Mont Vert Axis
RG-MH-22992 · RERA P52100032943 · Last updated on MahaRERA portal: 10 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 30 months
- 1 extension taken
- Rs 240.00 crore secured on the land, in favour of Piramal Capital and Housing Finance Limited
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Mont Vert Axis is a Commercial project by Mont Vert Needs in Pune, Maharashtra, registered with MahaRERA as P52100032943 on 2 Feb 2022. Possession is promised by 31 Dec 2028. The completion date has moved by 30 months from the original filing. 87 of the 146 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.
At a glance
Project
- NameMont Vert Axis
- TypeCommercial
- Location
- Sr. No. 53
- Hissa No. 13/B/2
- 3
- 5
- 6
- 7(P)
- Bavdhan
- Bavadhan BK
- Mulshi
- Pune
- 411021
- Pincode411021
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100032943
- ReraGenie IDRG-MH-22992
Builder
- NameMont Vert Needs
- Entity typePartnership
- PartnersJayant Vallabhdas Kaneria, Kiran Ranjeet Nimhan, Kumar Ranjit Nimhan, Kaushal Ranjit Nimhan
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on2 Feb 2022
- Promised completion31 Dec 2028
- Revised completionRevised to 31 Dec 2028 (originally 30 Jun 2026)
- Buildings1 building record
- Documents filed133 files
Current status
Figures as on 10 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Mont Vert Axis | NA | 31 | 23 | 0 | 146 | 146 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 10 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 95%.
Mont Vert Axis: 18% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 95% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 10 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed227
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Mont Vert Axis | NA | Rs 47.46 cr | Rs 22.31 cr |
| - | NA | Rs 10.68 cr | Rs 5.66 cr |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vikas Achalkar AT consultants |
| Architect | AKRITI ASSOCIATE |
| Architect | Shrinivas V Kadkol |
| Engineer | G V Khasnis |
| Engineer | Rameshwar Bamodkar |
| Chartered Accountant | Ganesh Gundecha |
| Chartered Accountant | SAC AND CO LLP |
| Chartered Accountant | Priyanka Chordiya & Associates |
| Partner | Role in project |
|---|---|
| Mont Vert Needs | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1. Excavation took at least 8 months more due to unexpectedly hard rock strata and a weaker adjoining building on adjacent project, limiting us to use low intensity excavation equipment as an abundant precaution. 2. Revision of plan took 2 months more than expected. 3. We had to let go of a non-performing RCC contractor and hire a new contractor adding to 3 months of transition delays. 4. This project is a part of multiple projects in a basket funding with a financial institution(lenders). There is a default of loan payment of these loans. The financial institution has initiated proceedings un
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 1 Aug 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Jan 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 8 Aug 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed133
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 133 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Axis Form 1 Q1 2026.pdf | 10 Aug 2026 |
| Withdrawal Update Form 2File: FORM 2 AXIS June 2026.pdf | 10 Aug 2026 |
| Withdrawal Update Form 3File: Mont vert Axis Form 3 30 06 2026 sign.pdf | 10 Aug 2026 |
| Form 2A (FY 2024-2025)File: Form 2A 2024-2025.pdf | 6 Aug 2026 |
| Form 2A (FY 2022-2023)File: Form 2 A 2022-23.pdf | 6 Aug 2026 |
| Form 2A (FY 2023-2024)File: Form 2 A 2023-24.pdf | 6 Aug 2026 |
| Form 5 (FY 2021-2022)File: form 5 202122.pdf | 3 Aug 2026 |
| Form 5 (FY 2022-2023)File: Form 5 fy 22-23 (MONT VERT NEEDS) both sign.pdf | 3 Aug 2026 |
| Form 5 (FY 2023-2024)File: form 5 Mont Vert Axis 31-03-2024.pdf | 3 Aug 2026 |
| Withdrawal Update Form 1File: FORM 1 AXIS June 2026.pdf | 21 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2 AXIS June 2026.pdf | 21 Jul 2026 |
| Withdrawal Update Form 3File: Mont vert Axis Form 3 30 06 2026 sign.pdf | 21 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form 2A Maharera Mont Vert Axis 2025 2026.pdf | 13 May 2026 |
| Withdrawal Update Form 1File: FORM-1 AXIS 31032026.pdf | 4 May 2026 |
| Withdrawal Update Form 2File: FORM-2 AXIS 31032026.pdf | 4 May 2026 |
| Withdrawal Update Form 3File: Mont vert Axis Form 3 31032026 sign.pdf | 4 May 2026 |
| Withdrawal Update Form 1File: FORM 1 NEEDS Dec 205 sign.pdf | 25 Feb 2026 |
| Withdrawal Update Form 2File: FORM 2 NEEDS AXIS 31122025.pdf | 25 Feb 2026 |
| Withdrawal Update Form 3File: Mont vert Axis Form 3 31122025 sign_compressed.pdf | 25 Feb 2026 |
| Withdrawal Update Form 1File: FORM-1 AXIS Arch Sep 2025.pdf | 17 Oct 2025 |
| Withdrawal Update Form 1File: FORM-1 AXIS Arch Sep 2025.pdf | 17 Oct 2025 |
| Withdrawal Update Form 1File: FORM-1 AXIS Arch Sep 2025.pdf | 17 Oct 2025 |
| Withdrawal Update Form 2File: FORM 2 Mont Vert Axis Sep 2025.pdf | 17 Oct 2025 |
| Withdrawal Update Form 2File: FORM 2 Mont Vert Axis Sep 2025.pdf | 17 Oct 2025 |
| Withdrawal Update Form 2File: RERA FORM-2 Mont Vert Axis Sep 2025.pdf | 17 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 Axis Sept 2025 sign.pdf | 17 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 Axis Sept 2025 sign.pdf | 17 Oct 2025 |
| Withdrawal Update Form 3File: Mont vert Axis Form 3 30-09-2025 sign_compressed.pdf | 17 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form 5 Mont Vert Axis FY 2024-2025 sign.pdf | 15 Oct 2025 |
| Withdrawal Update Form 1File: FORM 1 April to June 2025 - 30062025.pdf | 10 Sep 2025 |
