Home / Browse projects / Pune, Maharashtra / MIravet District Phase - I

Registered Litigation declared Residential / Group Housing project

MIravet District Phase - I

By AUM DEVELOPERS

RG-MH-17501 · RERA P52100030203 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 4 cases
  • 3 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken
  • Rs 12.00 crore secured on the land, in favour of Godrej Housing Finance Ltd
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
39 of 44Construction stages doneacross 4 buildings; furthest along: Staircases, 90%
38 of 406Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 178 documents Report an error

MIravet District Phase - I is a Residential / Group Housing project by AUM DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100030203 on 5 Aug 2021. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 368 of the 406 units on this registration are recorded sold or booked, and 39 of 44 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameMIravet District Phase - I
  • TypeResidential / Group Housing
  • Location
    • 45 Mtr BRT Road
    • Mhaske Wasti
    • Ravet
    • Ravet
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100030203
  • ReraGenie IDRG-MH-17501

Builder

  • NameAUM DEVELOPERS
  • Entity typePartnership
  • PartnersANIL SHAMANDAS ASWANI, SHRICHAND SHANMANDAS ASWANI
  • Other registrations5 more →
  • Completed3 of 6
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2021First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on5 Aug 2021
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
  • Buildings4 building records
  • Documents filed178 files

Current status

91%368 of 406 units booked
79.1%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA24241540154
Wing - CNA181870070
Wing - BNA181870070
Wing - DNA18181120112

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

39 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 90%.

WING A96%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing - C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing - B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing - D91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed1029

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1,029
Closed/Covered1,029
BuildingClosed/CoveredTotal
WING A432432
Wing - C167167
Wing - B167167
Wing - D263263

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area13,267 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofGodrej Housing Finance Ltd
Secured amountRs 12.00 crore
CERSAI search filedYes
Declared on7 Mar 2026

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Muncipal Corporation
Permissible FSI46379.44
Proposed, not sanctioned46,379 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNEAR GANESH HOTEL PIMPRI, PUNE-17
Estimated costRs 163.52 cr
Cost incurredRs 129.36 cr
Work done79.11%
BuildingWingEstimatedIncurred
WING ANARs 64.21 crRs 36.65 cr
Wing - DNARs 39.32 crRs 39.32 cr
Wing - BNARs 24.97 crRs 24.97 cr
Wing - CNARs 24.82 crRs 24.82 cr
-NARs 10.20 crRs 3.60 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPrakash Kulkarni
EngineerSuraj Patil
Chartered AccountantA N J K & CO LLP
Chartered AccountantRV Nevatia & Co
Chartered AccountantYashkumar Santosh Soni
PartnerRole in project
AUM DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA15072502073Dec 2025 → Dec 2026

Reason as filed by the promoterWe hereby request an extension of the project timeline under RERA due to unforeseen delays caused by a shortage of both skilled labour and essential construction materials. Over the past few months, our project has faced significant disruptions in workforce availability, which has slowed down on-site progress of Wing A. Additionally, the supply chain for critical raw materials such as cement and steel has been inconsistent, leading to delays in procurement and execution of key construction activities. We would like to mention that we have received Part Occupancy Certificate dated 28/11/2024 fo

Litigation declared4

CaseCourtStatus
1484/2012CIVIL JUDGE SENIOR DIVISIONArgument on Exh Unready
13/2020DISTRICT AND SESSION COURT PUNEsteps unready
1344/2026civil judge senior DivisionOngoing
2/2015civil judge junior divisionOngoing

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC005000000116928VAISHALI BALASAHEB WAGHEREM/s. A.U.M.Developers Thr.its Partner a)Mr.Shrichand Aswani b)Mr.Dhanjibhai Kabaria c)Mr.Anil Aswani19/04/2022
CC005000000116953Pallavi Pravin ShindeM/S. Aum Developers03/07/2022
CC005000000147219santosh shankar satheASWANI PROMOTERS AND BUILDERS PRIVATE LIMITED11/06/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Jun 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed178

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 178 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Withdrawal Application Form1.pdf20 Jul 2026
Withdrawal Update Form 2File: Withdrawal Application Form2.pdf20 Jul 2026
Withdrawal Update Form 3File: Withdrawal Application Form3.pdf20 Jul 2026
Withdrawal Update Form 1File: Withdrawal Application Form 1.pdf20 Apr 2026
Withdrawal Update Form 2File: Withdrawal Application Form2.pdf20 Apr 2026
Withdrawal Update Form 3File: Withdrawal Application Form 3.pdf20 Apr 2026
Form 2A (FY 2025-2026)File: Form 2A Quality Assurance Certificate.pdf20 Apr 2026
Withdrawal Update Form 1File: Withdrawal Application Form1.pdf27 Jan 2026
Withdrawal Update Form 2File: Withdrawal Application Form2.pdf27 Jan 2026
Withdrawal Update Form 3File: Withdrawal Application Form3.pdf27 Jan 2026
Withdrawal Update Form 1File: Withdrawal Application Form1_Signed.pdf28 Nov 2025
Withdrawal Update Form 2File: Withdrawal Application Form2_Signed.pdf28 Nov 2025
Withdrawal Update Form 3File: Withdrawal Application Form3_Signed.pdf28 Nov 2025
Form 2A (FY 2024-2025)File: Form 2A Quality Assurance Certificate.pdf28 Nov 2025
Form 5 (FY 2024-2025)File: CA Form 5_FY 2024-25_Miravet District Phase I_Signed.pdf17 Nov 2025
Withdrawal Update Form 1File: ARCHITECTS CERTIFICATE-FORM-1.pdf3 Sep 2025
Withdrawal Update Form 2File: ENGINEERu0027S CERTI FICATE-FORM-2 _.pdf3 Sep 2025
Withdrawal Update Form 3File: CA CERTIFICATE-FORM-3_.pdf3 Sep 2025
Form 1File: Form 1 Architect Certificate Dec 2024.pdf25 Jun 2025
Form 2File: Form 2 Engineer Certificate December 2024 signed.pdf25 Jun 2025
Form 3File: CA Certificate Miravet Phase 1 - Dec 2024 signed.pdf25 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory - Dec 2024.pdf25 Jun 2025
Form 1File: Form 1 March 2025 signed.pdf25 Jun 2025
Form 2File: Form 2 Engineer Certificate March 2025 signed.pdf25 Jun 2025
Form 3File: CA Certificate Miravet Phase 1 - March 2025 signed.pdf25 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory - March 2025.pdf25 Jun 2025
Withdrawal Update Form 1File: Form 1 March 2025 signed.pdf25 Jun 2025
Withdrawal Update Form 2File: Form 2 Engineer Certificate March 2025 signed.pdf25 Jun 2025
Withdrawal Update Form 3File: CA Certificate Miravet Phase 1 - March 2025 signed.pdf25 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Form 5 Miravet District Phase I.pdf26 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate Sept 2024.pdf30 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate New Format - Sept 2024 - Sign.pdf30 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate Sept 2024.pdf30 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - Sept 2024.pdf30 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate June 2024.pdf6 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate June 2024.pdf6 Aug 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - June 2024.pdf6 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate - June 2024.pdf6 Aug 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration Format A on Separate bank account.pdf1 Jul 2024
Building plan approvalFile: 11.pdf26 Jun 2024
Building plan approvalFile: 12.pdf26 Jun 2024
Building plan approvalFile: 13.pdf26 Jun 2024
Building plan approvalFile: 14.pdf26 Jun 2024
Building plan approvalFile: 15.pdf26 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: 11.pdf26 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: 12.pdf26 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: 13.pdf26 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: 14.pdf26 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: 15.pdf26 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf26 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Quality Assurance Certificate.pdf26 Jun 2024
Other - TechnicalFile: Land Area Declaration Merged.pdf26 Jun 2024
Declaration about Commencement CertificateFile: CC Declaration-scanned.pdf21 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate June 2023.pdf21 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate December 2023.pdf21 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate March 2024.pdf21 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Form 2 Engineer Certificate June 2023.pdf21 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form 2 Engineer Certificate September 2023.pdf21 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3Form 2 Engineer Certificate December 2023.pdf21 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 Form 2 Engineer Certificate March 2024.pdf21 Jun 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - December 2022_11zon.pdf21 Jun 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - March 2023_11zon.pdf21 Jun 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - June 2023_11zon.pdf21 Jun 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - September 2023_11zon.pdf21 Jun 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - December 2023_11zon.pdf21 Jun 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - March 2024_11zon.pdf21 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Signed.pdf21 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate - December 2023_11zon.pdf21 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate - March 2024_11zon.pdf21 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 21-22.pdf21 Jun 2024
Layout approvalFile: 1.pdf24 Mar 2024
Building plan approvalFile: 2.pdf24 Mar 2024
Building plan approvalFile: 3.pdf24 Mar 2024
Building plan approvalFile: 4.pdf24 Mar 2024
Building plan approvalFile: 5.pdf24 Mar 2024
Building plan approvalFile: 6.pdf24 Mar 2024
Building plan approvalFile: 7.pdf24 Mar 2024
Building plan approvalFile: 8.pdf24 Mar 2024
Building plan approvalFile: 9.pdf24 Mar 2024
Building plan approvalFile: 10.pdf24 Mar 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
ASWANI GREEN VALLEYWAKAD179CompletedOct 2017Oct 2017

How this compares with Pune

91%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MIravet District Phase - I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mhaske Wasti, Ravet13,700+ in Pune

2 kmMIravet District Phase -Completed 80Lapsed / revoked 40Other 74Dot size: filed unitsN

Filed coordinates, straight-line distance. 194 registered projects within 2 km.

Builder: AUM DEVELOPERS

AUM DEVELOPERS has 6 registrations on MahaRERA, including RADHAKUNJ CHS and Valley Vista. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if MIravet District Phase - I is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MIravet District Phase - I?

The registered promoter entity is AUM DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MIravet District Phase - I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MIravet District Phase - I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MIravet District Phase - I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MIravet District Phase - I?

The professionals named in the filing: Architect: Prakash Kulkarni; Engineer: Suraj Patil; Chartered Accountant: A N J K & CO LLP; Chartered Accountant: RV Nevatia & Co; Chartered Accountant: Yashkumar Santosh Soni. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MIravet District Phase - I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MIravet District Phase - I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MIravet District Phase - I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.