Home / Browse projects / Pune, Maharashtra / Midori Towers
Midori Towers
RG-MH-75933 · RERA P52100047310 · Last updated on MahaRERA portal: 22 Dec 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 24 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Midori Towers is a Residential / Group Housing project by Saikrushna Developers in Pune, Maharashtra, registered with MahaRERA as P52100047310 on 19 Oct 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 42 of the 65 units on this registration are recorded sold or booked, and 8 of 22 construction stages are filed complete.
At a glance
Project
- NameMidori Towers
- TypeResidential / Group Housing
- Location
- 13/1A/1 Sai Nagar
- Mamurdi
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 412101
- Pincode412101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100047310
- ReraGenie IDRG-MH-75933
Builder
- NameSaikrushna Developers
- Entity typePartnership
- PartnersDIPAK SAHEBRAO WAGH, TUKARAM SUBASH JADHAV
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on19 Oct 2022
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2024)
- Buildings2 building records
- Documents filed67 files
Current status
Figures as on 22 Dec 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Midori Tower A wing | NA | 8 | 8 | 32 | 5 | 37 |
| Midori Tower B wing | NA | 8 | 0 | 28 | 0 | 28 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 22 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 90%.
Midori Tower A wing51%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 75% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 45% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 40% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Midori Tower B wing72%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 90% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
Progress on shared amenities15
As on 22 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 80% |
| Electrical meter room, sub-station, receiving station | Yes | 20% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed26
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| Midori Tower A wing | 13 | 13 |
| Midori Tower B wing | 13 | 13 |
Land and ownership4
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Faizal Abdul Hamid Shaikh | Mamurdi | Pune |
| Abdul Gani Abdul Wahid Khan | Mamurdi | Pune |
| Abdul Waddu Abdul Wahid Khan | Mamurdi | Pune |
| Hamidabanu Nijamuddin Shaikh | Mamurdi | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Midori Tower A wing | NA | Rs 10.85 cr | Rs 8.26 cr |
| Midori Tower B wing | NA | Rs 10.85 cr | Rs 8.26 cr |
| - | NA | Rs 50.00 lakh | Rs 28.00 lakh |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Madhura Parag Merukar |
| Architect | Vastushree Architect |
| Engineer | Akshay A Wadkar |
| Engineer | Prasad Jadhav |
| Engineer | Vikas Bhimrao Patil |
| Engineer | Sandeep Suresh Dhumal |
| Chartered Accountant | Anant Dingare |
| Chartered Accountant | A A Dhingare & Co |
| Partner | Role in project |
|---|---|
| Saikrushna Developers | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work Given the circumstances, we kindly request an extension until 31/12/2025 to complete the project and fulfil all regulatory requirements
Reason as filed by the promoterWe request an extension of the project registration as the construction work is almost completed except minor finishing work and only closure formalities remain. The conveyance deed, society formation, and completion certificate processes are currently under progress with the concerned authorities. Additional time is required to finalize these statutory requirements and upload the necessary documents on the RERA portal. We assure completion at the earliest.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 9 Aug 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 7 Jan 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Jun 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 13 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed67
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 Sep 25 Signed_compressed (1).pdf | 22 Dec 2025 |
| Form 2File: Form 2 Sep 25 Signed_compressed.pdf | 22 Dec 2025 |
| Form 3File: Form 3 Sep 25 Signed_compressed.pdf | 22 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Cicular 29.pdf | 22 Dec 2025 |
| Withdrawal Update Form 1File: Form 1 Sep 25 Signed_compressed (1).pdf | 22 Dec 2025 |
| Withdrawal Update Form 1File: Form 1 Sep 25 Signed_compressed (1).pdf | 22 Dec 2025 |
| Withdrawal Update Form 2File: Form 2 Sep 25 Signed_compressed.pdf | 22 Dec 2025 |
| Withdrawal Update Form 2File: Form 2 Sep 25 Signed_compressed.pdf | 22 Dec 2025 |
| Withdrawal Update Form 3File: Form 3 Sep 25 Signed_compressed.pdf | 22 Dec 2025 |
| Withdrawal Update Form 3File: Form 3 Sep 25 Signed_compressed.pdf | 22 Dec 2025 |
| Declaration in FORM BFile: Form B.pdf | 13 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 2024.pdf | 13 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 2024.pdf | 13 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec 2024.pdf | 13 Jan 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Fromat D.pdf | 13 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Circular 29.pdf | 13 Jan 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf | 13 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2022-23.pdf | 13 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022-23.pdf | 13 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2023-24.pdf | 13 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24.pdf | 13 Jan 2025 |
| Layout approvalFile: A_merged_11zon.pdf | 7 Jan 2025 |
| Layout approvalFile: A.pdf | 7 Jan 2025 |
| Layout approvalFile: HPSC0138_compressed.pdf | 7 Jan 2025 |
| Layout approvalFile: abb_rotated (1).pdf | 7 Jan 2025 |
| Layout approvalFile: AB.pdf | 7 Jan 2025 |
| Copy of Layout Approval (in case of layout)File: A.pdf | 7 Jan 2025 |
| Copy of Layout Approval (in case of layout)File: HPSC0138_compressed.pdf | 7 Jan 2025 |
| Copy of Layout Approval (in case of layout)File: abb_rotated (1).pdf | 7 Jan 2025 |
| Copy of Layout Approval (in case of layout)File: AB.pdf | 7 Jan 2025 |
| Copy of Layout Approval (in case of layout)File: A_merged_11zon.pdf | 7 Jan 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: 20241220075022 (1)_rotated_11zon (1).pdf | 7 Jan 2025 |
| Layout approvalFile: imgw-410161015.pdf | 20 Apr 2024 |
| Layout approvalFile: imgw-410160917 (1).pdf | 20 Apr 2024 |
| Layout approvalFile: imgw-410160847 (1).pdf | 20 Apr 2024 |
| Layout approvalFile: imgw-410160944 (1).pdf | 20 Apr 2024 |
| Copy of Layout Approval (in case of layout)File: imgw-410161015.pdf | 20 Apr 2024 |
| Copy of Layout Approval (in case of layout)File: imgw-410160917 (1).pdf | 20 Apr 2024 |
| Copy of Layout Approval (in case of layout)File: imgw-410160847 (1).pdf | 20 Apr 2024 |
| Copy of Layout Approval (in case of layout)File: imgw-410160944 (1).pdf | 20 Apr 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: doc07949920240410202917.pdf | 20 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SAIKRUSHNA DEVELOPERS ARCHITECT CERTIFICATE.pdf | 15 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SAIKRUSHNA DEVELOPERS ENGINEER CERTIFICATE_compressed.pdf | 15 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SAIKRUSHNA DEVELOPERS CA CERTIFICATE_compressed.pdf | 15 Mar 2023 |
| Other - LegalFile: Court Order 02.pdf | 15 Mar 2023 |
| Other - LegalFile: SAIKRUSHNA DEVELOPERS COURT CASE_compressed.pdf | 15 Mar 2023 |
| Other - LegalFile: Case PCMC Order 01.pdf | 15 Mar 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation 14_10_22.pdf | 14 Oct 2022 |
| Other - LegalFile: FINAl AFS 14_10_22.pdf | 14 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: organized (14)_compressed.pdf | 3 Oct 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200248675191_For_Asset_Based_Search_01_10_2022_13_01_18_801.pdf | 1 Oct 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Midori -Formmat A.pdf | 1 Oct 2022 |
| Copy of the legal title reportFile: LEGAL TILTLE REPORT SAIKRUSHNA DEVELOPERS 22-23 (1).pdf | 9 Aug 2022 |
| Declaration about Commencement CertificateFile: CC DECLARATION.pdf | 9 Aug 2022 |
| Proforma of Allotment letterFile: Proforma_Allotement_Letter.pdf | 9 Aug 2022 |
| Deviation Report with respect to Allotment letterFile: No_Deviation_Allotment_and_AgreementForSale.pdf | 9 Aug 2022 |
| Details of encumbrances concerned to LegalFile: Encumbrances_Concened_Legal.pdf | 4 Jul 2022 |
| Details of encumbrancesFile: Saikrushna Encumbrances.pdf | 20 Jun 2022 |
| Declaration in FORM BFile: Saikrushna_Developers_Affidavit cum Declaration (1).pdf | 20 Jun 2022 |
| Layout approvalFile: Saikrushna Plan1.pdf | 3 Jun 2022 |
| Layout approvalFile: Saikrushna Plan 2.pdf | 3 Jun 2022 |
| Building plan approvalFile: Saikrushna NA order (1).pdf | 3 Jun 2022 |
| PAN CardFile: Saikrushna_Developers_PAN_Card.pdf | 3 Jun 2022 |
| Copy of Layout Approval (in case of layout)File: Saikrushna Plan1.pdf | 3 Jun 2022 |
| Copy of Layout Approval (in case of layout)File: Saikrushna Plan 2.pdf | 3 Jun 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Saikrushna NA order (1).pdf | 3 Jun 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement_Certificate_2022.pdf | 3 Jun 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 67 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Midori Towers on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mamurdi13,700+ in Pune
Filed coordinates, straight-line distance. 228 registered projects within 2 km.
Godrej Park Greens
Godrej Skyline Developers Limited
FOREST GROVE AT GODREJ PARK GREENS
Godrej Skyline Developers Limited
Om Mangalam Samruddhi
NDG Homes LLP
PCMC EWS KIWALE
Pimpri Chinchwad Municipal Corporation
Godrej Nurture
Godrej Skyline Developers Limited
My Home Sanctuary Phase I
MAMURDI DEVELOPERS LLP
Builder: Saikrushna Developers
Saikrushna Developers has 1 registration on MahaRERA, including Midori Towers. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Midori Towers is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Midori Towers?
The registered promoter entity is Saikrushna Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Midori Towers?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Midori Towers?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Midori Towers?
The professionals named in the filing: Architect: Madhura Parag Merukar; Architect: Vastushree Architect; Engineer: Akshay A Wadkar; Engineer: Prasad Jadhav; Engineer: Vikas Bhimrao Patil; Engineer: Sandeep Suresh Dhumal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Midori Towers?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback