Home / Browse projects / Pune, Maharashtra / MIravet District Phase - I
MIravet District Phase - I
RG-MH-17501 · RERA P52100030203 · Last updated on MahaRERA portal: 20 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 4 cases
- 3 complaints at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
- Rs 12.00 crore secured on the land, in favour of Godrej Housing Finance Ltd
- The declared charge does not appear in the CERSAI report on the filing
Clear
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
MIravet District Phase - I is a Residential / Group Housing project by AUM DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100030203 on 5 Aug 2021. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 368 of the 406 units on this registration are recorded sold or booked, and 39 of 44 construction stages are filed complete. 3 complaints are on record with the regulator.
At a glance
Project
- NameMIravet District Phase - I
- TypeResidential / Group Housing
- Location
- 45 Mtr BRT Road
- Mhaske Wasti
- Ravet
- Ravet
- Haveli
- Pune
- 412101
- Pincode412101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100030203
- ReraGenie IDRG-MH-17501
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on5 Aug 2021
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
- Buildings4 building records
- Documents filed178 files
Current status
Figures as on 20 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | NA | 24 | 24 | 154 | 0 | 154 |
| Wing - C | NA | 18 | 18 | 70 | 0 | 70 |
| Wing - B | NA | 18 | 18 | 70 | 0 | 70 |
| Wing - D | NA | 18 | 18 | 112 | 0 | 112 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
39 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 90%.
WING A96%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 70% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing - C91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing - B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing - D91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed1029
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| WING A | 432 | 432 |
| Wing - C | 167 | 167 |
| Wing - B | 167 | 167 |
| Wing - D | 263 | 263 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| WING A | NA | Rs 64.21 cr | Rs 36.65 cr |
| Wing - D | NA | Rs 39.32 cr | Rs 39.32 cr |
| Wing - B | NA | Rs 24.97 cr | Rs 24.97 cr |
| Wing - C | NA | Rs 24.82 cr | Rs 24.82 cr |
| - | NA | Rs 10.20 cr | Rs 3.60 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Prakash Kulkarni |
| Engineer | Suraj Patil |
| Chartered Accountant | A N J K & CO LLP |
| Chartered Accountant | RV Nevatia & Co |
| Chartered Accountant | Yashkumar Santosh Soni |
| Partner | Role in project |
|---|---|
| AUM DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe hereby request an extension of the project timeline under RERA due to unforeseen delays caused by a shortage of both skilled labour and essential construction materials. Over the past few months, our project has faced significant disruptions in workforce availability, which has slowed down on-site progress of Wing A. Additionally, the supply chain for critical raw materials such as cement and steel has been inconsistent, leading to delays in procurement and execution of key construction activities. We would like to mention that we have received Part Occupancy Certificate dated 28/11/2024 fo
Litigation declared4
| Case | Court | Status |
|---|---|---|
| 1484/2012 | CIVIL JUDGE SENIOR DIVISION | Argument on Exh Unready |
| 13/2020 | DISTRICT AND SESSION COURT PUNE | steps unready |
| 1344/2026 | civil judge senior Division | Ongoing |
| 2/2015 | civil judge junior division | Ongoing |
Complaints filed with MahaRERA3
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000116928 | VAISHALI BALASAHEB WAGHERE | M/s. A.U.M.Developers Thr.its Partner a)Mr.Shrichand Aswani b)Mr.Dhanjibhai Kabaria c)Mr.Anil Aswani | 19/04/2022 |
| CC005000000116953 | Pallavi Pravin Shinde | M/S. Aum Developers | 03/07/2022 |
| CC005000000147219 | santosh shankar sathe | ASWANI PROMOTERS AND BUILDERS PRIVATE LIMITED | 11/06/2022 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Mar 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Jun 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed178
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 178 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Withdrawal Application Form1.pdf | 20 Jul 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2.pdf | 20 Jul 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form3.pdf | 20 Jul 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form 1.pdf | 20 Apr 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2.pdf | 20 Apr 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form 3.pdf | 20 Apr 2026 |
| Form 2A (FY 2025-2026)File: Form 2A Quality Assurance Certificate.pdf | 20 Apr 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1.pdf | 27 Jan 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2.pdf | 27 Jan 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form3.pdf | 27 Jan 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1_Signed.pdf | 28 Nov 2025 |
| Withdrawal Update Form 2File: Withdrawal Application Form2_Signed.pdf | 28 Nov 2025 |
| Withdrawal Update Form 3File: Withdrawal Application Form3_Signed.pdf | 28 Nov 2025 |
| Form 2A (FY 2024-2025)File: Form 2A Quality Assurance Certificate.pdf | 28 Nov 2025 |
| Form 5 (FY 2024-2025)File: CA Form 5_FY 2024-25_Miravet District Phase I_Signed.pdf | 17 Nov 2025 |
| Withdrawal Update Form 1File: ARCHITECTS CERTIFICATE-FORM-1.pdf | 3 Sep 2025 |
| Withdrawal Update Form 2File: ENGINEERu0027S CERTI FICATE-FORM-2 _.pdf | 3 Sep 2025 |
| Withdrawal Update Form 3File: CA CERTIFICATE-FORM-3_.pdf | 3 Sep 2025 |
| Form 1File: Form 1 Architect Certificate Dec 2024.pdf | 25 Jun 2025 |
| Form 2File: Form 2 Engineer Certificate December 2024 signed.pdf | 25 Jun 2025 |
| Form 3File: CA Certificate Miravet Phase 1 - Dec 2024 signed.pdf | 25 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory - Dec 2024.pdf | 25 Jun 2025 |
| Form 1File: Form 1 March 2025 signed.pdf | 25 Jun 2025 |
| Form 2File: Form 2 Engineer Certificate March 2025 signed.pdf | 25 Jun 2025 |
| Form 3File: CA Certificate Miravet Phase 1 - March 2025 signed.pdf | 25 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory - March 2025.pdf | 25 Jun 2025 |
| Withdrawal Update Form 1File: Form 1 March 2025 signed.pdf | 25 Jun 2025 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate March 2025 signed.pdf | 25 Jun 2025 |
| Withdrawal Update Form 3File: CA Certificate Miravet Phase 1 - March 2025 signed.pdf | 25 Jun 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Form 5 Miravet District Phase I.pdf | 26 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate Sept 2024.pdf | 30 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate New Format - Sept 2024 - Sign.pdf | 30 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate Sept 2024.pdf | 30 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - Sept 2024.pdf | 30 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate June 2024.pdf | 6 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate June 2024.pdf | 6 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - June 2024.pdf | 6 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate - June 2024.pdf | 6 Aug 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration Format A on Separate bank account.pdf | 1 Jul 2024 |
| Building plan approvalFile: 11.pdf | 26 Jun 2024 |
| Building plan approvalFile: 12.pdf | 26 Jun 2024 |
| Building plan approvalFile: 13.pdf | 26 Jun 2024 |
| Building plan approvalFile: 14.pdf | 26 Jun 2024 |
| Building plan approvalFile: 15.pdf | 26 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 11.pdf | 26 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 12.pdf | 26 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 13.pdf | 26 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 14.pdf | 26 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 15.pdf | 26 Jun 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 26 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Quality Assurance Certificate.pdf | 26 Jun 2024 |
| Other - TechnicalFile: Land Area Declaration Merged.pdf | 26 Jun 2024 |
| Declaration about Commencement CertificateFile: CC Declaration-scanned.pdf | 21 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate June 2023.pdf | 21 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate December 2023.pdf | 21 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate March 2024.pdf | 21 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Form 2 Engineer Certificate June 2023.pdf | 21 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form 2 Engineer Certificate September 2023.pdf | 21 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3Form 2 Engineer Certificate December 2023.pdf | 21 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 Form 2 Engineer Certificate March 2024.pdf | 21 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - December 2022_11zon.pdf | 21 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - March 2023_11zon.pdf | 21 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - June 2023_11zon.pdf | 21 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - September 2023_11zon.pdf | 21 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - December 2023_11zon.pdf | 21 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - March 2024_11zon.pdf | 21 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Signed.pdf | 21 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate - December 2023_11zon.pdf | 21 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate - March 2024_11zon.pdf | 21 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 21-22.pdf | 21 Jun 2024 |
| Layout approvalFile: 1.pdf | 24 Mar 2024 |
| Building plan approvalFile: 2.pdf | 24 Mar 2024 |
| Building plan approvalFile: 3.pdf | 24 Mar 2024 |
| Building plan approvalFile: 4.pdf | 24 Mar 2024 |
| Building plan approvalFile: 5.pdf | 24 Mar 2024 |
| Building plan approvalFile: 6.pdf | 24 Mar 2024 |
| Building plan approvalFile: 7.pdf | 24 Mar 2024 |
| Building plan approvalFile: 8.pdf | 24 Mar 2024 |
| Building plan approvalFile: 9.pdf | 24 Mar 2024 |
| Building plan approvalFile: 10.pdf | 24 Mar 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| ASWANI GREEN VALLEY | WAKAD | 179 | Completed | Oct 2017 | Oct 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 6 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 5 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 178 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep MIravet District Phase - I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mhaske Wasti, Ravet13,700+ in Pune
Filed coordinates, straight-line distance. 194 registered projects within 2 km.
Godrej Park Greens
Godrej Skyline Developers Limited
FOREST GROVE AT GODREJ PARK GREENS
Godrej Skyline Developers Limited
Om Mangalam Samruddhi
NDG Homes LLP
PCMC EWS KIWALE
Pimpri Chinchwad Municipal Corporation
Godrej Nurture
Godrej Skyline Developers Limited
My Home Sanctuary Phase I
MAMURDI DEVELOPERS LLP
Builder: AUM DEVELOPERS
AUM DEVELOPERS has 6 registrations on MahaRERA, including RADHAKUNJ CHS and Valley Vista. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if MIravet District Phase - I is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of MIravet District Phase - I?
The registered promoter entity is AUM DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in MIravet District Phase - I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against MIravet District Phase - I?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for MIravet District Phase - I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at MIravet District Phase - I?
The professionals named in the filing: Architect: Prakash Kulkarni; Engineer: Suraj Patil; Chartered Accountant: A N J K & CO LLP; Chartered Accountant: RV Nevatia & Co; Chartered Accountant: Yashkumar Santosh Soni. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MIravet District Phase - I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback