Home / Browse projects / Thane, Maharashtra / MAULI ANGAN

Registration lapsed No litigation declared Residential / Group Housing project

MAULI ANGAN

By MAULI ENTERPRISES

RG-MH-69507 · RERA P51700033171 · Last updated on MahaRERA portal: 9 Jul 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 19 months past the filed date
  • Completion date moved by 15 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2025Possession promised19 months past this date
20 of 44Construction stages doneacross 4 buildings; furthest along: Internal walls, 75%
0Complaints at MahaRERAon this registration
Jump to the 32 documents Report an error

MAULI ANGAN is a Residential / Group Housing project by MAULI ENTERPRISES in Thane, Maharashtra, registered with MahaRERA as P51700033171 on 9 Feb 2022. Possession was promised by 31 Mar 2025 and is now 19 months past that date. The completion date has moved by 15 months from the original filing.

At a glance

Project

  • NameMAULI ANGAN
  • TypeResidential / Group Housing
  • Location
    • MOUJE MANGAON
    • MANGAON
    • Kalyan
    • Thane
    • 421204
  • Pincode421204
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700033171
  • ReraGenie IDRG-MH-69507

Builder

  • NameMAULI ENTERPRISES
  • Entity typePartnership
  • GSTIN27ABHFM8214E1ZB
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersDILIP BHAGAJI VAZE, KRISHNA L BHOIR, NILESH NIVRUTI MHATRE, BHANUDAS BALARAM PATIL, JANARDHAN YASHWANT BHOIR, TANAJI BALARAM PATIL
  • Other registrations3 more →
  • Completed2 of 4
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

19 months past promisethis monthRegisteredFeb 2022First promiseDec 2023Revised toMar 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Feb 2022
  • Promised completion31 Mar 2025
  • Revised completionRevised to 31 Mar 2025 (originally 31 Dec 2023)
  • Buildings4 building records
  • Documents filed32 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WING - UPTO 4TH FLOORNA50000
B WING - UPTO 4TH FLOORNA50000
A WING - 5TH TO 8TH FLOORNA40000
B WING - 5TH TO 8TH FLOORNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 9 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 75%.

A WING - UPTO 4TH FLOOR62%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
B WING - UPTO 4TH FLOOR62%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
A WING - 5TH TO 8TH FLOOR62%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
B WING - 5TH TO 8TH FLOOR62%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities16

As on 9 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes25%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%
ONE SOCIETY OFFICE COMMON TOILET AND COMMON ENTRANCE LOBBYYes50%

Parking filed12

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots12
Open Space12
BuildingOpen SpaceTotal
A WING - UPTO 4TH FLOOR66
B WING - UPTO 4TH FLOOR66

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,300 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
DINESH RAMSUNDER VISHWAKARMADOMBIVLIThane
ARVIND LALBAHADUR YADAVDOMBIVLIThane
GIRISH BANKELAL AGARWALDOMBIVLIThane
CHATRAPATI P KOLIDOMBIVLIThane

Approvals and building plan

Permissible FSI2282.4
Proposed, not sanctioned1,196 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NOS 1, 2,3,4 AND 5 GROUND FLOOR GOPAL NAGAR S NO 30 2 PLOT NO 6, MIDC ROAD, KARTAP, BADLAPUR

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr.Tibin Tonson Thomas partner of M/s. Shalom Consultants
EngineerMANOHAR PATIL
Chartered AccountantVipul Jain of Ms J Vipul & Associates
PartnerRole in project
MAULI ENTERPRISES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700019684Dec 2023 → Mar 2025

Reason as filed by the promoterDue to delay in Planning and material availability

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jan 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Jan 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Jul 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed32

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Building plan approvalFile: Mauli Plan 001 Compressed.pdf9 Jul 2024
Building plan approvalFile: Mauli Plan 002 Compressed.pdf9 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: Mauli Plan 001 Compressed.pdf9 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: Mauli Plan 002 Compressed.pdf9 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: Mauli Ent 20240129201538 CC.pdf9 Jul 2024
Declaration in FORM BFile: Form B_CoPromoter_compressed.pdf29 Apr 2024
Declaration in FORM BFile: Form B _Promoter.pdf29 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_compressed.pdf29 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Signed Final.pdf29 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Signed Final_compressed.pdf29 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf28 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 (1).pdf28 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 A.pdf28 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf28 Nov 2022
CERSAI detailsFile: CERSAI Undertaking.pdf3 Feb 2022
Declaration about Commencement CertificateFile: Updated CC Declaration.pdf31 Jan 2022
Declaration in FORM BFile: Promoter Form B.pdf31 Jan 2022
OtherFile: Updated CC Declaration.pdf31 Jan 2022
Proforma of Allotment letterFile: Allotment Letter Draft.pdf18 Jan 2022
Layout approvalFile: PLAN COPY.pdf17 Jan 2022
Building plan approvalFile: PLAN COPY.pdf17 Jan 2022
PAN CardFile: PAN Card.pdf17 Jan 2022
Copy of the legal title reportFile: LEGAL TITLE PART 1.pdf17 Jan 2022
Copy of the legal title reportFile: LEGAL TITLE PART 2.pdf17 Jan 2022
Details of encumbrancesFile: NO ENCUMBRANCE DECLARATION.pdf17 Jan 2022
Copy of Layout Approval (in case of layout)File: PLAN COPY.pdf17 Jan 2022
Building Plan Approval / NA Order for plotted developmentFile: PLAN COPY.pdf17 Jan 2022
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf17 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf17 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf17 Jan 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf17 Jan 2022
Proforma of Allotment letterFile: DRAFT AGREEMENT (1).pdf17 Jan 2022

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 15 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MAULI ANGAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MANGAON7,600+ in Thane

2 kmMAULI ANGANCompleted 11Lapsed / revoked 6Other 31Dot size: filed unitsN

Filed coordinates, straight-line distance. 48 registered projects within 2 km.

Builder: MAULI ENTERPRISES

Mauli Enterprises has 4 registrations on MahaRERA, including Mauli Residency and Sopan Residency. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that MAULI ANGAN shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MAULI ANGAN is delayed beyond 31 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MAULI ANGAN?

The registered promoter entity is MAULI ENTERPRISES, a partnership as per the filing. Its GSTIN 27ABHFM8214E1ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MAULI ANGAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MAULI ANGAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MAULI ANGAN?

The professionals named in the filing: Architect: Mr.Tibin Tonson Thomas partner of M/s. Shalom Consultants; Engineer: MANOHAR PATIL; Chartered Accountant: Vipul Jain of Ms J Vipul & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAULI ANGAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAULI ANGAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAULI ANGAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.