Jun 2023
Declaration in FORM BFile: FORM B.pdf16 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEERS CERTIFICATE AUG 2023.pdf16 Jun 2023
Proforma of Allotment letterFile: Allotment letter proforma.pdf16 Jun 2023
Deviation Report with respect to Allotment letterFile: No Deviation report allotment letter.pdf16 Jun 2023
Deviation Report with respect to model copy of AgreementFile: No Deviation report agreement to sale.pdf16 Jun 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationRegisteredStatusPromisedDelivered
TROVEP52100031289BANER, PuneOct 2021Certificate SignedSep 2023Late, Jun 2024

How this compares with Pune

74%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 6 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MONTAGE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pashan13,700+ in Pune

2 kmMONTAGECompleted 104Lapsed / revoked 35Other 133Dot size: filed unitsN

Filed coordinates, straight-line distance. 272 registered projects within 2 km.

Builder: GOLDEN KALASH HOUSING LLP

GOLDEN KALASH HOUSING LLP has 1 registration on MahaRERA, including MONTAGE. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if MONTAGE is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MONTAGE?

The registered promoter entity is GOLDEN KALASH HOUSING LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MONTAGE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MONTAGE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MONTAGE?

The professionals named in the filing: Architect: AR PRAKASH KANHEKAR; Engineer: MR AVINASH CHANDRAKANT HARKAL; Engineer: Fidesto Projects Pvt Ltd; Chartered Accountant: CA PRASAD RATHOD; Chartered Accountant: Pravin Pise. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MONTAGE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MONTAGE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MONTAGE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.