| Withdrawal Update Form 2File: FORM-2 AXIS COMM 30-6-2025.pdf | 10 Sep 2025 |
| Withdrawal Update Form 3File: Mont vert Axis Form 3 30-06-2025 sign_compressed.pdf | 10 Sep 2025 |
| Form 1File: Form_01_Mont_Vert_Axis_March_2025.pdf | 5 Sep 2025 |
| Form 2File: FORM-2 AXIS COMMER MARCH 2025.pdf | 5 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Unsold 31032025.pdf | 5 Sep 2025 |
| Form 3File: FORM 3 NEEDS AXIS MARCH 2025.pdf | 5 Sep 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form_01_Mont_Vert_Axis_March_2025.pdf | 11 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 NEEDS AXIS MARCH 2025 (1).pdf | 11 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 AXIS COMMER MARCH 2025.pdf | 11 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold and Unsold Mont Vert Axis March 2025.pdf | 11 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 Most Vert Axis Dec 2024.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Mont Vert Axis Dec 2024.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 2024 Axis.pdf | 4 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Axis Form 2 Dec 2023.pdf | 22 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Axis RERA 2023-2024.pdf | 22 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 RERA Belcreek 2023-2024.pdf | 22 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Axis Dec 2023.pdf | 21 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Axis March 2024.pdf | 21 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Axis June 2024.pdf | 21 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Axis Sept 2024.pdf | 21 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A AXIS 2022-2023.pdf | 21 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold M V NEEDS AXIS 30-6-2024.pdf | 15 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold M V NEEDS AXIS 30-9-2024.pdf | 15 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 Most vert Axis 30-06-2024_compressed.pdf | 13 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Mont Vert Axis 30092024.pdf | 13 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Mont Vert Axis June 2024 ANNEXURE B.pdf | 13 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 AXIS000.pdf | 13 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold 31032024 AXIS.pdf | 20 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Mont Vert Axis 31032024.pdf | 17 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 AXIS.pdf | 17 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 Mont Vert Axis 31-03-2024-both sign-compress.pdf | 17 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 Mont Vet Axis 31122023 both signed_compressed.pdf | 26 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Axis 30-9-23 AXIS.pdf | 6 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Mont Vert Axis Sep 2023.pdf | 10 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Axis Spt 2023_compressed.pdf | 10 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Axis Form 1 Oct 2023.pdf | 6 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annexure F MONT VERT NEEDS.pdf | 6 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 AXIS 30-06-23.pdf | 9 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 AXIS 8-07-23.pdf | 9 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A AXIS 8-07-23.pdf | 9 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-Mont Vert Needs-Mont Vert Axis-both sign compressed.pdf | 9 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Mont Vert Axis Dec 2022 Both sign.pdf | 24 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Mont Vert Axis March 2023 Both sign.pdf | 24 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 M V Axis Mar 23 Qtr.pdf | 18 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 M V Axis Mar 23.pdf | 8 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A M V Axis Mar 23.pdf | 8 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory M V Axis Mar 23.pdf | 8 Apr 2023 |
| Proforma of Agreement for saleFile: Axis agreement draft.pdf | 18 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 2022 mont vert axis Both Sign.pdf | 17 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Mont Vert Needs certificate Form 5 2022.pdf | 17 Feb 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 133 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Mont Vert Axis on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bavdhan13,700+ in Pune
Filed coordinates, straight-line distance. 176 registered projects within 2 km.
NYATI EQUINOX I
MIHIR HOMES ENTERPRISE LLP
Puraniks Abitante Fiore, Phase 2A
Puranik Buildcon Private Limited
Puraniks Abitante Fiore, Phase 2B
Puranik Buildcon Private Limited
cloud 51
OREE REALITY PVT LTD
CIELO BY VTP LUXE
DELAS REALCON LLP
Puraniks Abitante Fiore Phase 2C1
Puranik Buildcon Private Limited
Builder: Mont Vert Needs
Mont Vert Needs has 1 registration on MahaRERA, including Mont Vert Axis. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Mont Vert Axis is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Mont Vert Axis?
The registered promoter entity is Mont Vert Needs, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Mont Vert Axis?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Mont Vert Axis?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Mont Vert Axis?
The professionals named in the filing: Architect: Vikas Achalkar AT consultants; Architect: AKRITI ASSOCIATE; Architect: Shrinivas V Kadkol; Engineer: G V Khasnis; Engineer: Rameshwar Bamodkar; Chartered Accountant: Ganesh Gundecha. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Mont Vert Axis?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback